Thursday, 14, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

The State Of Tripura vs Shri Raja Raw Ghosh
2024 Latest Caselaw 765 Tri

Citation : 2024 Latest Caselaw 765 Tri
Judgement Date : 15 May, 2024

Tripura High Court

The State Of Tripura vs Shri Raja Raw Ghosh on 15 May, 2024

Author: Arindam Lodh

Bench: Arindam Lodh

                                  Page 1 of 7




                       HIGH COURT OF TRIPURA
                             AGARTALA

                            Arb.A. No.5 of 2022
1. The State of Tripura, represented by the Secretary, Department of PWD,
   Government of Tripura.
2. Executive Engineer, PWD (R&B), Bisramganj Division, Bisramganj,
   Sepahijala District.
                                                         ......... Appellant (s)
                           VERSUS

Shri Raja Raw Ghosh, Contractor, East Bank of Jagannath Dighi, P.O.
Radhakishorepur, Udaipur, Gomati Tripura, Pin-799120.
                                                      ......... Respondent(s)
For Appellant (s)        :     Mr. P. Gautam, Advocate.
For Respondent(s)        :     Mr. A. Sengupta, Advocate.
      HON'BLE THE CHIEF JUSTICE MR. APARESH KUMAR SINGH
              HON'BLE MR. JUSTICE ARINDAM LODH

                         Date of hearing : 15.05.2024
                       Whether Fit for Reporting : NO


                     JUDGMENT & ORDER (ORAL)

Heard Mr. P. Gautam, learned counsel for the appellants and Mr. A.

Sengupta, learned counsel for the respondent.

[2] The instant appeal under Section 37(1)(c) of Arbitration and

Conciliation Act, 1996 read with Section 13(1A) of the Commercial Courts Act,

2015 seeks to challenge the judgment dated 25.02.2022 passed in Civil Misc.

(Arbitration) No.13 of 2018 by the Judge, District Commercial Court, West

Tripura, Agartala whereby the application under Section 34 of the Arbitration

and Conciliation Act, 1996 (for short, the Act of 1996) preferred by the

appellant-State of Tripura has been dismissed without any interference in the

impugned award.

[3] The brief facts which are borne from the record and have been also

referred to in paragraph-2 of the impugned judgment convey that the dispute

revolved around the agreement dated 16.07.2007 between the contractor and the

appellant-State of Tripura for construction of three numbers of RCC bridge out of

which two numbers of bridge were over river „Burimaa‟ at Takarjala and

Jampuijala market and another was over Senaigang-cherra at Gabordi under the

PWD(R&B), Bisramganj Division. The work order was issued on 29.07.2007

and the works were to be commenced from the 15th day of issuance of work order

and were to be completed within thirty months, i.e. on or before 12.05.2010. The

contractor could not complete the work within the scheduled time and

accordingly time was extended. The contractor, however, completed the work on

25.12.2014 but he failed to erect the Baily bridge for making diversion.

Thereafter, the contractor submitted his claims which was not allowed by the

employer. Consequently, on an application made under Section 11(6) of the Act

of 1996 before this Court, the matter was referred for adjudication to an

independent Arbitrator. The Arbitrator, upon consideration of the pleadings and

material documents placed on record, framed the following issues for

consideration:

"In course of hearing, the following issues were framed:

1) Whether the claimant is entitled to get balance payment due on account of value of works done in the final bill (since previous) or any higher or lower amount as per record of the respondent?

2) Whether the claimant is entitled to get balance payment due on account of price escalation as per clause 10 CC of the agreement?

3) Whether the claimant is entitled to get damages suffered for longer retention of site establishment, staff, plants and machineries etc?

4) Whether the claimant is entitled to get refund of the excess amount deducted as TST /TVAT in gross violation of provision of the agreement?

5) Whether the claimant is entitled to get refund of security deposit as per record of respondent?

6) Whether the claimant is entitled to get interest @18% p.a. on the demanded sum w.e.f. 01.02.2016 till actual date of payment?

7) Whether the claimant is entitled to cost of Arbitration proceedings and incidental thereto?

Issue on the counter claim of the respondent was framed as follows:

i) Whether the contractor breached the condition of the contract by non supply of 3 Nos. of portable bailey bridge?"

[4] The learned Arbitrator, upon consideration of the rival submissions

of the parties and the materials on record, rendered the following award:

"The total amount of award is stated below:


                      Sl.    Claim    Particular of Amount               Amount allowed
                      No.    no/      claim/         claimed Rs.         Rs
                             Issue    counter
                             no       claim
                      1      1        Balance        13,55,857.00        6,56,067.00 Six
                                      payment of Thirteen lakh           lakh fifty six
                                      final bill     fifty        five   thousand sixty
                                                     thousand eight      seven only
                                                     hundred fifty
                                                     seven only
                      2      2        Escallation 1,02,36,699.00         1,02,36,699.00
                                      as         per One crore two       One crore two
                                      clause      10 lakh thirtysix      lakh    thirtysix
                                      CC             thousand six        thousand      six
                                                     hundred ninety      hundred ninety
                                                     nine only           nine only
                      3      3        Damages        45,48,000.00        32,29,000.00
                                      for longer Forty five lakh         Thirty two lakh
                                      retention of forty        eight    twenty       nine
                                      men,           thousand only       thousand only
                                      machineries
                      4      4        Refund of 9,19,480.00              9,19,480.00
                                      excess         Nine        lakh    Nine        lakh
                                      deduction      nineteen            nineteen
                                      of TVAT        thousand four       thousand four
                                                     hundred eighty      hundred eighty
                                                     only                only
                      5      5        Refund of 71,47,598.00             71,47,598.00
                                      security       Seventy one         Seventy      one
                                      deposit        lakh       forty    lakh forty seven
                                                     seven thousand      thousand     five
                                                     five hundred        hundred ninety
                                                     ninety     eight    eight only
                                                     only
                      6      6        Interest       As may be           Simple interest
                                                     decided by the      on the total
                                                     Arbitrator          amount awarded
                                                                         at the current
                                                                         rate of interest
                                                                         plus 2% on
                                                                         higher       side,
                                                                         w.e.f. the date of
                                                                         award if the
                                                                         amount is not
                                                                         paid       within





                                                                    3(three) months
                                                                    from the date of
                                                                    communication
                                                                    of award to the
                                                                    respondent till
                                                                    payment.
                      7     7         Cost        of As may be Nil
                                      arbitration    decided by the
                                                     Arbitrator
                                                                      2,21,88,844.00

(Rupees two crore twenty one lakh eighty eight thousand eight hundred forty four only)".

[5] Being aggrieved by findings on certain Issue Nos. (2), (3) and (5)

the State of Tripura preferred an objection application under Section 34 of the

Act of 1996. It was submitted that the impugned findings do not refer to the delay

of 927 days out of 1618 days caused by the contractor. Apart from that non

communication of decision of SPT bridge in place of Baily bridge was actually

attributable to the contractor. The contractor did not supply the components of

Baily bridge in time. The appellant-State of Tripura further contended that the

Arbitrator while deciding the Issue No.(3) awarded an amount of Rs.32,29,000/-

which is not permissible due to the fact that the claimant was responsible for the

delay and such fact was not considered by the Arbitrator. Apart from that the

Arbitrator had awarded an amount of Rs.71,47,598/- without considering the fact

that the contractor had not completed the work. That apart, the learned Arbitrator

had failed to frame any Issue on the counter claim filed by the appellant-State of

Tripura in view of Section 23(2-A )of the Arbitration Act.

[6] The learned Commercial Court in the major part of the judgment has

referred to the decisions of the Apex Court on the scope of interference in an

application under Section 34 of the Arbitration and Conciliation Act, 1996 and

summarily concluded at paragraph-7 as under:

"7. On the basis of the citation of law as referred to above coupled with the provisions of Section 34 of the Arbitration Act, it seems to us that the scheme and scope of the provisions of Section 34 of Arbitration Act aims at keeping

the supervisory roles of the court at minimum level, therefore, we cannot correct the errors so done by the arbitrator by entering into the merits of the case through re- appreciation of the materials on record by sitting as an Appellate Court, it can only be quashed leaving the parties to begin the arbitration again if it is desired. The issues so raised for and on behalf of the petitioner seeking interference of this court are related to merits of the case and do not come within the mischief of any of the grounds as enumerated in Section 34(2) or Section 34(2A) of the Arbitration Act and as such we are lacking in jurisdiction to interfere with the findings and decision so arrived at by the Arbitrator".

[7] Mr. P. Gautam, learned counsel for the appellant-State of Tripura

has assailed the impugned finding on the ground that there is no analysis in

respect of the findings rendered by the learned Arbitrator on Issue Nos. (2), (3)

and (5) which were specifically under challenge. The learned Arbitrator has

straightaway rendered his opinion that the Court under Section 34 exercised

supervisory role which cannot correct the errors of the Arbitrator by entering into

the merits of the case through re-appreciation of the materials on record. Learned

Court went on to observe that the Issues raised by the appellant are related to

merits of the case and do not come within the mischief of any of the grounds as

enumerated under Section 34(2) or Section 34(2A) of the Arbitration Act. As

such the application was dismissed.

[8] It is submitted that there are grounds of patent illegality raised on

behalf of the appellant which have not been properly considered and discussed.

The findings of the learned Commercial Court are, therefore, without proper

application of mind and without any reasons. As such, the impugned judgment

may be set aside.

[9] Mr. A. Sengupta, learned counsel for the respondent-contractor has

opposed the prayer and inter alia submitted that the decision of the learned

Commercial Court does not suffer from any errors calling for interference in

appeal under Section 37(1)(c) of the Act of 1996. The learned Court was right in

holding that the grounds raised by the appellant-State in respect of the findings of

the learned Arbitrator on Issue Nos. (2), (3) and (5) invite interference on the

merits of the findings rendered by the learned Arbitrator and are, therefore, not

amenable to challenge under Section 34(2A). Therefore, the impugned judgment

is proper in the eye of law and needs no interference.

[10] We have considered the submissions of the learned counsel for the

parties and taken note of the material pleadings placed from record. We have also

gone through the impugned judgment. We have taken note of the grounds of

challenge raised by the appellant-State on Issue No.(2), (3) and (5) rendered by

the learned Arbitrator. Unfortunately, the learned Commercial Court has not even

touched upon the findings rendered by the learned Arbitrator on any of these

Issues to come to a considered finding that the grounds of challenge are without

merit and border on entering into re-appreciation of the materials on record as an

appellate Court in the findings of the learned Arbitrator. The learned Court has

only referred to decisions rendered by the Apex Court such as in the case of (i)

Assam State Electricity Board vs Buildworth Private Ltd. reported in AIR 2017

SC 3336; (ii) G. Ramachandra Reddy & Company vs Union of India & Anr.

reported in (2009) 6 SCC 414 (iii) Delhi Airport Metro Express Pvt. Ltd. vs

Delhi Metro Rail Corporation Ltd. decided on 09.09.2021 before coming to a

conclusion straightaway at paragraph-7 of the impugned judgment which has

been extracted above that none of the grounds fall within the mischief under

Section 34(2) or Section 34(2A) of the Arbitration Act. We are afraid in the

absence of any analysis of the findings of the learned Arbitrator on the grounds

raised by the appellant-State, the conclusions rendered by the learned

Commercial Court are without any reason. Reasons are the soul of any judicial

order. It reflects the application of mind of the concerned Court to the Issue at

hand in the context of the facts and the relevant law applicable to the case of the

parties. It also enables the appellate Court to examine as to whether the reasons

are proper in the eye of law. Unfortunately, the learned Commercial Court seems

to have been completely oblivious of the requirement of proper adjudication on

the grounds available under Section 34(2) or 34(2A) of the Act of 1996 in such a

matter. Such an approach of the learned Commercial Court has unnecessarily led

to delay in proper adjudication of the disputes between the parties at the stage of

Section 34 application. It has led to the appeal under Section 37(1)(c) before this

Court. In the absence of any discussion or analysis of findings rendered by the

learned Arbitrator on the grounds of challenge raised by the appellant on Issue

Nos.(2), (3) and (5) by the learned Commercial Court, we are unable to scrutinize

the grounds raised by the appellant at this stage. The contours of jurisdiction

under Section 37(1)(c) of the Act of 1996 by this Court are further narrowed than

what is available under Section 34(2) of the Act of 1996. In such a situation, we

are left with no other option than to remand the matter to the learned Commercial

Court for fresh adjudication on the grounds raised by the appellant-State in

accordance with law within a reasonable time preferably 12(twelve) weeks from

the date of receipt of a copy of this judgment after giving due opportunity to the

parties.

Accordingly, the instant appeal is disposed of. Pending

application(s), if any, also stands disposed of.

(ARINDAM LODH), J                                                  (APARESH KUMAR SINGH), CJ



Munna S MUNNA SAHA

                     Date: 2024.05.22 16:29:30 +05'30'
 

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter