Citation : 2022 Latest Caselaw 3008 UK
Judgement Date : 19 September, 2022
IN THE HIGH COURT OF UTTARAKHAND
AT NAINITAL
SRI JUSTICE VIPIN SANGHI, C.J.
AND
SRI JUSTICE R.C. KHULBE, J.
19th September, 2022 WRIT PETITION (M/S) NO. 3067 OF 2018 Between:
Unicon Builders and Contractors ......Petitioner.
And
State of Uttarakhand and another. ....Respondents & WRIT PETITION (M/S) NO. 3063 OF 2018 Between:
Unicon Builders and Contractors ......Petitioner.
And
State of Uttarakhand and another. ....Respondents
Counsel for the petitioner : Mr. Bhuwan Bhatt.
Counsel for the respondents : Mr. B.P.S. Mer, learned Brief Holder for the State of Uttarakhand / respondent No. 1.
Mr. Pradeep Chamiyal, learned counsel for respondent Nos. 2 & 3.
Upon hearing the learned Counsel, the Court made the following
COMMON JUDGMENT : (per Sri Vipin Sanghi, C.J.)
The petitioner has preferred these two writ
petitions in similar circumstances.
2. The petitioner participated in the tendering
process in relation to two works, namely
UDRP/PWD/07/RD/118 and UDRP/PWD/07/RD/119. Writ Petition (M/S) No. 3063 of 2018 relates to the first of
these works, whereas Writ Petition (M/S) No. 3067 relates
to the second work aforesaid.
3. For the purpose of ease, we are treating Writ
Petition (M/S) No.3067 of 2018 as the lead matter, and
taking note of the facts and circumstances in relation to
the said case. The facts of the other case are also similar.
4. The estimated cost of the work in relation to the
Package No. UDRP/PWD/07/RD/119 was Rs.1528.53 lacs.
The bid submitted by the petitioner in response to the said
Package was of Rs. 15,24,91,267.15. Thus, the bid of the
petitioner was only about four lacs less than the estimated
cost. The respondents issued the Letter of Acceptance on
23.09.2017, wherein the respondents, inter alia, required
the petitioner to submit an Additional Security
Performance Security to the tune of ₹2,88,69,664.72 "for
unbalanced bids in terms of ITB Clause 40". The
Communication, however, did not state as to how the
petitioner's bid was claimed to be "unbalanced". It merely
stated that the total Contract Price "excluding of GST and
inclusive of levies and other duties is ₹12,92,29,887.40",
and that the "Total amount of GST payable at the time of
deadline bid submission @ 18% is ₹2,32,61,379.73".
5. Since the petitioner did not agree to furnish the
Additional Performance Security-claiming that the same
was contrary to the terms of the Contract, the
respondents sought to forfeit the bid security of the
petitioner.
6. The petitioner earlier preferred Writ Petition
(M/S) No. 2798 of 2017. The case of the petitioner was
that the respondents had not given any basis to claim that
there was any justification to require the petitioner to
furnish additional performance security under Clause 40.1
of the ITB. The said Clause reads as under:-
"40.1 If the bid, which results in the lowest Evaluated Bid Price, is seriously unbalanced, front loaded or substantially below updated estimates in the opinion of the Employer, the Employer may require the Bidder to produce detailed price analyses (with breakdown of unit rates) for any or all items of the Bill of Quantities, to demonstrate the internal consistency and justification of those prices with the construction methods and schedule proposed. After evaluation of the price analyses, taking into consideration the schedule of estimated contract payments, the Employer may require that the amount of the performance security be increased at the expense of the Bidder to a level sufficient to protect the Employer against financial loss in the event of default of the successful Bidder under the Contract."
7. The said writ petition was disposed of by the
learned Single Judge with a direction to the respondents
to consider the case of the petitioner in terms of Clause
40.1 of the Instructions to Bidders (ITB). The petitioner
was required to give its explanation within a week, and
the respondent-Employer was required to pass an order in
accordance with law. The order further stated that "If the
employer comes to the conclusion that the bid price of the
petitioner is extremely low and work cannot be done, the
employer would always be at liberty either to ask for the
additional performance guarantee, or to cancel the bid and
go for fresh bid, after explaining the changed
circumstances in terms of public money".
8. The respondents have now passed the
impugned order dated 31.08.2018 stating it to be in
compliance of the said order, wherein the respondents
have stated as follows:-
"ek0 mPp U;k;ky; uSuhrky }kjk ikfjr vkns'k ds dze esa vk[;k fcUnqokj fuEukuqlkj gS& fufonknkrk M/s Unicon Builders & Contractors] }kjk vius i=kad UBC/PB/2018/551 fnukad 02-07-2018 }kjk bl dk;kZy; dks fnukad 02-07-2018 esa ek0 mPp U;k;ky; }kjk nh x;h ,d lIrkg dh le; lhek ds vUrxZr viuk Explanation fn;k x;k gS ftlesa muds }kjk fy[kk x;k gS fd%& "Further it is submitted that, your office will always have our performance BG @6% of the entire contract amount, till the completion of work and 5% security will be deducted from our every running bill. That means our huge amount will always remain with your office till the completion of work, in such case there is no question arise of leaving any work incomplete, we assure you that we will complete the work to the entire satisfaction within time limit. So kindly allot the work without considering any Additional performance Bank Guarantee."
