Sunday, 10, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

ARBAP/24/2024
2025 Latest Caselaw 2813 UK

Citation : 2025 Latest Caselaw 2813 UK
Judgement Date : 23 May, 2025

Uttarakhand High Court

ARBAP/24/2024 on 23 May, 2025

                                                                   2025:UHC:4395
     IN THE HIGH COURT OF UTTARAKHAND
                             AT NAINITAL
                    SRI JUSTICE G. NARENDAR, C.J.


                             23RD MAY, 2025
        ARBITRATION PETITION NO. 24 OF 2024
Between:
M/s Mago Construction Pvt. Ltd.                        ................Applicant

and

Union of India and others.                                    .....Respondents

Counsel for the applicant              :       Mr. Modassir   H.   Khan,   learned
                                               counsel.

Counsel for the respondents            :       Mr. Rajesh Sharma, learned Standing
                                               Counsel for the Union of India.
Upon hearing the learned Counsel, the Court
made the following


JUDGMENT :

Heard learned counsel for the applicant and

learned Standing Counsel for the Union of India /

respondents.

2. The applicant, an 'SS Class' Contractor with

Military Engineering Services, and the applicant was

declared as successful bidder and was awarded certain

civil work by way of letter dated 08.01.2015.

Thereafter, the work order came to be issued to the

applicant on 27.01.2015 and initial date of completion

of the work was 26.07.2017. Later, the works were

completed as on 31.07.2019 pursuant to extensions

given by the respondents.

2025:UHC:4395

3. Learned counsel for the respondents would

not dispute the extensions granted by him for

completion of the work. The work was completed on

31.07.2019 and the work completion was intimated by

letter dated 06.08.2019. The applicant requested the

opposite parties for deviation orders by letter dated

27.01.2021, and the final bill was submitted with the

respondents on 25.12.2020.

4. It is fairly admitted by the respondents'

counsel that the final bill has neither been accepted,

nor has it been rejected. By notice dated 21.01.2023,

the applicant invoked Condition-70 of the GCC and

sought for reference of disputes for determination by

arbitration. Despite the same, the respondents have

failed to appoint an arbitrator.

5. In the above background and facts, the

present Application has been preferred. The

Application is resisted by the respondents' counsel on

the ground that the same is belated and barred by

limitation.

6. Admittedly, the issue of limitation is a mixed

question of facts and law. The dates, narrated above,

clearly indicate that there is no rejection of the final bill

and in the absence of the rejection of the final bill, the

2025:UHC:4395 question that arises is whether limitation starts

running? That apart, the notice invoking arbitration

clause has also not been denied or repudiated.

Disputes having arisen and Condition No. 70 of the GCC

for providing for settlement of disputes by way of

arbitration, the applicant has made out a case for grant

of relief under sub-section (6) of Section 11 of the

Arbitration and Conciliation Act, 1996.

7. In that view of the matter, the instant Application

is allowed. Hon'ble Mr. Justice Raghvendra Singh

Chauhan (Retd), former Chief Justice of this High

Court, is appointed to officiate as an Arbitrator to

adjudicate the disputes that have arisen between the

parties on merits, in accordance with the Act.

8. Let a copy of this order be communicated to

Hon'ble Mr. Justice Raghvendra Singh Chauhan (Retd),

former Chief Justice of this High Court.

9. The Arbitrator shall, in terms of Section 11(8)

of the Act, furnish his disclosure in writing to the Court

within 15 days from the date of receipt of a certified

copy of this order. The Arbitrator shall, in consultation

with the parties, fix the remuneration and other

chargeable fees. The Arbitrator shall endeavour to hear

2025:UHC:4395 and pass an Award within the time provided under the

statute.

10. There shall be no order as to costs.

11. In sequel thereto, all pending Applications

stand disposed of.

________________

G. NARENDAR, C.J.

Dt: 23rd May, 2025 Rathour

PRAVIND Digitally signed by PRAVINDRA SINGH RATHOUR DN: c=IN, o=HIGH COURT OF UTTARAKHAND, ou=HIGH COURT OF UTTARAKHAND,

RA SINGH 2.5.4.20=23699ccc2fd40ad81b6fd13323779d 9e3aeb1097d17dbb53d481cabd25946eed, postalCode=263001, st=UTTARAKHAND, serialNumber=1F65499E931DF71CDAF92A40

RATHOUR CC6179B8E010331BA695239171F906FD5C45 C4E8, cn=PRAVINDRA SINGH RATHOUR Date: 2025.05.30 11:50:25 +05'30'

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter