Wednesday, 13, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

ARBAP/14/2022
2022 Latest Caselaw 1929 UK

Citation : 2022 Latest Caselaw 1929 UK
Judgement Date : 1 July, 2022

Uttarakhand High Court
ARBAP/14/2022 on 1 July, 2022
      IN THE HIGH COURT OF UTTARAKHAND
                  AT NAINITAL

       THE HON'BLE THE CHIEF JUSTICE SRI VIPIN SANGHI

           ARBITRATION APPLICATION NO. 14 OF 2022

                            1st July, 2022

Between:

M/s Piyush Infratech Pvt. Ltd.            ...... Applicant/Petitioner

and

Uttarakhand Jal Vidhut Nigam
Limited and another                       ......          Respondents



Counsel for the applicant     :     Mr. Prateek     Tripathi,   learned
                                    counsel

Counsel for the respondents   :     Mr.  Vinay     Kumar,   learned
                                    counsel for respondent No. 1

                                    Mr.   B.S.   Parihar,   learned
                                    Standing Counsel for the State /
                                    respondent No. 2



The Court made the following:


JUDGMENT:

The applicant has preferred the present

application under Section 11(6) of the Arbitration and

Conciliation Act to seek appointment of an Arbitrator to

adjudicate the disputes between the parties arisen out of

agreement no. 06/DGM (CM-BV) Maneri/13-14 dated

25.02.2014.

2) The applicant was awarded the said contract in

response to the tender floated by the respondent No. 1

for construction of protection wall around reservoir rim

of Joshiyara Barrage of Maneri Bhali Stage- II, HEP at

Uttarkashi.

3) It is the case of the applicant that the disputes

have arisen between the parties in relation to the

performance of the work under the contract. The

contract between the parties contains an arbitration

agreement in Clause 55, according to which, all question

of disputes relating to the meaning of the specification

design, drawing and instructions as to the quality of

workmanship or materials used on the work or as to any

other question claim, right, matter or thing, whatsoever

in any way arising out of or relating to the contract,

designs, drawings, specifications, estimates,

instructions, orders or the condition or otherwise

concerning the work, or the execution or failure to

execute the same, shall be adjudicated in accordance

with the provisions of the Arbitration and Conciliation

Act. The agreement, inter alia, provides that for claims

upto rupees ten crores, the case shall be referred to sole

Arbitrator to be appointed by the Principal Secretary /

Secretary (Energy) GoU. However, where claims exceed

rupees ten crores, a three member Arbitral penal shall

be constituted for arbitration, one to be nominated by

the contractor, the second to be nominated by UJVNL,

and the third by mutual understanding / consensus of

both the nominated arbitrator.

4) The admitted position is that despite

invocation of arbitration on 09.10.2020 by the applicant,

the respondents did not nominate an Arbitrator. Even

the applicant did not nominate one Arbitrator in terms of

the aforesaid agreement. Since the matter has not

proceeded, the applicant has now preferred this

application.

5) Learned counsels for the respondents do not

dispute the factum of the applicant being awarded the

contract in question, as also the factum of the arbitration

agreement contained in the General Conditions of

Contract. It is not disputed that disputes have arisen

between the parties which are referable to Arbitrator. It

is, however, pointed out by learned counsel for the

respondents that since the claims of applicant are in

excess of rupees ten crores, under the arbitration

agreement a three member Arbitral Tribunal is required

to be constituted. Since the parties did not act in terms

of the arbitration agreement by nominating one

arbitrator each, I am inclined to appoint a sole Arbitrator

to adjudicate the dispute between the parties.

6) Accordingly, the Arbitration Application is

allowed. I appoint Mr. Justice B.S. Verma, (Retd.)

Judge, Uttarakhand High Court, as the sole Arbitrator to

adjudicate the disputes which have arisen between the

parties under the aforesaid agreement.

________________ VIPIN SANGHI, C.J.

Dt: 1st July, 2022 Negi

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter