Monday, 18, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Kanpur Development Authority vs M/S Aradhana Constructions
2023 Latest Caselaw 35043 ALL

Citation : 2023 Latest Caselaw 35043 ALL
Judgement Date : 14 December, 2023

Allahabad High Court

Kanpur Development Authority vs M/S Aradhana Constructions on 14 December, 2023

Author: Mahesh Chandra Tripathi

Bench: Mahesh Chandra Tripathi





HIGH COURT OF JUDICATURE AT ALLAHABAD
 
 


?Neutral Citation No. - 2023:AHC:236754-DB
 
Court No. - 40
 
Case :- APPEAL UNDER SECTION 37 OF ARBITRATION AND CONCILIATION ACT 1996 DEFECTIVE No. - 623 of 2023
 
Appellant :- Kanpur Development Authority
 
Respondent :- M/S Aradhana Constructions
 
Counsel for Appellant :- Saurabh Srivastava
 

 
Hon'ble Mahesh Chandra Tripathi,J.
 

Hon'ble Prashant Kumar,J.

1. Heard Shri Saurabh Srivastava, learned counsel for the appellant and learned counsel appearing for the respondent.

2. The instant appeal under Section 37 of the Arbitration and Conciliation Act, 1996 has been filed challenging the judgment and decree dated 15.05.2023 passed by the Commercial Court, Kanpur Nagar in Execution Case No. 66 of 2020 (M/s Aradhana Constructions v. Kanpur Development Authority), which was an application preferred by the appellant under Section 34 of the Arbitration and Conciliation Act, 1996 (hereinafter for the sake of brevity has been referred to as "Arbitration Act").

3. Apparently, there was a dispute between the parties, which has been referred to the arbitration and an award was passed.

4. The award was challenged by filing an application under Section 34 of Arbitration & Conciliation Act, 1996. The Commercial Court, Kanpur Nagar was pleased to reject the application preferred by the appellant by a judgement and order dated 15.05.2023.

5. Against this rejection order dated 15.05.2023, the appellant herein preferred the instant appeal under Section 37 of the Arbitration Act.

6. As per Section 13 (1A) of the Commercial Court Act, 2015 read with Section 37 of the Arbitration Act, the limitation prescribed to file an appeal under Section 37 of Arbitration Act is 60 days. For ready reference Section 13 (1A) of the Commercial Court Act, 2015 is quoted hereunder :-

"(1A) Any person aggrieved by the judgment or order of a Commercial Court at the level of District Judge exercising original civil jurisdiction or, as the case may be, Commercial Division of a High Court may appeal to the Commercial Appellate Division of that High Court within a period of sixty days from the date of the judgement or order:"

7. There is a delay of 114 days in filing of the instant appeal and no substantial ground for delay has been mentioned in the delay condonation application filed along with the instant appeal for condonation of delay.

8. The primary aspect which arises for consideration in this appeal is as to whether the petition filed under Section 37 of the Act 1996 was within the period of limitation provided therein. If not, whether the delay is condonable by exercise of power under Section 5 of Limitation Act.

9. The Hon'ble Supreme Court in P. Radha Bai vs. P. Ashok Kumar, 2019 (13) SCC 445, has held as follows:-

"33.2. The proviso to Section 34 (3) enables a court to entertain an application to challenge an award after the three months' period is expired, but only within an additional period of thirty dates, "but not thereafter". The use of the phrase "but not thereafter" shows that the 120 days' period is the outer boundary for challenging an award. If Section 17 were to be applied, the outer boundary for challenging an award could go beyond 120 days. This Court has consistently taken this view that the words "but not thereafter" in the proviso of Section 34 (3) of the Arbitration Act are of a mandatory nature, and couched in negative terms, which leaves no room for doubt."

10. The Hon'ble Supreme Court in Union of India vs. M/s Varindra Construction Ltd., 2020 (2) SCC 111, has held that since a Section 34 application has to be filed within a maximum period of 120 days including the grace period of 30 days, an appeal filed from the self-same proceeding under Section 37 should be covered by the same drill. Given the fact that an appellate proceeding is a continuation of the original proceeding, as has been held in Lachmeshwar Prasad Shukul and Others vs. Keshwar Lal Chaudhuri and Others, AIR 1941 Federal Court 5, and repeatedly followed by our judgments, we feel that any delay beyond 120 days in the filing of an appeal under Section 37 from an application being either dismissed or allowed under Section 34 of the Arbitration and Conciliation Act, 1996 should not be allowed as it will defeat the overall statutory purpose of arbitration proceedings being decided with utmost despatch.

11. That the Hon'ble Supreme Court in the matter of Government of Maharashtra (Water Resources Department) Represented by Executive Engineer Vs. M/s Borse Brothers Engineers & Contractors Pvt. Ltd., 2021 (6) SCC 460, has held that, given the aforesaid object of speedy disposal sought to be achieved both under the Arbitration Act and the Commercial Courts Act, for appeals filed under Section 37 of the Arbitration Act that are governed by Articles 116 of the Limitation Act or Section 13(1A) of the Commercial Courts Act, a delay beyond prescribed time can only be condoned by way of exception and not by way of rule only in a fit case in which a party has otherwise acted bonafide and not in a negligent manner, a short delay beyond such period can, in the discretion of the court, be condoned, always bearing in mind that the other side of the picture is that the opposite party may have acquired both in equity and justice, what may now be lost by the first party's inaction, negligence or laches.

12. That the Hon'ble Supreme Court in the matter of Mahindra and Mahindra Financial Services Ltd. Vs Maheshbhai Tinabhai Rathod and others, 2022 (4) SCC 162, has held that where limitation is prescribed and the extent to which it can be condoned is circumscribed, the Court, under Section 5 of Limitation Act cannot condone the delay beyond the period prescribed under the Arbitration and Conciliation Act.

14. In view of the aforesaid facts and circumstances that the appeal was filed with delay of 114 days, we are not inclined to entertain this appeal.

15. The instant appeal under Section 37 of the Arbitration and Conciliation Act, 1996 read with Section 13 (1A) of the Commercial Court Act, 2015 is, accordingly, dismissed.

Order Date :- 14.12.2023

Rama Kant

 

 

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : MAIMS

 
 
Latestlaws Newsletter