Sunday, 17, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Sri Arun Kumar Dey vs The Oil And Natural Gas Corporation ...
2025 Latest Caselaw 144 Tri

Citation : 2025 Latest Caselaw 144 Tri
Judgement Date : 11 July, 2025

Tripura High Court

Sri Arun Kumar Dey vs The Oil And Natural Gas Corporation ... on 11 July, 2025

                                 Page 1 of 11




                      HIGH COURT OF TRIPURA
                            AGARTALA

                            Arb. P. No.5 of 2025

Sri Arun Kumar Dey, Contractor, son of Late Biraj Mohan Dey, resident of
A.D. Nagar, Police Line, P.O. A. D. Nagar-799003, P.S. A. D. Nagar,
District-West Tripura;
                                                        ......... Petitioner(s).
                                VERSUS
1. The Oil and Natural Gas Corporation Limited (ONGC), Tripura Asset,
Badharghat Complex, Agartala, P.O. ONGC-799014, P.S. - Amtali,
District-West Tripura, represented by the Executive Director;

2. The Chief Engineer (Civil), Oil and Natural Gas Corporation Limited
(ONGC), Tripura Asset, Badharghat Complex, Agartala, P.O. ONGC-
799014, P.S. - Amtali, District-West Tripura;
                                                  ......... Respondent(s).
For Petitioner(s)               : Mr. Abhijit Sengupta, Advocate.
For Respondent(s)               : Mr. Jyotirmoy Das, Advocate.

 HON'BLE THE CHIEF JUSTICE MR. APARESH KUMAR SINGH

                                   Order
11/07/2025

Heard Mr. Abhijit Sengupta, learned counsel for the petitioner

and Mr. Jyotirmoy Das, for the respondents.

2. Petitioner has invoked Clause 25.1.12 of the agreement dated

27.01.2022 entered into between the parties pursuant to tender No.TC2EC

21003 floated for execution of the work 'Board purchase for construction of

seven numbers of drill sites, its drill site accommodation and its approach

road for drilling for exploratory location of Tripura Asset, Oil and Natural

Gas Corporation Limited (for short, ONGC)'. Petitioner was awarded work

for execution of three numbers of drill sites for a total value of

Rs.8,56,33,802/- i.e. Rs.2,85,44,600/- for each site. The stipulated period of

the work was 12 months from the date of handing over of the first site. The

agreement was executed on 27.01.2022. Petitioner deposited performance

bank guarantee of Rs.25,69,015/- on 07.12.2021 in favour of GM

(Mechanical), I/C, Tender and Technical Cell Engineering Service, ONGC,

Tripura Asset. However, petitioner was handed over only two numbers of

drill sites, namely, BMST and ROBJ.

3. It is submitted by learned counsel for the petitioner that

petitioner completed the said work to the satisfaction of the ONGC and

handed over two sites to them. Though petitioner submitted bank guarantee

for three sites but third site was not handed over to him till then. Petitioner

made reminders for handing over the third site as a result of which he had

been incurring overhead expenses. He was informed vide letter dated

07.06.2024 that the third site will not be handed over to him since the

contract period was for one year which is already over. Petitioner denied the

allegations vide his letter dated 30.08.2024 (Annexure-4). Petitioner claimed

10% of the expected profit for non-execution of the work amounting to

Rs.28,54,460/- from the respondent-ONGC. Petitioner submitted his demand

contained in letter dated 31.08.2024 (Annexure-5) for a claim of

Rs.33,34,460/- for loss of profit and remuneration of site engineer and

supervisor. Thereafter, he submitted an application for referring the dispute

to the respondent-ONGC under Arbitration Clause 25.1.12 (Annexure-6)

dated 14.11.2024.

4. The respondent-ONGC asked the petitioner to submit

application for mediation/re-conciliation vide communication dated

07.01.2025. On 03.05.2024 petitioner found that an amount of

Rs.46,00,069.85/- was credited to his account against the bill dated

21.03.2024 but they were short in payment of his full bills. On verification it

was found that an amount of Rs.77,55,760/- has been deducted from his bills

without assigning any reason. Thereafter, petitioner filed a writ petition

bearing WP(C) No.500 of 2024 which was disposed of vide judgment dated

26.07.2024 directing the respondent-ONGC to consider his case in the light

of his legal notice dated 14.05.2024 within a period of two months

(Annexure-11). The respondent-ONGC replied vide communication dated

06.11.2024 that the amount of Rs.77,55,760/- has rightly been recovered

from his bills as per the terms of the contract (Annexure-12).

5. Petitioner again submitted an application for reference of the

dispute for arbitration under Clause 25.1.12 vide letter 18.01.2025

(Annexure-14). The respondents have once again asked him to submit

application for conciliation/mediation vide letter dated 12.02.2025

(Annexure-15). However, learned counsel for the petitioner submits that

since the petitioner has opted to invoke the Arbitration Clause he is not

inclined to go for mediation/conciliation through Outside Expert Committee

(OEC). The details of the disputes have been furnished at paragraph 6 in the

form of a chart. Earlier, the petitioner had approached this Court in

Arbitration Petition No.01 of 2025 for reference of the dispute to an

independent arbitrator but the same was withdrawn vide order dated

19.02.2025 as the entire claims were not incorporated in the petition.

Thereafter, the present petition has been filed by the petitioner.

6. Learned counsel for the petitioner submits that in these facts

and circumstances in view of the Arbitration Clause entered into between the

parties, since the respondents have not nominated an arbitrator he has been

compelled to approach this Court under Section 11(6) of the Arbitration and

Conciliation Act, 1996.

7. Respondents have appeared on notice and filed their counter-

affidavit. Mr. Jyotirmoy Das, learned counsel for the respondents has

referred to the contents of the counter-affidavit and submitted that the

petitioner had served a legal Demand Notice under Section 80 (1) on the

Executive Director, Respondent ONGC through his Advocate on 30.03.2024

for handing over of the 3rd drill site as per the contract when the contract

period was over and termination of contract already affected much earlier,

under Clause-40 of General Conditions of Contract (GCC, for short).

8. On receipt of the reply of that Demand Notice issued by ONGC

on 07.06.2024, wherein the demand for handing over of 3 rd drill site to the

contractor was rejected on the ground of expiry period of the contract and

also having his doubtful credibility, the contractor then by a letter dated

30.08.2024 had shifted his demand for handing over the 3rd drill site and

tried to defend himself by simply denying and disputing the factual

allegations of inferior workmanship, already verified against him by a team

of engineers headed by ONGC Vigilance Department.

9. The petitioner then by a demand notice dated 31.08.2024

claimed for the payment of infrastructure expenses on overhead cost, being

the salary for Supervisors and Site Engineers, amounting to Rs. 4,80,000.00

and Loss of profit @10% on the 1/3rd total contract amount for the 3rd drill

site amounting to Rs. 28,54,460.00 and the total amount of claim of

Rs.33,34,460.00 was raised.

10. Respondents contend that after expiry of the contract period

such a claim for the above infrastructure expenses for the period from

11.01.2022 to 10.01.2023 have been raised when whole of his infrastructure

set up was already engaged for execution of the other two drill sites namely

ROBJ and BMST. Therefore, no question arose for deployment of

infrastructure during that period of contract for the 3rd drill site. Moreover,

the contractor never approached the ONGC authority within the contract

validity period to take over the 3rd drill site. The contractor never prayed for

any extension of the contract period nor the ONGC authority has exercised

its option to extend the contract period by issuing any order. The agreement

is automatically terminated once it expires.

11. The contractor, after submitting his demand notice dated

31.08.2024, i.e. after the expiry of contract period, served another notice

invoking arbitration Clause 25.1.12 of the contract without waiting for the

response from the ONGC authority. The petitioner, thereafter hastily has

approached this Court vide petition No. Arb.P.01/2025 filed on 10/01/2025,

under Section 11(6) for appointment of an impartial arbitrator for

adjudication of that particular claim/dispute.

12. The above-mentioned dispute was not an arbitrable dispute as is

an 'Excepted Matter' as per the contract clause No. 40.1 and 40.8 of GCC.

Moreover, the contractor after receipt of payment advice amounting to

Rs.46,00,069.85 dated 16/04/2024 against 2nd RA Bill, served a demand

notice on ONGC dated 14.05.2024 claiming the refund of withheld amount

of Rs.77,55,760.15 which the respondent-ONGC rejected vide letter dated

06.11.2024. Therefore, this dispute already existed before filing the petition

Arb.P.01/2025 on 10.01.2025.

13. The petitioner approached this court by making the false plea

that 'certain more disputes have cropped up during this period' for

withdrawal of Arb.P.01/2025 with liberty to file a fresh petition. To cover up

the circumstances and to tag along with the earlier dispute the petitioner

served another notice again on 18.01.2025, repeatedly invoking the

arbitration clause for the same contract in order to approach this Court under

section 11(6) of the Arbitration and Conciliation Act, 1996.

14. Mr. Jyotirmoy Das, learned counsel for the respondents,

submits that the contractor has been lackadaisical in his approach in

handling the contract. The ROBJ drill site upon completion of construction

was handed over to ONGC on 25.4.2023; Post Rig building works were

completed on 14.05.2023 and the BMST drill site was handed over on

20.05.2023 after retrofitting the RCC structure. But due to inferior quality of

workmanship in the RCC work, huge horizontal crack developed on the Rig

foundation of BMST drill site, even before the drilling rig could be deployed

on the foundation. The matter was so serious that a vigilance inquiry was

conducted. On inspection by the technical team of engineers and Vigilance

department of ONGC Tripura Asset, it was found, that the failure has

happened due to inferior quality of workmanship by the contractor without

following the engineering standard and working procedure.

15. The delay in execution of the contract has attracted the Clause -

2 of GCC. Accordingly, the recovery was made from the contractor of a

sum equivalent to ½ % (half percent) of the contract price/work subject to

maximum of 10% by way of liquidated damages and withheld from the 2nd

RA Bill. Under paragraph No.12 of the counter-affidavit the respondents

have by way of tabular chart enclosed the total amount of Rs.77,55,760.15/-

recovered against the contractor for bad workmanship and liquidated

damages etc.

16. Learned counsel for the respondents submits that the petitioner

was fully aware of the other issues relating to non-handing over of the 3rd

drill site during the validity of the contract period and had in fact referred to

it in his notice dated 31.08.2024 (Annexure-5) while approaching this Court

in Arb.P.01/2025. However, he has sought to withdraw Arb.P.01/2025 to

raise additional claim in respect of the 3 rd drill site by issuing another notice

dated 18.01.2025 for reference of the dispute under Clause 25.1.12 of the

agreement. It is submitted that the petitioner cannot be allowed to improve

upon its claim relating to existing dispute as it is in teeth of arbitration

Clause 25.1.12. Moreover, the approach of the petitioner in withdrawing

Arb.P.01/2025 and thereafter raising additional claims for reference to

arbitration under the present arbitration petition is mala fide.

17. Mr. Abhijit Sengupta, learned counsel for the petitioner, has

sought to explain that the earlier arbitration application was made after

invocation of the arbitration clause in terms of notice dated 14.11.2024

(Annexure-6). He submitted that in the said notice also the petitioner has

taken a plea that the ONGC was bound to hand over the three numbers of

sites immediately after work order was issued but it failed to deliver one site

valued at Rs.2,85,44,600/- to him. Therefore, it had committed breach of

contract with him. Learned counsel for the petitioner also submits that the

petitioner had not raised any further additional claim in the present

arbitration petition. If that be so there was no reason to withdraw the first

arbitration petition.

18. I have considered the submission of the learned counsel for the

parties and taken note of the relevant materials placed from record. The

chronology of the events pleaded by the parties captured in the previous

paragraphs of this order need no repetition. In order to appreciate the

controversy, it is pertinent to refer to Clause 25.2.1 which falls under the

head 'Arbitration and Conciliation' under Clause - 25. Clause 25.1 provides

that if any dispute, difference, question or disagreement arises between the

parties hereto or their respective representatives or assignees, in connection

with construction, meaning, operation, effect, interpretation of the contract

or breach thereof which parties are unable to settle mutually, the same may

first be referred to conciliation through Outside Expert Committee ("OEC")

to be constituted by CMD, ONGC as provided thereunder. Clause 25.1.12

provides that if the parties are not able to resolve the dispute through OEC or

do not opt for conciliation through OEC, the party may invoke arbitration

clause as provided in the contract. Clause 25.2 provides for arbitration

(applicable in case of supply order/ contracts with firms, other than Public

Sector Enterprises) (Not applicable in cases valuing less than Rs.5 lakhs). It

further provides that Except as otherwise provided elsewhere in the contract,

if any dispute, difference, question or disagreement arises between the

parties hereto or their respective representatives or assignees, in connection

with construction, meaning, operation, effect, interpretation of the contract

or breach thereof which parties are unable to settle mutually, the same shall

be referred to Arbitration as provided thereunder.

19. The clause 25.2.1 which has been invoked by the petitioner,

reads as under:

"25.2.1 A party wishing to commence arbitration proceeding shall invoke Arbitration Clause by giving 60 days notice to the other party. The notice invoking arbitration shall specify all the points of disputes with details of the amount claimed to be referred to arbitration at the time of invocation of arbitration and not thereafter. If the claim is in foreign currency, the claimant shall indicate its value in Indian Rupee for the purpose of constitution of the arbitral tribunal."

A careful reading of the aforesaid provision clearly indicates

that the notice invoking arbitration shall specify all the points of disputes

with details of the amount claimed to be referred to arbitration at the time of

invocation of arbitration and not thereafter.

20. Clause 25.2.2 provides for the number of the arbitrators to be

appointed depending upon the value of the claim.

21. The chronology of the dates and events referred to hereinabove

indicates that the petitioner has initially approached this Court in WP(C)

No.500 of 2024 against the amount deducted from his bills allegedly without

any reason. On the basis of the direction passed by the writ Court the legal

notice issued by the petitioner was replied by the ONGC vide

communication dated 06.11.2024 stating that an amount of Rs.77,55,760/-

has rightly been recovered from his bills as per the terms of the contract

(Annexure-12). Petitioner had thereafter, invoked the jurisdiction of this

Court under Section 11(6) of the Arbitration and Conciliation Act, 1996 on

the basis of the dispute raised vide letter dated 14.11.2024 (Annexure-6)

upon the respondent ONGC invoking arbitration Clause 25.1.12. The said

petition was later on withdrawn by the petitioner with a plea that the entire

claims were not incorporated in that petition. In order to improve upon his

case, petitioner had in the meantime issued another arbitration notice under

Clause 25.1.12 dated 18.01.2025 (Annexure-14). That was also replied by

the respondents asking him to submit to conciliation mediation which the

petitioner refused as he had opted to invoke the Arbitration Clause and

chosen to remain outside the mediation/conciliation process through Outside

Expert Committee (OEC). The details of the disputes were furnished at

paragraph-6 in the form of a chart. The aforesaid background facts indicate

that the petitioner has indulged in raising arbitration claims through multiple

notices served upon the respondent-ONGC under Clause 25.1.12. This is

impermissible in view of clause 25.1.12 quoted hereinabove. Petitioner was

required to specify all the points of the disputes with details of the amount to

be referred to arbitration at the time of invocation of arbitration and not

thereafter. In the earlier arbitration application based upon the notice dated

14.11.2024, the respondents had filed a counter affidavit and taking a

particular stand. The petitioner, perhaps becoming wise, chose to improve

upon his case by withdrawing Arb.P.01/2025 to present a fresh petition as

his entire claims were not incorporated in the said petition. For this purpose,

he also had issued another notice invoking arbitration Clause 25.1.12 vide

letter dated 18.01.2025 (Annexure-14) which was not permissible.

Arb.P.01/2025 was permitted to be withdrawn on the request of the

petitioner with liberty. However, the withdrawal of the writ petition with

liberty could not override the specific arbitration clause agreed between the

parties under the agreement in question. Clause 25.1.12 provides that the

notice invoking arbitration should specify all the points of disputes with

details of amount claimed to be referred to arbitration at the time of

invocation of the arbitration and not thereafter.

22. Perusal of the notices dated 14.11.2024 and 18.01.2025 would

also give an impression that the petitioner has raised further claim than

originally raised in his notice dated 14.11.2024 which is impermissible

under the arbitration clause. Respondents are therefore right in contending

that the petitioner has tried to improve upon his claim despite being

conscious for the reasons for recovery of the amount of Rs.77,55,760.15

from his outstanding bills and also the reasons for non-handing over of the

3rd drill site. In such circumstances, the present petition seeking appointment

of an independent arbitrator by successive notice issued in teeth of clause

25.1.12 cannot be allowed. The approach of the petitioner in seeking

invocation of arbitration clause on repeated occasions under the same

agreement by raising different claims is misconceived.

Accordingly, the instant petition is dismissed.

Pending application(s), if any, shall stand disposed of.

(APARESH KUMAR SINGH), CJ

Munna MUNNA SAHA Digitally signed by MUNNA SAHA Date: 2025.07.14 15:56:03 +05'30'

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 

LatestLaws Partner Event : IJJ

 
 
Latestlaws Newsletter