Monday, 11, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Sri K. Jagan Mohan A1, Khammam Dist., And ... vs The State Of A.P., Rep. By Spl. P.P., ...
2025 Latest Caselaw 3202 Tel

Citation : 2025 Latest Caselaw 3202 Tel
Judgement Date : 19 March, 2025

Telangana High Court

Sri K. Jagan Mohan A1, Khammam Dist., And ... vs The State Of A.P., Rep. By Spl. P.P., ... on 19 March, 2025

             HON'BLE SRI JUSTICE K.SURENDER

         CRIMINAL APPEAL Nos.815 and 879 of 2010
COMMON JUDGMENT:

1. Criminal Appeal No.815 of 2010 is filed by appellants/A1

and A2, and Criminal Appeal No.879 of 2010 is filed by A4. The

appellants A1, A2, and A4 are questioning their conviction vide

judgment in C.C.No.29 of 2005 dated 30.06.2010, passed by the

Principal Special Judge for SPE and ACB, City Civil Courts,

Hyderabad.

2. Since both the appeals are filed questioning the same

judgment in C.C.No.29 of 2005, they are being heard together

and disposed off by way of this Common Judgment.

3. The appellants will be hereinafter referred to as A1, A2, and

A4 as mentioned in the trial Court. In all, A1 to A4 were tried by

the learned Special Judge. However, A3 was acquitted of all the

offences. The ACB did not prefer any appeal against the acquittal

of A3.

4. Heard Sri J.Manikanta Reddy, learned counsel for A1,

Mrs.D.Sangeetha Reddy, learned counsel for A2 and Sri M.Bala

Mohan Reddy, learned Special Public Prosecutor for ACB.

5. Briefly, the case of the prosecution is that, for the

improvement of the Erra Cheruvu of Lachagudem village, tenders

were called for and work was awarded to A-4, who is a President

of M/s.Tribal Labour Co-operative Society, Narayanapuram,

Khammam. The estimated value was Rs.4,79,000/-. Later on,

due to the representation by the villagers for widening of the top

width of the bund up to 3 Mts., to enable the movement of Carts

and Tractors, modified estimates were prepared for Rs.9,23,000/-

under a supplemental agreement dated 17.8.1993. After

execution of the improvement work to Erra Cheruvu at

Rs.4,79,000/-, the Ryots of Rajaboinagudem village submitted a

representation about the deficiency of work, and one Sri

Damodar Reddy (not examined) of the Area submitted a

complaint before A.P.Lokayuktha alleging irregularities in the

works. The Joint Director of A.P. Lokayukta Sri K.Narsing Rao

(not examined) was entrusted to enquire, and after enquiry, he

submitted a report to the Hon'ble Lokayukta. In turn, the report

was sent to the D.G., ACB to investigate into the allegations of

fraud. In turn, the D.G, ACB, issued proceedings to Sri

M.Lazarus (not examined), the then DSP, ACB, Warangal to

investigate and accordingly, Sri M.Lazarus registered the case

vide Crime No.14/ACB-WKH/2000 under Section 13(1)(d) r/w

Section 13(2) of the Act and under Section 477/A r/w Section 34

IPC. The case was entrusted to Sri G.Raghava Reddy (P.W.8),

Inspector of Police, ACB, Khammam for the purpose of

investigation and report.

6. During investigation, it was observed that the

measurements were recorded by A1 and the bill was prepared for

Rs.8,74,987.31ps. A2, D.E.E, Check measured and restricted the

amount to Rs.7,01,658.78 ps, and A3/E.E super checked and

further restricted it to Rs.4,04,249/-. After thorough verification

by Sri Chalamaiah (P.W.4), the then E.E., restricted the amount

to Rs.1,20,000/- since the work was found to be defective, both

quantitatively and qualitatively, and the said amount was paid to

contractor-A4 vide cheque dated 31.3.1994, and A4 accepted the

same under protest.

