Sunday, 10, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

M/S Chaudhary Sandeep Contractor ... vs State Of Uttarakhand & Others
2023 Latest Caselaw 3163 UK

Citation : 2023 Latest Caselaw 3163 UK
Judgement Date : 16 October, 2023

Uttarakhand High Court
M/S Chaudhary Sandeep Contractor ... vs State Of Uttarakhand & Others on 16 October, 2023
             IN THE HIGH COURT OF UTTARAKHAND
                                  AT NAINITAL
                    HON'BLE THE CHIEF JUSTICE SRI VIPIN SANGHI
                                          AND
                      HON'BLE SRI JUSTICE RAKESH THAPLIYAL

                   WRIT PETITION (M/B) NO. 251 OF 2023

                            16TH OCTOBER, 2023

M/s Chaudhary Sandeep Contractor & Supplier                         .....Petitioner.
                                        Versus

State of Uttarakhand & others                                    ....Respondents.

Counsel for the Petitioner : Mr. Xitiz Kaushik, learned counsel.

Counsel for the Respondent No.1 : Mr. Amarendra Pratap Singh, learned Additional Advocate General.

Counsel for the Respondent Nos.2 to 5 : Mr. Ashish Joshi, learned counsel.

The Court made the following:

JUDGMENT:(per Hon'ble The Chief Justice Sri Vipin Sanghi)

The present order is being passed in continuation of

the order dated 19.09.2023. The said order reads as follows:-

"1. Mr. Xitij Kaushik, learned counsel for the petitioner.

2. Mr. Amarendra Pratap Singh, learned Additional Advocate General for the State of Uttarakhand/ respondent no. 1.

3. Mr. Ashish Joshi, learned counsel for respondent nos. 2 to 5.

4. Mr. Joshi has tendered instructions. The submission of Mr. Joshi is that there were eight bidders in all, and several of them corrected their financial bids after the issuance of the Corrigendum dated 10.08.2023.

5. The grievance of the petitioner is that, in respect of one of the items in the Bill of Quantities, namely at Sl. No. 222 - Sculptures for Yoga Park, the quantity initially indicated was 21, which, by the aforesaid Corrigendum, was reduced to

01. However, in the computer system of the respondents, the figure continued to be 21, inasmuch as, when the petitioner tendered its rates for one item, the figure got multiplied by

21. That is how the petitioner's financial bid, in respect of Item No. 222 - Sculptures for Yoga Park, got inflated by 21 times, and the petitioner has been ousted on the ground of not being the L1 bidder.

6. The submission of learned counsel for the petitioner is that, if the petitioner's bid for Item No. 222 is reduced 21 times, the petitioner would emerge as the L1 bidder.

7. On the other hand, Mr. Joshi, on instructions, states that, even if the said exercise is undertaken, the petitioner would not be the L1 bidder.

8. The declaration of the financial bid result is in Annexure No. 5, as per which the L1 bidder has quoted an amount of Rs. 4,37,06,771.67.

9. We direct the respondents to produce the financial bid of the petitioner, and also to provide the necessary calculation, reducing the cost of the Item at Sl. No. 22 by 21 times, with the amount stated to have been quoted by the petitioner. The said calculation be produced on the next date.

10. List on 26.09.2023.

11. Interim order to continue till the next date of listing."

2. The respondents have since filed their counter-

affidavit. In Paragraph Nos.11 and 12, the respondents have

stated as follows:-

"11. That perusal of the said list shall reveal that for item showed at serial no.222 the petitioner quoted an amount of INR 38,38,66,686/- (Rupees Thirty Eight Crore Thirty Eight Lakh Sixty Six Thousand Six Hundred and Eighty Six) only for 21 items. The said amount was for 21 sculptures which is admittedly a typographical error on behalf of the answering respondents. Therefore, on dividing the aforesaid amount by 21, we will get the cost for 1 sculpture. Hence the amount quoted by the petitioner for 1 sculpture is 38,38,66,686 ÷ 21 = 1,82,79,366/- (Rupees One Crore Eighty Two Lakh Seventy Nine Thousand Three Hundred and Sixty Six) only.

12. That it is pertinent to mention that even after adding the correct bid amount for item at serial no.222 to the bid amount

of the remaining items quoted by the petitioner, his total bid for the tender would be INR 4,84,04,069.22/- (Rupees Four Crore Eighty Four Lakhs Four Thousand Sixty Nine Rupees and Twenty Two Paisa) only which still makes the petitioner L2 bidder because the said amount is greater than the amount quoted by Shri Balaji Enterprises which is INR 4,37,06,771.67/- (Rupees Four Crore Thirty Seven Lakhs Six Thousand Seven Hundred Seventy One and Sixty Seven Paisa). For the kind perusal of the court a table is placed regarding the same.

12.1 That table below contains the details of all the 3 bid submitted by the bidders on the official portal of the answering respondents.

      Sr.           Bidders                 Bid Amount   Bid Rank (L1 is
      No.                                                 the winner)
      1.    Shri Balaji Enterprises   INR                      L1
                                      4,37,06,771.67/-
      2.    Cox Infrastructure Pvt. INR 49114620.93/-          L2
            Ltd.
      3.    M/s          Chaudhary INR 413991389.22/-          L3
            Sandeep Contractor &
            Supplier (Petitioner)



12.2 That the table below contains the list of bidders after the compliance of the order dated 19.09.2023 of this Hon'ble Court.

      Sr.           Bidders                 Bid Amount   Bid Rank (L1 is
      No.                                                 the winner)
      1.    Shri Balaji Enterprises   INR                      L1
                                      4,37,06,771.67/-
      2.    M/s          Chaudhary INR                         L2

Sandeep Contractor & 4,84,04,069.22/-

Supplier (Petitioner)

3. Cox Infrastructure Pvt. INR 49114620.93/- L3 Ltd.

3. The respondents have tabulated the emerging

position with regard to the financial bids received from the

technically qualified bidders, which shows that even after

dividing the petitioner's quotation in respect of Sl. No. 222 by

21, the petitioner still remains the L2 bidder, and one Shri

Balaji Enterprises has emerged as the L1 bidder.

4. Aforesaid being the position, no useful purpose

would be served in proceeding further in this writ petition.

5. The writ petition is, accordingly, disposed of.

6. Pending application, if any, also stands disposed of.

(VIPIN SANGHI, C.J.)

(RAKESH THAPLIYAL, J.) Dated: 16th October, 2023 NISHANT

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter