Tuesday, 19, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Pearl Corporation vs Wbphidcl & Ors
2022 Latest Caselaw 2716 Cal/2

Citation : 2022 Latest Caselaw 2716 Cal/2
Judgement Date : 11 November, 2022

Calcutta High Court
Pearl Corporation vs Wbphidcl & Ors on 11 November, 2022
 ORDER                                                                 OD-5
                             APOT/176/2022
                             WPO/2335/2022
                            IA NO.GA/1/2022
                               GA/2/2022

                   IN THE HIGH COURT AT CALCUTTA
                    CIVIL APPELLATE JURISDICTION
                            ORIGINAL SIDE


                          PEARL CORPORATION
                                VERSUS
                           WBPHIDCL & ORS.



BEFORE:
THE HON'BLE CHIEF JUSTICE PRAKASH SHRIVASTAVA
THE HON'BLE JUSTICE RAJARSHI BHARADWAJ
DATE : 11TH NOVEMBER, 2022


                                                                   APPEARANCE:
                                                         Mr. Tapas Dutta, Advocate
                                                               ......for the appellant
                                                        Mr. Sayan Sinha, Advocate
                                                            Mr. Adil Nasir, Advocate
                                                        Steven S. Biswas, Advocate
                                                     ... for the respondents 1, 2 & 3

Mr. Debasish Ghosh, Advocate Mr. Sayan Ganguly, Advocate ....for the State

The Court:- By this intra-Court appeal, the writ petitioner has

challenged the order of the learned Single Judge dated 23rd August, 2022

whereby GA/3/2022 for interim stay has been rejected.

The appellant had approached the writ Court with the plea that it

was awarded the contract for renovation and up-gradation of Headquarters of

Traffic Guard of Kolkata Police at Brabourne Road, Kolkata and that the initial

period for completion of the work was 365 days. The work could not be

completed. Therefore, twice extension was granted and as per the last

extension, the work was to be completed by 2nd June, 2022. According to the

appellant, there was delay on the part of the respondents in handing over the

site and clearing the bills, therefore, the work could not be completed.

Meanwhile, the contract was terminated vide communication dated 29th

March, 2022. Hence, the appellant had made a prayer in the writ petition to

set aside the termination notice dated 29th March, 2022 and also sought a

direction on the respondents to make payment of the bill dated 31st March,

2022. In the pending writ petition, GA/3/2022 was filed seeking stay of the

work order dated 24th June, 2022 which was issued in favour of the third

party. The stay application was rejected by the impugned order.

The submission of the learned counsel for the appellant is that the

contract contains the penalty clause but the said clause was not invoked

before termination of the contract. It also provides for compensation for delay

that was also not invoked and the contract has been terminated before expiry

of the extended period and that the bills were not paid. Therefore, the contract

could not have been terminated. He submits that there was a delay in handing

over the site, therefore, the work could not be completed and in this

background he has submitted that the learned Single Judge has committed an

error in rejecting the prayer for grant of stay.

The learned counsel appearing for the respondents has opposed

the appeal and supported the impugned order passed by the learned Single

Judge and has submitted that the nature of work was relating to public

service and serious lapses were committed by the appellant and that the bills

were cleared as per the tender conditions and there was no delay on the part

of the respondents in handing over the site as the work was relating to

renovation and for that purpose the sites were to be handed over in phased

manner. He has further submitted that contract provides for termination and

the termination clause has rightly been invoked and the appellant had

belatedly approached the Court.

We have heard learned counsel for the parties. Perusal of the order

passed by the learned Single Judge reveals that all the relevant aspects have

duly been considered by the learned Single Judge. Record reflects that the

appellant had initially made a prayer in the writ petition itself for interim relief

and originally the said prayer was considered by the learned Single Judge and

by order dated 13th July, 2022, limited protection was extended by directing

that the action taken by the respondents shall abide by the result of the

proceedings. The prayer for grant of interim order restraining the termination

of the contract was not granted. This order was not challenged any further.

It has been pointed out by the learned counsel for the respondents

that the contract was terminated on 29th March, 2022. Thereafter the work

order to the third party was issued on 24th June, 2022 but the writ petition

was filed by the appellant sometime on 8th July, 2022 much after the

termination of the contract and issuance of fresh work order to the third party.

When the matter for grant of interim relief was heard earlier by the Single

Bench on 13th July, 2022 at that time the work order to the third party was

already issued. Hence, considering all the circumstances, limited protection

was extended to the appellant by order dated 13th July, 2022. Hence, there

was no occasion to file a fresh application being GA/3/2022 seeking stay of

the work order. That apart the order of the learned Single Judge reflects that

though the appellant was contending that the work to the extent of 88% was

completed whereas the stand of the respondents is that the appellant had

completed the work to the extent of 27.3%. This being a disputed question, the

stand of the appellant in respect of the completion of work could not be

accepted. The counsel for the appellant has also pointed out the relevant

clause of the contract permitting termination of the contract. Hence, the stand

of the appellant that no such clause exists has rightly been rejected by the

learned Single Judge. That apart it is also noticed that the work relating to the

public utility service is required to be completed at the earliest. Therefore, the

learned Single Judge has rightly refused the prayer for stay of the work order

by observing that the nature of the work concern is an infrastructural project

of public importance and directly connected to the law and order situation.

Thus, valid reasons have been assigned by the learned Single Judge for

rejecting the prayer for stay.

Leaned Counsel for the appellant has placed reliance upon the

judgment of the Supreme Court in the matters of Madhya Pradesh Power

Management Company Limited vs. Renew Clean Energy Private Limited And

Another reported in (2018) 6 SCC 157 and N. G. Projects Limited v. Vinod

Kumar Jain And Others reported in (2022) 6 SCC 127. But both these

judgments have been considered in detailed by the learned Single Judge have

not been found to be applicable in the facts of the present case. In fact, in the

matter of N.G. Projects Limited (Supra), the Hon'ble Supreme Court has gone

to the extent observing that if court finds that there is total arbitrariness or

that the tender has been granted in a mala fide manner, still the Court should

refrain from interfering in the grant of tender but instead relegate the parties

to seek damages for the wrongful exclusion rather than to injunct the

execution of the contract.

The view taken by the learned Single Judge is in consonance with

the observation made by the Hon'ble Supreme Court. In the aforesaid

circumstances of the case, we find no good ground to interfere the order of the

learned Single Judge.

At this stage, it has been pointed out that pleadings are complete

in the writ petition and the writ petition is already appearing in the list of

learned Single Judge. Hence, we expect that the learned Single Judge will take

up the writ petition and decide the same as expeditiously as possible.

The appeal is, accordingly, disposed of. All the pending

applications are, accordingly, dismissed.

(PRAKASH SHRIVASTAVA, C.J.)

(RAJARSHI BHARADWAJ, J.)

akg/pa

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : MAIMS

 
 
Latestlaws Newsletter