7. It is further the case that the M.Book disclosed that the

work was completed on 15.5.1993, whereas, the agreement for

enhanced estimates was entered into between A4 and S.E on

17.8.1993. After completion of the investigation, Inspector, ACB,

observed that the measurements recorded in the M.Book were

false, and the measurements were found to be recorded before

entering into the supplemental agreement. A charge sheet was

laid after completion of investigation against A1 to A4 for the

offences punishable under Sections 13(1)(d) r/w 15 of Prevention

of Corruption Act r/w Section 34 of IPC, Under Sections 420 and

477-A r/w Section 34 and Section 511 of IPC, against A1 to A3,

Under Section 420 r/w Section 511 of IPC against A4.

8. Charge was framed against the appellants for obtaining

pecuniary advantage to a tune of Rs.4,04,249/- during 1993-

1994, by recording false measurements in measurement books

even before entering into the supplemental agreement in respect

of the execution of the work for improvement of Erra Cheruvu of

Lachagudem Village. The said contract was executed by A4.

9. Learned Special Judge examined P.Ws.1 to 8 and marked

Exs.P1 to P27 on behalf of the prosecution. Three witnesses,

D.Ws.1 to 3, were examined on behalf of the appellants.

10. P.W.1 speaks about the contract work estimations and the

role played by A1 and A2, as narrated above. P.W.1 further stated

that Chalamaiah (P.W.4), Executive Engineer, Irrigation, visited

the work, made enquiries, and found that there was a deficiency

in the work executed by A4. Thereafter, P.W.4 addressed a letter

Ex.P5 to the District Collector, pointing out the deficiency, and

also issued a notice to A4 to rectify the defects. P.W.1 also

recorded the measurements, after the rectification work had

taken place.

11. In the cross-examination, P.W.1 stated that he recorded the

work only after the completion of work and payment being made

to the contractors, in accordance with the measurements in the

M.Book. P.W.1 further stated that A4 had completed the contract

work. The recording of measurements by P.W.1 was on

27.03.1996.

12. P.W.2 also deposed the case of the prosecution in the same

lines as P.W.1.

13. P.W.3, who retired as the Executive Engineer, found the

following differences with regard to the work done:

"Benching to old bund worked out to 388.4 Cubic meters, which is actual. But it was shown as the work done of 1,496.11 cubic meters, which is in excess. Reflected at Page 47 of the work statement.

Excavation work-raising bund actual worked out to 9087 cubic meters whereas it is mentioned 12426.20 cubic meters which is also in excess at page 47.

225 MM thick rough stone dry packing or revetment to bund actual work out to 332.34 cubic meters, but it is shown 597.66 cubic meters which is also excess. I have worked out the above said quantities prior to rectification of the work."

14. P.W.3 further stated that he has not personally visited the

work spot, but he based his calculations on the statements and

measurements which were furnished to him.

15. P.W.4 is a crucial witness to the prosecution. According to

him, after verification of the work done by A4, though claim for

Rs.7.00 lakhs was made, P.W.4 found that the work was

defective, both in quantity and quality, as such, a

recommendation for Rs.1,20,000/- was made by him. According

to P.W.4, he addressed a letter to A4 to rectify the defective work

done by him.

16. In the cross-examination, P.W.4 admitted that he has not

given any reasons for restricting the amount to Rs.1,20,000/-.

Further, the deficiencies were also not mentioned in the M.Book.

According to P.W.4, he inspected the work along with A1 and A2.

Experience certificate was issued by P.W.4 to A4 on 17.06.1993,

stating that the work was satisfactory. However, P.W.4 added

that the said certificate was given on the basis of certification

given by A2.

17. P.W.7 is the retired Tahsildar, who states about the

defective work done. However, in the cross-examination, P.W.7

admits that he was not personally aware about the defective

work, nor did he go for any personal inspection of the work.

18. P.W.8 is the Investigating Officer. He stated that the FIR was

registered on 06.09.2000, based on the report of the Lokayuktha.

Sri Narsing Rao, Joint Director of A.P. Lokayuktha, who enquired

and submitted report to Lokayuktha, was not examined.

According to P.W.8, he conducted the investigation and seized the

records. P.W.8 admitted that he has gone through the certificate

issued by P.W.4 on 17.06.1993. Further, according to the

Lokayuktha report, A1, A2, one Patnayak, and

P.W.4/Chalamaiah were responsible for the alleged

misappropriation of the government funds.

