Citation : 2023 Latest Caselaw 1363 UK
Judgement Date : 17 May, 2023
IN THE HIGH COURT OF UTTARAKHAND
AT NAINITAL
THE HON'BLE THE CHIEF JUSTICE SRI VIPIN SANGHI
AND
THE HON'BLE SRI JUSTICE RAKESH THAPLIYAL
WRIT PETITION (M/B) NO. 22 OF 2023
17TH MAY, 2023
Between:
Suresh Tomar ...... Petitioner
and
State of Uttarakhand & another ...... Respondents
Counsel for the petitioner : Mr. Kushagra Bansal, learned
counsel
Counsel for the respondents : Mr. B.S. Parihar, learned Standing
Counsel for the State / respondent
No. 1
The Court made the following:
JUDGMENT: (per Hon'ble The Chief Justice Sri Vipin Sanghi)
The petitioner has preferred the present writ
petition to assail the order dated 02.03.2023, passed by
respondent No. 1. The petitioner also seeks a direction
to the respondent authorities to terminate the contract
of respondent No. 2 under clause 52 of the General
2
Conditions of Contract, in respect of the tender bearing
No. 51/UT-03-97(1)/XVIII/CE-URRDA/19-20, dated
12.07.2019, under the name and style of "Tapovan-
Reengi to Subhai (Bhavisyabadri) M/s Stage-1".
2) The petitioner claims that the respondent No.
2 engaged the petitioner as a sub-contractor in respect
of the aforesaid contract, allegedly in breach of the
terms and conditions of the contract entered into
between respondent No. 1 and respondent No. 2. It
appears that disputes have arisen between the petitioner
and respondent No. 2-contractor. The petitioner earlier
preferred a writ petition, being WPMS No. 2635 of 2022,
which was disposed of by this Court on 05.12.2022. The
said petition had also been preferred claiming the same
relief, i.e., that the contract of respondent No. 2, as
contractor, be terminated under clause 52 of the General
Conditions of Contract.
3) We disposed of the said petition by observing
as follows :
"The petitioner claims to be a sub-contractor of
respondent No. 2 in relation to a contract awarded by
respondent No. 1 to respondent No. 2 under the
Pradhan Manti Gramin Sadak Yojna.
3
It appears that the petitioner and respondent No.
2 entered into a sub-contract, in respect of which
disputes have arisen regarding payments. The
petitioner has represented to respondent No. 1 that
respondent No. 2 has breached clause 7 of the general
conditions of contract, which lays down stipulations
with regard to sub-contracting the works by the
contractor.
Those representations have not been decided. In
this background the petitioner has preferred this writ-
petition for the reliefs as set out hereinabove.
We are not inclined to entertain the writ-petition
to consider the relief sought by the petitioner, as
disputed questions of facts would require to be
adjudicated.
The petitioner can approach the Civil Court, in
case the petitioner is so advised.
At the same time, since the petitioner has made
representation to respondent No. 1 alleging breach of
contract by respondent No. 2 - the contractor, we
dispose of this petition with a direction to respondent
No. 1 to examine the representation made by the
petitioner and dispose of the same with speaking order
within four weeks."
4) Thus, it would be seen, that this Court was not
inclined to entertain the writ petition to consider the
reliefs sought by the petitioner, as disputed questions of
facts were raised, which require adjudication. We left it
open to the petitioner to approach the civil court to press
4
his reliefs. We also directed respondent No. 1 to decide
the representation of the petitioner. By the impugned
order, the said representation has been considered, and
rejected. The respondent No. 1 has taken the stand that
the alleged sub-contract entered into between the
petitioner and respondent No. 2 was without their
consent, and they have no concern with the same. They
have stated that only respondent No. 2 shall be held
responsible for the work under the contract. The
rejection of the said representation is now assailed
before us.
5) We have heard learned counsel for the
petitioner.
6) In our view, no direction as sought by the
petitioner can be issued by us in these proceedings. The
petitioner has brought to notice of respondent No. 1, the
alleged breach of the terms and conditions of the
contract. It is for the respondent No. 1 to decide -
whether, or not, to condone the said breach, and waive
the alleged breach. This Court cannot issue direction to
respondent No. 1 to mandatorily terminate the contract.
It could be that despite the respondent No. 2 being in
breach of the terms and conditions of the contract, i.e.,
5
clause 7 and clause 52, the respondent No. 1 may
decide not to terminate the contract in public interest.
7) We, therefore, do not find any merit in this
petition. The same is, accordingly, dismissed.
________________
VIPIN SANGHI, C.J.
________________
RAKESH THAPLIYAL, J.
Dt: 17th MAY, 2023 Negi
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!