Citation : 2022 Latest Caselaw 3756 UK
Judgement Date : 23 November, 2022
IN THE HIGH COURT OF UTTARAKHAND
AT NAINITAL
SRI JUSTICE VIPIN SANGHI, C.J.
AND
SRI JUSTICE R.C. KHULBE, J.
23RD NOVEMBER, 2022 WRIT PETITION (PIL) NO. 44 OF 2020 Between:
Birendra Singh ......Petitioner.
and
Union of India and others. ....Respondents
Counsel for the petitioner : Mr. P.B. Suresh and Mr. Karthik.
Counsel for the respondents : Mr.Manoj Kumar, learned Standing
Counsel for the Union of India /
respondent No. 1.
Mr. Pradeep Joshi, learned Additional Chief Standing Counsel for the State of Uttarakhand / respondent No.2.
Mr. Vikas Srivastava and Mr. Akshay
Pradhan, learned counsel for
respondent Nos. 3 & 4.
Upon hearing the learned Counsel, the Court made the following
ORDER : (per Sri Vipin Sanghi, C.J.)
Vide our order dated 18.11.2022, we had directed
the State to file a report in terms of the order dated
20.03.2020. On 20.03.2020, this Court took notice of the
order passed by the Supreme Court on 11.02.2020 in Civil
Appeal No. 8560 of 2018, whereby the Supreme Court
disposed of the said Civil Appeal, preferred by the petitioner,
herein, against the order dated 24.07.2018 passed by the
National Green Tribunal dismissing his petition being O.A.
No. 791 of 2017, by placing reliance on a Court
Commissioner's report, appointed by it. In its order, the
National Green Tribunal extracted a part of the detailed report prepared by the Court Commissioner dated
09.07.2018.
2. The Supreme Court, while passing the order
dismissing the Civil Appeal No. 8560 of 2018 on 11.02.2020,
inter alia, directed that survey and demarcation be
conducted within a period of 8 weeks from the date of the
said order in respect of the area falling in three patches of
the Jilling estate, wherein the density of forest appears to be
40% or more. The Court Commissioner has found that about
8.5 hectares out of the entire Estate, i.e. 36 hectares-
constituting Jilling Estate, appears to have a high density of
forest cover in the range of 40% or more. The Supreme
Court directed the conduct of survey and demarcation in
terms of the direction contained in Clause (vi) of the
conclusions drawn in the report of the Court Commissioner
Shri Bikram Singh Sajwan. The said demarcation was
necessary to determine, whether the same would,
eventually, be classified as "Deemed Forest" in terms of the
judgment passed by the Supreme Court in T.N.
Godavarman vs. Union of India and others [WP
(Appeal) No. 202 of 1995, decided on 12.12.1996];
Lafarge Umiam Mining Pvt. Ltd. vs. Union of India
(2011) 7 SCC 338 and; Anand Arya and another vs.
Union of India and others (I.A.No.2609-2610 of 2009 in
WP (Civil) No. 202 of 1995).
3. The State has filed, what is claimed to be, a
Compliance Affidavit of the Divisional Forest Officer (DFO,
Nainital). The said Affidavit has not complied with either
Supreme Court's order, or our order, inasmuch as, no
demarcation has been carried out. The only exercise carried
out is to identify the different kinds of trees found in
different Khasra Numbers.
4. In our view, the said non-compliance of the order
of the Supreme Court as well as our order constitutes
contempt of Court. The direction to carry-out survey and
demarcation was issued by the Supreme Court as early as
on 11.02.2020. However, before we proceed to take action
under the Contempt of Courts Act against the erring officers,
we consider it appropriate to grant them one more
opportunity to strictly comply with the order passed by the
Supreme Court as well as by us on 20.03.2020. Compliance
be made positively within the next two weeks, and a report
in that regard be filed soon thereafter.
IA Nos. 4401 & 4402 of 2022
5. Issue Notice.
6. Mr. Manoj Kumar learned Standing Counsel for
the Union of India / respondent No. 1, appears and accepts
notice.
7. Mr. Pradeep Joshi, learned Additional Chief
Standing Counsel for the State of Uttarakhand / respondent
No.2, appears and accepts notice.
8. Mr. Vikas Srivastava and Mr. Akshay Pradhan,
learned counsel for respondent Nos. 3 & 4, appear and
accept notice.
9. Let replies to these Applications be filed by all the respondents within two weeks.
10. Rejoinder, if any, be filed before the next date.
11. The petitioner has placed on record, along with IA No. 4401 of 2022, the pictures of the Google Map of the area concerned. The position-which is shown to exist in 2015, 2018 and 2022 demonstrates that the green cover between 2015-2018 appears to have been substantially reduced. Even between 2018-2022, it appears that even in the area of having dense population of trees, roads have been constructed / broadened and extended.
12. Since we are looking at Google Map pictures, our conclusion, obviously, cannot be final. However, for prima facie evaluation, we certainly can take notice of these pictures. These pictures show that even in the dense tree cover area, developmental activity has been undertaken as the roads / paths appear broader, clearly defined, and extended in their length. The three pictures of 2015, 2018 and 2022 produced by the petitioner along with the Application at Page 290 of the record are as follows:-
13. The petitioner has also placed on record, along
with IA No. 4402 of 2022, an Inspection Report dated
prepared by the Surveyor, Geology and Mining Unit
Haldwani. This shows that respondent Nos. 3 & 4 employed
a JCB machine to carry-out development activities in the
area. Admittedly, no permission to use the JCB machine
was obtained by the said respondents, or the Contractor
employed by them.
14. Learned counsel for respondent Nos. 3 & 4 states
that JCB machine was used for seven days only for the
purpose of leveling the ground. Consequently, a fine of Rs.
4 Lacs was imposed for the unauthorized use of JCB
machine, which has also been paid by the respondents or
their Contractor.
15. The Inspection Report prepared by the Surveyor,
Geology and Mining Unit Haldwani, notes that sanctioned
map and documents were not produced at site sanctioned
by the competent Authority for the project in that area. To
this, the submission of the learned counsel for respondent
Nos. 3 and 4 is that since the site in question is at a
distance of more than 200 meters from the Highway, no
sanctioning of plan is required by the respondents.
16. Considering the aforesaid aspects, since the issue
of Deemed Forest in the area admeasuring 8.5 hectares or
thereabout, is still pending consideration and since prima
facie it appears that respondent Nos. 3 and 4 have carried
out development activities, including in the said 8.5
hectares' area, which has dense tree cover in excess of
40%, we are inclined to direct a fresh inspection of the
entire Jilling Estate to be conducted, so that a report is
available for the Court to proceed further in the matter.
17. We were inclined to appoint Shri Bikram Singh
Sajwan as the Court Commissioner, since he had conducted
the earlier inspection as a Court Commissioner, and he has
first-hand knowledge of the topography and the
characteristics of the area. Unfortunately, he is not in a
position to complete the task early, and would require 6 to 8
weeks, as indicated by him to the parties today.
Accordingly, we appoint Dr. Dvijendra Kumar Sharma, IFS
(Retd.), R/o C-103, Ispatika Apartments, Sector-4, Plot No.
29, Dwarka, Delhi-110078 (Having Mobile No. 9899761167)
as the Court Commissioner. The Court Commissioner shall
carry-out the local physical on-the-spot inspection and
furnish a report before us, particularly stating as to whether
respondent Nos. 3 & 4 have carried-out any activity in the
area admeasuring 8.5 hectares or thereabout, which may
eventually be declared as a Deemed Forest. We also
request him to inspect the development activities carried-
out by respondent Nos. 3 & 4 in the area falling outside the
8.5 hectares, but within 36 hectares constituting Jilling
Estate, and to report whether the said developmental
activities have been undertaken in violation of any of the
norms/ Rules / Regulations, or without any permission,
which they were obliged to obtain. The inspection shall be
carried out by the Court Commissioner as early as possible,
and the same be completed within the next two weeks. He
shall be provided with all the relevant record by the parties,
including the inspection report of Shri Bikram Singh Sajwan,
who had earlier carried-out the local inspection. A
responsible officer, nominated by the District Magistrate,
Nainital; a Nominee of the Conservator of Forest, and the
DFO, Nainital shall remain present when the inspection is
carried-out, and all assistance shall be provided to the Court
Commissioner for carrying-out the inspection. The
Commissioner shall also have photographs taken, wherever
he considers it necessary for explaining the report. The
Court Commissioner shall not adjourn the proceedings on
the request of either of the parties, or authorities, and they
shall not seek any accommodation in that regard. The fees
of the Court Commissioner is fixed at Rs. 2 Lacs to be
shared equally by the petitioner on one hand, and
respondent Nos. 3 & 4 on the other hand.
18. The representatives of the petitioner and
respondent Nos. 3 & 4 shall also remain present during the
inspection.
19. Till the next date, all further development /
construction activities in Jilling Estate shall remain stayed.
20. Let notice issue to respondent No.5, returnable by
15.12.2022.
21. List on 15.12.2022. No adjournment shall be
granted on the next date.
22. Liberty is given to mention on the next date, in
case the case is lower down in the list.
________________ VIPIN SANGHI, C.J.
____________ R.C. KHULBE, J.
Dt: 23rd November, 2022 Rathour
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!