fufonknkrk M/s Unicon Builders & Contractors] }kjk nh x;h fufonk esa 42 Nos. Items of Work eas fufonk njsa foHkkxh; Lohd`r vkax.ku ds lkis{k Substantially Low FkhA Bid Document ds ITB Clause No. 40.1 "If the bid, which results in the lowest Evaluated Bid Price, is seriously unbalanced, front loaded or substantially below updated estimates in the opinion of the Employer, the Employer may require the Bidder to providuce detailed price analyses (with breakdown of unit rates) for any or all items of the Bill of Quantities, to provide justification for the quoted price and to demonstrate the internal consistency and justification of those prices with construction method and scheduled proposed. After evaluation of the price analyses, taking into consideration the scheduled of estimated contract payments, the Employer may require that the amount of the performance security be increased at the expense of the Bidder to a level sufficient to protect the Employer against financial loss in the event of default of the successful Bidder under the Contract." ds vuqikyu esa fufonknkrk dh 42 Nos. Items of Work eas fufonk njsa foHkkxh; Lohd`r vkax.ku ds lkis{k Substantially Low gksus ds dkj.k] fufonknkrk ds Default gksus dh n'kk esa foHkkx dks gksus okyh foRrh; gkfu;ksa dks n`f"Vxr djrs gq, mRrjk[k.M 'kklu ds 'kklukns'k la0 [email protected](2)/17-20(lkekU;) /2011 Vh0lh0] nsgjknwu fnukad 12-06- 2017 }kjk fu/kkZfjr ekudksa ds vuqlkj Additional Performance Security ₹2,88,69,664.72 vkadfyr dh x;h FkhA fufonknkrk }kjk fufonk esa nh x;h vR;f/kd de njksa dks n`f"Vxr djrs gq, Hkfo"; esa fufonknkrk }kjk dk;Z djus ;k u djus ds fo"k; esa fVIi.kh ugha dh tk ldrh gS] vfirqw foHkkx }kjk fufonknkrk dks l{ke ekurs gq, fufonknkrk dks bl dk;kZy; ds i=kad 1646/UDRP/PWD/07/RD/119 fnukad 23-09-2017 }kjk Letter of Acceptance (LOA) fuxZr fd;k x;kA fufonknkrk }kjk LOA esa mYysf[kr Bid Document dh ITB Clause No. 40.1 ,oa mRrjk[k.M 'kklu ds 'kklukns'k la0 770/III(2)/17-20 (lkekU;) /2011 Vh0lh0] nsgjknwu fnukad 12-06- 2017 ds vuqikyu esa vkadfyr Additional Performance Security fnukad 31-10-2017 rd Hkh tek u djus ds dkj.k Bid Document ds ITB Clause No. 45.1 ,oa Clause No. 45.2 ds vuqikyu esa bl dk;kZy; ds i=kad 1781/UDRP/PWD/07/RD/119 fnukad 01-11- 2017 ds }kjk iznRr LOA i=kad 1646/UDRP/PWD/07/RD/119 fnukad 23-09-2017 dks fujLr djrs gq, Bid dks iwoZ esa gh cancel fd;k tk pqdk gSA orZeku ifjfLFkfr;ksa esa ;w0Mh-vkj0ih0 ifj;kstuk le;c) gksus ds dkj.k ifj;kstuk dk vfUrehdj.k ekg twu] 2019 esa fd;k tkuk gSA fo"k;d dk;Z dks iw.kZ djus dh dk;kZof/k 15 ekg Fkh ,oa orZeku esa fufonk izfdz;k ,oa
dk;ksZa dks iw.kZ djus gsrq ek= 10 ekg dk le; gh vo'ks"k gSA vr% orZeku ifjfLFkfr;ksa esa l{ke vf/kdkjh }kjk dk;Z dks fujLr djus dk fu.kZ; fy;k x;k gSA ;fn fufonknkrk }kjk fu/kkZfjr le;kfof/k ds vUrxZr Performance Security tek dj nh gksrh rks ;g ifjfLFkfr mRiUu u gksrh rFkk dk;Z fu/kkZfjr le;kof/k ds vUrxZr iw.kZ gks tkrkA"
9. A perusal of the impugned order would show
that the respondents have not undertaken the exercise
that was expected of them, which was to clearly state in
respect of which item the rates submitted by the
petitioner were found to be unbalanced, or substantially
low.
10. Mere submission that the petitioner's rates were
substantially low would not suffice, since the petitioner
claims that its bid was merely four lacs below the
estimated cost and invocation of Clause 40 of the ITB
required the respondents to arrive at an objective
conclusion that the bid submitted by the bidder was
substantially low.
11. We find that the impugned order does not
comply with the order passed by the learned Single Judge
in Writ Petition (M/S) No. 2798 of 2017 dated 25.06.2018
in either letter or spirit.
12. We, therefore, quash the impugned order, and
once again remand back the matter to the respondents to
clearly state as to on what basis the respondents have
claimed that the bids / rates submitted by the petitioner
were substantially low. The respondents should take into
consideration the analysis of rates furnished by the
petitioner on 02.07.2018 in compliance of the order dated
25.06.2018 passed in Writ Petition (M/S) No. 2798 of
2017, and after considering the same and granting
personal hearing to the petitioner, the respondents should
pass a reasoned order.
13. We make it clear that we have not ourselves examined the aspect whether the rates/ quotations submitted by the petitioner were substantially low, or not, as that aspect would fall for consideration of the respondents, who submitted that the rates / quotations submitted by the petitioner were substantially low, without objectively disclosing as to on what basis the said conclusion was reached. The aforesaid exercise should be completed by the respondents within four weeks from today.
14. Both the writ petitions stand disposed of in the aforesaid terms.
________________ VIPIN SANGHI, C.J.
____________ R.C. KHULBE, J.
Dt: 19th September, 2022 Rathour
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!