Citation : 2024 Latest Caselaw 458 UK
Judgement Date : 21 March, 2024
Reserved Judgment
IN THE HIGH COURT OF UTTARAKHAND
AT NAINITAL
HON'BLE THE CHIEF JUSTICE MS. RITU BAHRI
AND
HON'BLE MR. JUSTICE RAKESH THAPLIYAL
Reserved on : 06.03.2024
Delivered on : 21.03.2024
APPEAL FROM ORDER NO. 406 OF 2022
State of Uttarakhand & others ...... Appellants
Versus
Sandesh Kumar ...... Respondent
WITH
APPEAL FROM ORDER NO. 407 OF 2022
State of Uttarakhand & others ...... Appellants
Versus
Sandesh Kumar ...... Respondent
Counsel for the appellants : Mr. Shailendra Singh Chauhan,
learned counsel
Counsel for the respondent : Mr. Rajat Mittal, learned counsel
The Court made the following:
JUDGMENT:
(per Hon'ble the Chief Justice Ms. Ritu Bahri)
The State has come up in both the appeals
against the common judgment and order dated
11.05.2022, passed by the Additional District Judge
(Commercial) Dehradun, whereby arbitration case No.
96 of 2019 and Arbitration Case No. 97 of 2019, filed by
the appellants against the award dated 28.07.2016,
passed by the single Arbitrator Mr. M.Z. Haq, in, were
rejected. The two appeals before us have arisen out of
common judgment and order, therefore, they are being
decided together for the sake of brevity and
convenience.
2) Brief facts leading to filing of both the appeals
are that the appellants instituted aforementioned
arbitration cases under Section 34 of the Arbitration and
Conciliation Act, 1996 against the award dated
28.07.2016, passed by the single Arbitrator Mr. M.Z.
Haq. The contention of the appellants is that the
arbitration cases were filed before the Arbitrator on
11.08.2015. Opposite party submitted its written
statement and counter-claim on 03.11.2015. The
contract in question was executed between the parties
for expansion and development of Kotdwar to Haridwar
motor road. Opposite party presented a bank guarantee
of Rs.20,53,300/-. The work commenced on 24.02.2012
and has to be completed on 31.03.2013. It is contended
that the opposite party was handed over the possession
of work place, but he failed to bring the resources,
labour and machinery on the pretext that work had to be
undertaken in forest area, whereas the fact was that
necessary permission had already been taken for said
work in the forest area. The road was in existence since
1960. Opposite party left the work, and when the
payment of his bank guarantee was sought, he instituted
a suit under Section 09 of the Arbitration and
Conciliation Act. It is also contended that the opposite
party had taken back the bank guarantee during
pendency of the said suit due to which the appellants
had to suffer losses. The appellants had to invite bid
afresh and made to pay Rs.426.42 lakhs to the other
contractor. It is further contended that the Arbitrator by
admitting the claim petitioner and Rs.34,09,920/- for
counter-claim of the appellants had passed the award in
question.
3) The appellants in their arbitration cases took
the ground that the Arbitrator had not framed issues and
no conclusion has been drawn in it and as such the
appellants had to suffer due to miscarriage of justice. It
is also contended that the procedure prescribed on
03.08.2015 had not been complied with; no evidence
was there for award on account of overhead expenses;
there was no evaluation formula alleged for it. It is
alleged that the Arbitrator was negligent for misconduct
as violated the public policy, and without appreciating
the evidence regarding loss of machinery, had passed
the award in question. No evidence was brought on
record to show that the contractor ever brought any
machinery at the work place, or he was the owner of any
machinery and passed the award regarding the loss of
working labour. Opposite party had failed to produce
any evidence to show that labour had been employed by
him at the work place. The Arbitrator had passed the
award on account of loss and profit without any
evidence. It is alleged that the Arbitrator further had
not taken decision that the opposite party had violated
the contract, whereas sufficient evidence were available
on record in this regard. Lastly, it is contended that
there was no reason apparent on record for releasing the
bank guarantee, and the interest had been paid without
having any jurisdiction to do so. It is further alleged
that the award in question is against the law and is
contrary to the public policy of India and induced by
deceit and is against the moral ethics of substantial
principle of justice. Therefore, the award passed in
favour of the opposite party is liable to be set aside.
4) The Additional District Judge (Commercial)
Dehradun dismissed both the arbitration cases filed by
the appellants on the following grounds :
i) The appointment of Mr. M.Z. Haq as a single Arbitrator was as per the consent of both the parties, and a letter had already been issued by the Rural Development Department regarding appointment of the single Arbitrator.
ii) The respondent had initiated the arbitral proceedings after the proceedings under Clause 25 of the contract had been done.
iii) Prior to issuance of notice for arbitration, a letter has been sent to the adjudicator on 05.02.2015 (copy enclosed as Annexure-7 to the arbitration petition), and after that on account of non- decision by the adjudicator within the time stipulated, the respondent had taken a decision to initiate arbitration proceedings.
iv) As per Clause 19, sub-sections (2) and (3) of the Arbitration and Conciliation Act, the parties failed to follow the procedure to be followed by the arbitral tribunal in conducting its proceedings.
v) The issues in the present case were framed by the Arbitrator from 12.10.2015 till 23.01.2016, and these issues were proposed by the contractor as well as the State. Since the State did not push for framing of the issues proposed by it, and had consented to the procedure adopted by the Arbitrator, the award cannot be challenged on the above said grounds.
vi) With respect to concluding the arbitral proceedings within one year, it has been held that
arbitral proceedings were initiated on 03.11.2015, which were well within one year.
vii) The last ground for challenging the award was that the award is liable to be set aside as reasons for giving the award have not been explained.
5) The Commercial Court after perusing the
award in question dated 28.07.2016 observed that the
arbitral tribunal having considered the supporting
documents, the arguments and evidence in support
thereof, and after giving detailed consideration had
passed the award in question. While passing the award,
the table which was presented by the contractor before
the single Arbitrator depicting basis of loss on account of
overhead expenses, machinery, decrease in value, loss
in labour was made the basis for accepting the claim and
passing of the award. As per the judgment, all claims of
the contractor have been considered in accordance with
law, and reasons have been given for rejecting the
grounds taken by the appellants in challenging the
award.
6) After perusing the impugned judgment, the
scope of Section 37 of Arbitration and Conciliation Act,
1996, has to be examined for interfering in the arbitral
award. The scope for interference under Section 37 of
the Arbitration and Conciliation Act is very limited. The
Hon'ble Apex Court in Larsen Air Conditioning and
Refrigration Company Vs Union of India and others,
2023 SCC OnLine SC 982, has held that in appeal,
Section 37 of the Act grants narrower scope to the
appellate court to review the findings in an award, if it
has been upheld, or substantially upheld under Section
34.
7) Finally, the main ground for consideration is
with regard to the applications seeking condonation of
delay in both the appeals. Counsel for the appellants
has placed reliance on the judgments of the Division
Bench of this Court passed in Appeal against Order No.
346 of 2022, Haryana Vidyut Parsaran Nigam Limited &
another Vs M/s Mahavir Transmission Udyog Pvt. Ltd. &
another, decided on 02.11.2022; as well as in Appeal
from Order No. 127 of 2021, State of Uttarakhand &
others Vs M/s Hillways Constructions Company Pvt. Ltd.,
decided on 07.03.2022. Reliance has also been placed
on the judgment passed by learned Single Judge of this
Court in Appeal from Order No. 09 of 2022, Jishan Ali Vs
Arbitrator NHAI / Collector, decided on 05.03.2022.
8) However, in the instant case, the State has
come up in two separate appeals against the common
order of the Commercial Court, and there is delay of 91
days and 151 days, respectively, in preferring these
appeals. The judgment delivered by Kerala High Court
in the case of Muhammed Shafeek Vs M/s Tasty Nut
Industries, Kilikolloor, Kollam & others, rendered in
C.M. Appln. No. 01 of 2023 in COML. Appeal No. 3 of
2023, decided on 17.10.2023, cannot be made basis to
condone said delay. The issue of delay has already been
considered in a number of judgments. One such
judgment of the Division Bench of this Court was
rendered in Appeal from Order No. 127 of 2021, State
of Uttarakhand & others Vs M/s Hillways Constructions
Company Pvt. Ltd., decided on 07.03.2022, wherein
after examining the provisions of Section 13(1A) of the
Commercial Courts Act, which only provides condonation
of delay of 30 days and 60 days, the application for
condonation of delay of 85 days was dismissed, taking
note of the judgment of Hon'ble Apex Court rendered in
Government of Maharashtra (Water Resources
Department) represented by Executive Engineer Vs
Borse Brothers Engineers and Contractors Pvt. Ltd.,
(2021) 6 SCC 460, wherein in para 63 it has been held
as under :
"Given the aforesaid and the object of speedy disposal sought to be achieved both under the Arbitration Act and the Commercial Courts Act, for
appeals filed under section 37 of the Arbitration Act that are governed by Articles 116 and 117 of the Limitation Act or section 13(1-A) of the Commercial Courts Act, a delay beyond 90 days, 30 days or 60 days, respectively, is to be condoned by way of exception and not by way of rule. In a fit case in which a party has otherwise acted bona fide and not in a negligent manner, a short delay beyond such period can, in the discretion of the court, be condoned, always bearing in mind that the other side of the picture is that the opposite party may have acquired both in equity and justice, what may now be lost by the first party's inaction, negligence or laches."
9) Borse Brothers (supra) case has been followed
in another Division Bench judgment passed by this Court
on 02.11.2022, in Appeal against Order No. 346 of
2022, Haryana Vidyut Parsaran Nigam Limited &
another Vs M/s Mahavir Transmission Udyog Pvt. Ltd.
& another, where delay of 908 days was sought to be
condoned in an appeal filed under Section 37 of the
Arbitration and Conciliation Act, 1996. Even this appeal
was dismissed. Also, in Appeal from Order No. 09 of
2022, Jishan Ali Vs Arbitrator NHAI / Collector,
decided on 05.03.2022, learned Single Judge of this
Court taking note the proposition of law laid down in the
case of Borse Brothers (supra) rescind itself from
condoning the delay of 551 days, and rejected the
application seeking condonation of such delay.
10) In the cases in hand, there is a delay of 91
days and 151 days, respectively, in preferring both the
appeals. Since there is no sufficient cause given for
condoning such delay, therefore, delay condonation
applications, both bearing Nos. 02 of 2022, are hereby
rejected.
11) Apart from the delay, on merits also the award
has been passed by giving just and valid reasons.
12) In view of the foregoing discussion, this
court does not find any reason to interfere with the
impugned award dated 28.07.2016 along with
common judgment and order dated 11.05.2022,
passed under Section 34 of the Arbitration and
Conciliation Act, by Additional District Judge
(Commercial), Dehrdaun in Arbitration Case No. 96 of
2019 and Arbitration Case No 97 of 2019. Both the
appeals are, accordingly, dismissed. Interim order
dated 22.12.2022 is hereby vacated.
13) The FDR, along with interest, kept in the
nationalized bank by the Registry of this Court be
remitted to the court concerned.
______________ RITU BAHRI, C.J.
________________ RAKESH THAPLIYAL, J.
Dt: 21ST MARCH, 2024 Negi
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!