Citation : 2023 Latest Caselaw 309 Tri
Judgement Date : 18 April, 2023
Page 1 of 8
HIGH COURT OF TRIPURA
AGARTALA
W.A. No.105/2022
For Appellant(s) : Mr. Somik Deb, Sr. Advocate,
Mr. Tytan Debbarma, Advocate.
For Respondent(s) : Mr. P.K. Biswas, Sr. Advocate,
Mr. Arijit Bhowmik, Advocate, Mr. P. Majumder, Advocate, Ms. S. Debbarma, Advocate.
HON'BLE THE CHIEF JUSTICE MR. APARESH KUMAR SINGH HON'BLE MR. JUSTICE ARINDAM LODH
Order 18/04/2023
Considerable arguments have been advanced by the learned
counsel for the appellants, private respondent and the Municipal Corporation
taking us to the history of the litigation to its present stage. The report of the
learned Advocate Commissioner has been served upon the learned counsel
for the parties in terms of the order dated 15.02.2023.
The present appeal by the petitioner is against the judgment
dated 30.06.2022 whereby the learned Single Judge had dismissed the writ
petition on the ground of lack of locus standi of the petitioner/appellant. A
report of the present situation of deviations in the building of the private
respondent which were non-compoundable was brought on record in the writ
petition bearing letter No.171(A) dated 07.04.2022. Learned Single Judge
vide impugned judgment had upon consideration of rival submissions of the
parties and having heard the Municipal Commissioner who was present in
Court directed the Municipal Commissioner to look into the matter in its
entirety. An observation was made that the building had been constructed
after obtaining approval from the Agartala Municipal Corporation in
different periods in the years 1983 and thereafter and there has been a
change in the Municipal Rules periodically. The Commissioner was also
asked to consider all these aspects and analyze the permissible deviations.
He would also suggest the unofficial respondent regarding removing the
unauthorized construction by causing minimum damage to the property and
consider compounding of deviations as per law.
As per the private respondent, it had demolished certain part of
the deviations in the building earlier on 21.01.2020.
Be it noted here that initially the Case No.7(88)-UDD of 2016
instituted against the private respondent was decided by the Assistant
Municipal Commissioner and affirmed in appeal vide order dated
22.02.2018 by the Tribunal (Annexure-1 to the memo of appeal). The
challenge thereto by the private respondent in WP(C) No.371 of 2018 was
disposed of with certain directions upon the Assistant Commissioner,
Agartala Municipal Corporation to carry out an inspection of the subject
matter of the lis, i.e. house of the writ petitioner/private respondent herein to
ascertain the deviations from the original sanctioned municipal plan. The
private respondent/petitioner therein had undertaken to demolish all
constructions existing on the spot as found out in excess of the sanctioned
municipal plan at his own cost within a stipulated period. That undertaking
was taken on record. Thereafter, the private respondent approached this
Court in WP(C) No.196 of 2019 (Annexure-4 to the memo of appeal) which
got disposed of with the following observations and directions:
"[13] Having regard to the submission made by the learned counsel for the parties, this court is of the view that the building that was constructed in the year 1983 as per the approved plan and during its construction, no objection was raised from any quarters, should not be brought under the demolition exercise. However, so far the building that has been constructed in terms of the plan that was approved under No.HC/5024/16/AMC/4994-28 dated 30.04.2016 and the other approved plan (three storied) vide No.AMC/ EZ/ 21/ 3605/172810 dated 28.12.2017 and deviation from the plan has been demarcated the said exercise, the deviated part be demolished by the petitioner within a period of 15 (fifteen) days at his own expenses. For the purpose of demolition, Agartala Municipal Corporation shall take aid of the physical inspection team which shall identify that part of the building which has been constructed in terms of the said building plan dated 30.04.2016. The Municipal Corporation shall demarcate such parts of the building, which are constructed in deviation of the approved plan for purpose of demolition, if not already demolished by the petitioner, within a period of 15 (fifteen) days from the day of receipt of this order. The demolition by
the petitioner shall be completed within 15 (fifteen) days from the date of the said demarcation [the refurbished new report]. The petitioner shall receive a copy of the refurbished report in terms of this order.
[14] Agartala Municipal Corporation and the respondents No.2 and 3 are therefore directed to furnish the refurbished report of deviation to the petitioner within a period of 15 (fifteen) days from the day of receipt of this order. If the petitioner failed, for any reason, to demolish the unauthorized part, the respondents No.1, 2 and 3 shall execute the demolition at the expenses of the petitioner. The expenses may be recovered as the due to the Municipal Corporation. Such demolition will not purge the petitioner from the contempt action."
The private respondent again preferred WP(C) No.69 of 2020
which was dismissed as withdrawn vide order dated 22.02.2021. The
petitioner herein thereafter made a representation before the Agartala
Municipal Corporation on 18.09.2021 for implementation of the judgment
dated 20.06.2019 and 22.02.2021 in WP(C) No.196 of 2019 and WP(C)
No.69 of 2020 respectively and thereafter approached this Court by filing
Cont.Case(Civil) No.104 of 2021 for execution of the judgment dated
20.06.2019. The same was, however, dismissed as not pressed with liberty to
the petitioner to initiate appropriate action at law for execution of the said
judgment and order. Thereafter, the instant writ petition has been preferred
by the petitioner primarily for execution of the judgment passed earlier.
Learned counsel for the private respondent has referred to the
affidavit filed by the Municipal Corporation in WP(C) No.69 of 2020, in
particular paragraphs-7 and 8 in order to submit that the inspection that was
carried out in terms of this Court's orders dated 27.11.2018 and 20.06.2019
actually got the second floor building inspected inadvertently.
These events in the journey of this litigation are being noticed
hereinabove only to indicate that the stand of the Municipal Corporation has
also changed after the original order of the Assistant Municipal
Commissioner dated 03.09.2016 as affirmed in appeal by the Municipal
Appellate Tribunal. Taking this change in stand from time to time, it appears
that the learned Single Judge had directed the learned Municipal
Commissioner to consider the matter in entirety. By the previous order dated
09.12.2022 taking note of the nature of the dispute, a learned Advocate
Commissioner was appointed to inspect the disputed site and examine all the
records including the sanctioned plan of the private respondent and also to
verify up to what extent the building is extended in breach of the sanctioned
plan. He was also requested to examine as to how such extension affects the
free passage of air and lights to the building of the petitioner. The report has
been submitted and copies thereof have been served upon learned counsel
for the parties pursuant to the order dated 15.02.2023. The report is extracted
hereunder:
"In compliance of the order dated 09.12.2022 passed in W.A. No.105 of 2022 of the Hon'ble High Court of Tripura, I visited the disputed site on 24.12.2022 at about 11 hours, and I examined all the papers and sanctioned plan of the Private Respondent. I carefully inspect the building of Private respondent and the houses of the appellants. I took all the measurements in presence of the both the Appellants and Private Respondents. Photography also been taken by the profession photographer viz Sri Kamal Mitra from different angles of the disputed building as well as the houses of the Appellants. After taking measurement I prepared hand sketch map of the site in presence of both the parties. The Private Respondent signed in the said map but both the Appellants refused to put their signature as I have not worked according to their choice/directions and for that reason they denied to pay the fees as fixed by the Hon'ble Court. The details report is mentioned below:-
1. The difference between the houses of Appellant No.1 to the Private Respondent is 13′11′′ (Thirteen feet and eleven inches) boundary wall to boundary wall.
2. There is a 13′11′′ (Thirteen feet and eleven inches) wide road between the houses of the Appellant No.1, Sri Subrata Saha and the private Respondent. The said road is extended up to the main road in East-West direction. In the approach of the said road the house of the Appellant No.2 i.e. Sri Sankar Saha is situated.
3. That the Distance between the house of the Appellant No.2 i.e. Sri Sankar Saha and Private Respondent is 133′06′′ (one thirty three feet and six inches).
4. The houses of both the Appellants are no way connected within the boundary of the Private Respondent i.e. Sri Sambhunatha Saha. Houses of the Appellants are far away from the house of the Private Respondent.
5. That, there is a gap between disputed building of the private Respondent and his boundary is 3′06′′ (Three feet and Six inches), on the other hand the gap between the go down of Appellant No.1 i.e. Sri Subrata Saha and his boundary wall is 3′03′′ (Three feet and three inches).
6. That, the distance between dwelling house of Appellant No.1 i.e. Sri Subrata Saha and his boundary wall is 25′10′′ (Twenty five feet and ten inches).
7. That, the distance between the disputed building of the private Respondent viz Sri Sambhunath Saha and the house of the Appellant No.1 is 44′03′′ (Forty four feet and three inches).
8. That, there is no gap between the building of Appellant No.2 and his boundary in the Northern side.
According to Appellants, extension has been made in back side of the building of the Private Respondent. If it so, no way Appellants would be affected, because the back side of the disputed building is situated in the southern side of disputed building, it would more clear from my hand sketch map. I beg to say that only expert can say how far deviation has been made or not."
The sketch map in pencil in the handwriting of the learned
Advocate Commissioner is enclosed with the report.
Learned counsel for the petitioner has not disputed that there
exists a road of width of 13 feet 11 inches between the house of the private
respondent and the petitioner. At this stage, though we may not like to
observe as to the role of the petitioner in the present proceedings but taking
into consideration the last inspection report of the Assistant Municipal
Commissioner dated 07.04.2022 and the report of the learned Advocate
Commissioner dated 04.01.2023, we are of the view that the statutory
authority, i.e. the Municipal Corporation is required to come forth with a
clear stand on this issue as per their own inspection carried out earlier and
the by-laws governing the sanction of building plan under the Agartala
Municipal Corporation. The respondent-Corporation has to make it clear as
to how they intend to proceed in the matter. The statutory mandate upon the
Municipal Corporation to ensure that buildings are constructed as per the
sanctioned plan and no deviations beyond compoundable limits are
permitted to continue are required to be performed by them. In the
background of the conspectus of facts and circumstances taken note
hereinabove, learned counsel for the Corporation prays for and is allowed
10(ten) days time to come with a clear stand on this issue so that the matter
can be disposed of on the next date.
Let the case be listed on 02.05.2023.
(ARINDAM LODH), J (APARESH KUMAR SINGH), CJ Pulak
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!