19. P.W.8 further admitted that by the year 1996, the entire

work was executed and the final payment was also made. The

first agreement for the contract was on 28.01.1993 and the

second agreement was on 17.08.1993. However, none of the

witnesses, including P.W.8 stated about the contents of the two

agreements.

20. All the witnesses stated that A3 was not concerned with the

work and he only conducted super check of the work executed by

A4. For the said reason, learned Special Judge acquitted A3, as

no incriminating evidence was found against him.

21. D.W.1 is an agriculturist, examined by the defence. He

stated that he attended the work of repairs of Erra Cheruvu

during 1993, i.e., the work in question. According to him, after

1993, A4 did not do any repairs of Erra Cheruvu and no one

attended to the repairs.

22. Though witnesses, P.Ws.1 to 4, speak about the rectification

work done, however, no witnesses were examined to specifically

speak about the rectification work executed by A4.

23. The work was done in the year 1993, and even according to

the prosecution case, the entire work was completed, even prior

to 1996 and the entire amounts were paid to A4.

24. D.W.3 worked as Superintendent, Irrigation. He deposed in

his chief examination, as follows:

"I retired as Superintendent Irrigation. After the works are complete later the revised estimates are submitted. The concerned E.E has to inspect the works and satisfy himself and then only has to send the revised estimates to the Sanctioned Authority. In the Ex.P12 certificate Executive Engineer fully satisfied certified the work after inspection and signed to that effect. If any deductions are to be made the E.E has to get the abstract prepared and when mentioned the deductions before passing of the bill. Without assigning any reasons by the E.E the bill cannot be limited. After the finishing work is over when it becomes old it would not be possible to check up whether the finishing work properly or not. After one year after execution of work unless the undisturbed core sample is taken and sent to the Quality Tests laboratory it will not be possible to assess whether the consolidation is properly done or not. In the revitmant work a toe wall has to be constructed from the base level and gradually it should be raised upto the required level. While inspecting the revitmant work it has to be inspected from the base level to upward stage. In Ex.P25 there is no mention that the revitmant work was inspected from the base level. Due to loss of time and seepage of water the base level of the revitmant the silt will be formed over the revitmant and if the silt is removed the revitmant will be disclosed."

As stated by D.W.3, no scientific test was conducted to

determine any deficiency of work. In the cross-examination, the

evidence of D.W.3 remains unchallenged.

25. The charge is for preparing a false statement in the

measurement book to a tune of Rs.4,04,249/- during the year

1993-94. No reasons are given by any of the witnesses as to how

the said amount was arrived at, and none of the witnesses speak

about any scientific estimation of the work done vis-à-vis the

entries made in the measurement book.

26. The charges are framed for attempt to cheat and also

attempt to falsify the records. As already discussed, none of the

witnesses spoke about how amount was arrived at based on the

records. The ACB registered the case nearly after six years after

the work was executed. According to the investigating officer,

P.W.4 restricted the amount to Rs.4,04,249/-, which is the

alleged misappropriated amount. P.W.4 did not speak about how

the amount of Rs.4,04,249/- was arrived at or in what way the

said amount was subject to any pecuniary advantage by the

appellants.

27. The case of the prosecution is not based on any scientific

evidence but solely on the Lokayuktha report, which formed

basis to register the FIR. The person who prepared the

Lokayuktha report was not examined. On the basis of

assumption that the appellants have attempted to either cheat

the government or attempted to falsify the accounts, the

prosecution of the appellants is improper. Admittedly, there is no

loss to the Government or the department. None of the witnesses

speak about any monetary loss but speak about rectification of

the work executed. In the present circumstances, there is no

attempt to cause loss as alleged by the prosecution.

28. In the result, the judgment of trial Court in C.C.No.29 of

2005 dated 30.06.2010 is set aside, and the appellants/A1, A2,

and A4 are acquitted. Since the appellants are on bail, their bail

bonds shall stand discharged.

29. Accordingly, both Criminal Appeals are allowed.

__________________ K.SURENDER, J Date: 19.03.2025 kvs

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter