Sunday, 17, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

M/S. Telangana State Industrial ... vs Sri Mark Raj Kumar
2025 Latest Caselaw 575 Tel

Citation : 2025 Latest Caselaw 575 Tel
Judgement Date : 25 July, 2025

Telangana High Court

M/S. Telangana State Industrial ... vs Sri Mark Raj Kumar on 25 July, 2025

                                       1




      THE HON'BLE JUSTICE MOUSHUMI BHATTACHARYA
                          AND
       THE HON'BLE JUSTICE B.R.MADHUSUDHAN RAO


                           I.A.No.1 OF 2025
                                IN/AND
                          COMCA No.1 of 2025


Sri Shyam S.Agrawal, learned counsel for the appellant.

Mr. Ashish Kale, learned counsel representing Ms. Sneha Bhogle, learned
counsel for the respondent No.1.



COMMON ORDER:

(Per Hon'ble. Justice Moushumi Bhattacharya)

1. The petitioner/appellant, M/s. Telangana State Industrial

Development Corporation Limited, has challenged the impugned

order and decree passed by the learned Commercial Court dated

16.02.2023, whereby the appellant's Commercial Original Petition

(C.O.P.No.38 of 2016) filed under section 31(1)(a) and (aa) of The

State Financial Corporations Act, 1951, for a decree against the

respondents for an amount of Rs.1,30,31,000/- with interest

@ 17.5% per annum, was dismissed.

2. The present Appeal was filed on 26.12.2024 along with an

application (I.A.No.1 of 2025) for condonation of a delay of 514

days in filing the Appeal. The parties have filed their respective

affidavits in the I.A. The respondents have strongly objected to the

condonation of delay.

3. We have heard learned counsel appearing for the

petitioner/appellant and learned counsel appearing for the

respondent No.1 in support of their submissions and considered

the case law cited on behalf of the parties.

4. The petitioner/appellant has filed two affidavits in support of

the application for condonation of delay. The second affidavit is

described as an 'Additional Affidavit' for supplementing the reasons

stated in the first affidavit. The reasons for the condonation of

delay are set out from paragraph 25 of the first affidavit. The

relevant dates mentioned are as follows.

5. The petitioner states that after passing of the impugned

order on 16.02.2023, the petitioner applied for a Certified Copy of

the said order and decree on 22.02.2023 and the Certified Copy

was furnished to the petitioner on 07.06.2023. Upon receiving the

copy of the order, the petitioner's Law Officer prepared a note and

submitted it to the 'Higher Officials' for taking a decision and

necessary action. However, the immediate higher official, the

Deputy General Manager of the petitioner 'took long time to go

through and understand the impugned order and after sometime, he

had placed it before the Managing Director of the petitioner'.

Elections were declared in the State of Telangana, during which 'all

the officials were busy and no instructions were coming for the

decisions to be taken in regard to legal matters and the issue of the

present case was lying pending'. By the time normal work

resumed after the State Elections, the Union Elections had

commenced and 'again there was no progress in the work including

the issue of the present case'. Paragraph 26 of the affidavit further

states that even after the Union Elections, 'it took some time for

normal work to get resumed...... However, the file of the present case

got mixed up in the numerous files that were pending for

circulation...... and hence no decision was taken as the file itself

was got mixed up and went missing'.

6. Paragraph 27 of the affidavit states that it was only in

November, 2024 that the petitioner realized that 'the decision in

regard to the impugned order had not yet been taken' and that the

matter was pending. This came to light when the respondent No.1

approached the petitioner for return of the original Title Deeds of

the schedule property. The petitioner gave instructions to put up

the file 'but the same was not being traced and it was realized that

the file was missing'. The petitioner thereafter gave instructions to

trace the file and place it before the higher officials. It is further

stated that 'after a long search and with great difficulty, the file

could be traced out in the second week of December, 2024'. The

petitioner immediately held discussions with counsel and a

decision was taken to file an Appeal before the High Court. The

Appeal was thereafter prepared and filed.

7. The 'Additional Affidavit' reiterates the dates of the Elections

which were mentioned in the first affidavit. The petitioner states

that the schedule for the Elections to the Telangana State

Legislative Assembly was announced on 09.10.2023 and the

Elections were held on 30.11.2023. The employees of the

petitioner-Corporation, being a State Government company, were

assigned official duties for conducting elections and therefore,

could not 'concentrate on the issue relating to filing of the present

Appeal and obtaining necessary instructions' since they were

engaged in election related work. Paragraph 6 of the Additional

Affidavit states that the Election Commission of India had

announced the schedule for the General Elections on 16.03.2024,

and the polling in the State of Telangana was held on 13.05.2024.

The petitioner's employees were entrusted with election duties and

'they were completely involved therein'. The petitioner further

states that 'in view of such disturbances in work due to successive

elections, immediate action for filing of the appeal could not be taken

up'. Paragraph 7 states that following the change of the

Government, three Vice Chairmen and Managing Directors took

charge in quick succession at the petitioner-Corporation, which

further contributed to the delay in filing the Appeal.

8. The statements made in the two affidavits filed in support of

the application for condonation of delay in filing of the Appeal have

been reproduced verbatim in the preceding paragraphs. The

extracts in italics are reproduced from the two affidavits.

9. The dates mentioned in the two affidavits contain several

unexplained time-gaps. The impugned order was passed on

16.02.2023 and the application for a Certified Copy thereof was

made on 22.02.2023. Although the Certified Copy was made ready

on 07.06.2023, the next date mentioned in the Additional Affidavit

is 09.10.2023 (the announcement of the schedule for the

Telangana Legislative Assembly Elections), followed by the conduct

of the Elections on 30.11.2023.

10. The petitioner has not explained the lapse of four months

between 07.06.2023 and 09.10.2023. The second unexplained gap

is from 30.11.2023 (the date of the Legislative Assembly elections)

to 13.05.2024 (polling date for the General Elections in the State of

Telangana). There is no explanation for the intervening period of

six months from November, 2023 to May, 2024.

11. Apart from the gaps in the timeline, the reasons stated for

the delay are as follows:

(i) The Deputy General Manager of the petitioner took a

long time to go through and understand the impugned

order;

(ii) All the officials of the petitioner-Corporation were busy

with the election duties;

(iii) No instructions were issued to the officials regarding

the legal matters;






         (iv)    The file of the present case was mixed up with the

                 other files; and

         (v)     The file was ultimately lost.


12. It is evident from paragraph 27 of the first Affidavit that the

respondent No.1 demanding return of the original Title Deeds of

the schedule property triggered the petitioner's realization that no

decision had been taken with regard to the impugned order and

that the file was untraceable. Therefore, from 13.05.2024 to

November, 2024 i.e., for six months the petitioner took no steps to

challenge the impugned order dated 16.02.2023. The petitioner

admits that the file was located after a considerable delay. The

Appeal was filed in the second week of December, 2024. No other

specific dates are mentioned in the two affidavits.

13. Section 13 of The Commercial Courts Act, 2015 relates to

filing of appeals from decrees of Commercial Courts and

Commercial Divisions. Section 13(1A) provides that any person

aggrieved by the judgment or order of a Commercial Court or from

a Commercial Division of a High Court may file an appeal to the

Commercial Appellate Division of the High Court within a period of

sixty days from the date of the judgment or order.

14. The appellant has filed the present Appeal under the

provisions of The Commercial Courts Act, 2015 from the order of

the Commercial Court along with an application for condonation of

delay of 514 days. The reasons stated in the two affidavits filed

along with the application for condonation of delay have been

narrated in the foregoing paragraphs.

15. The first question is whether the Court should invoke its

discretionary powers to condone the delay.

16. The appellant entirely relies on section 5 of The Limitation

Act, 1963 which allows filing of an appeal or any application

beyond the prescribed period of time subject to the Court being

satisfied of the sufficiency of cause shown by the appellant or

applicant for the delay. The burden of proving the sufficiency of

cause lies with the appellant or applicant.

17. In Government of Maharashtra (Water Resources Department)

Vs. Borse Brothers Engineers and Contractors Private Limited 1, the

Supreme Court considered the applicable timeframe under section

37 of The Arbitration and Conciliation Act, 1996 which provides for

appeals from specified orders. Section 37 of the 1996 Act does not

specify a timeframe for filing of appeals. The Supreme Court

concluded that any delay beyond 90 days, 30 days or 60 days

(under Articles 116, 117 of The Limitation Act, 1963 and section

13(1A) of The Commercial Courts Act, 2015 respectively) for filing

of an appeal under section 37 of the 1996 Act should be condoned

by way of exception and not by way of rule. Besides, in Borse

Brothers, there was a delay of 131 days beyond the 60 days period

provided for filing of an appeal under section 13(1A) of The

Commercial Courts Act, 2015. The Supreme Court found that the

delay had not been explained with sufficient bona fides and

accordingly proceeded to dismiss the appeal.

18. It is now settled that section 5 of The Limitation Act, 1963

would apply to appeals filed under section 13(1A) of The

Commercial Courts Act, 2015: Borse Brothers; also refer to a recent

(2021) 6 SCC 460

decision of the Supreme Court in Jharkhand Urja Utpadan Nigam

Ltd., Vs. M/s. Bharat Heavy Electricals Limited 2.

19. However, in Borse Brothers, the Supreme Court made it clear

that the limitation beyond 60 days cannot be stretched to

unreasonable limits so as to defeat the object of The Commercial

Courts Act, 2015, wherein the Legislature made a conscious choice

of capping the timeline. The delay of 514 days is not being

castigated here for its length, but for the appellant's failure to

account for the delay in the manner mandated under section 5 of

The Limitation Act, 1963. Although, extension of the period of

limitation beyond the prescribed timeframe is a matter of public

policy, 'sufficient cause' cannot serve as a convenient excuse to

wipe out unexplained delays in pursuing stale claims.

20. Since section 5 of The Limitation Act, 1963 applies to the

present Commercial Court Appeal, the next question is whether

the appellant has satisfied the requirement of showing sufficient

cause. In this regard, the appellant cannot take refuge in the fact

of it being a Government Company. A discussion on this aspect

follows in the next paragraph.

2025 SCC OnLine SC 910

21. The facts before us are in stark contrast, both in degree and

depth, to those in Borse Brothers. As opposed to the delay of 131

days in Borse Brothers, the present appeal is set behind by 514

days. The only similarity with Borse Brothers is that the appellant

before the Supreme Court was the Government of Maharashtra

(Water Resources Department). In the present case, the appellant

is M/s. Telangana State Industrial Development Corporation

Limited (formerly Andhra Pradesh State Industrial Development

Corporation Ltd.).

22. A State Corporation/Government Department cannot be put

on a pedestal with privileged timelines which would be evident

from the underlying objective of special statutes which contemplate

fixed timelines. These Acts are entity-neutral in terms of limitation

periods. There is little doubt that the objective of a special statute

like The Commercial Courts Act, 2015 is to ensure speedy

resolution of high-value commercial disputes, without any

exceptions. The focus is on quick resolution which includes

Government entities when they are parties to commercial disputes.

23. Moreover, the logic of Government employees being oblivious

of timelines is totally misplaced. Government departments are

expected to be staffed with competent persons who are familiar

with Court proceedings especially in times when modern

technology aiding quick filings and communication is readily

available. The Law of Limitation binds everybody, including the

Government: Postmaster General Vs. Living Media India Limited 3.

The Government or a wing of the Government enjoys the same

perks and suffers the same pitfalls as a private entity in

commercial transactions; which begs the question whether the

Government can create and take shelter under a parallel timeline

in a fixed-period statute like The Commercial Courts Act, 2015 ?

24. None of the judgments cited on behalf of the appellant deal

with the specific limitation period prescribed under The

Commercial Courts Act, 2015. Collector Land Acquisition Officer,

Anantnag Vs. Katiji 4. N. Balakrishnan Vs. M.Krishnamurthy 5 and a

more recent judgment of the Supreme Court in Mool Chandra Vs.

(2012) 3 SCC 563 4 (1987) 2 SCC 107 5 (1998) 7 SCC 123

Union of India 6 deal with the requirement of showing sufficiency of

cause under section 5 of The Limitation Act, 1963. In

N.Balakrishna (supra), the Supreme Court dealt with the need to

advance substantial justice where the delay on the part of the

litigant was not deliberate or caused by mala fides. Similarly, in

Mool Chandra (supra) the Supreme Court found from the specific

facts of that case that there was no negligence attributable on the

part of the appellant. Sheo Raj Singh Vs. Union of India 7 agreed

with the view taken by the High Court in condoning the delay on

the part of the Union of India on the ground of proper exercise of

discretion. The Supreme Court relied on State of Manipur Vs.

Koting Lamkang 8 to hold that the impersonal nature of State-

functioning should be given due regard. Sheo Raj Singh however

involved the issue of compensation payable to the landowner and

was not under a special statute with rigorous timelines, namely,

The Commercial Courts Act, 2015.

25. Exercise of discretion under section 5 of The Limitation Act,

1963 empowers the Court to entertain an appeal or application

6 AIR 2024 SC 4046 7 (2023) 10 SCC 531 8 (2019) 10 SCC 408

beyond the prescribed period of limitation subject to the Court

being satisfied of the sufficiency of cause shown by the

applicant/appellant. The cause shown must be such that the

overarching requirement to advance the cause of substantial

justice outweighs the appellant's shortfall in filing the appeal

within the prescribed period of limitation. 'Sufficient' cause must

reflect a sense of purpose and a willingness to restore diligence.

The reasons shown cannot be slipshod or nonchalant so as to

demand condonation as a matter of entitlement. It must be borne

in mind that delay may have created equity in favour of another in

the interregnum.

26. As stated in the foregoing paragraphs, the appellant only

gives sporadic dates which randomly pop-up in a timeline from

February, 2023 to December, 2024. There is no attempt to explain

or account for the long blanks in-between these dates.

27. It is of crucial relevance that in paragraph 7 of the additional

affidavit, one of the reasons mentioned by the appellant for the

delay is that there were three Vice-Chairmen and the Managing

Directors who took charge of the appellant corporation in quick

successions. There are no dates mentioned with regard to the date

on which the Vice Chairmen and the Managing Directors assumed

charge. Counsel appearing for the respondent has however

produced G.O.Rt.No.54, dated 11.01.2024 which shows that

Dr.E.Vishnu Vardhan Reddy was placed in the post of Vice

Chairman, Managing Director, and Executive Director of the

appellant Corporation on and from 11.01.2024. There was no

change in the position of Vice Chairman/Managing Director of the

appellant from 11.01.2024 till the date of filing of the appeal i.e.,

on 26.12.2024.

28. It is of additional significance that one of the grounds for

passing the impugned order was whether the appellant's claim was

barred by limitation. The Commercial Court after considering the

facts, answered the issue against the appellant and in favour of the

respondent No.1. Thus, it is all the more difficult to accept that

the appellant would slip into a slumber for 514 days after having

suffered an order, inter alia, on the ground of delay.

29. We hence do not find any reason, satisfactory or otherwise,

in condoning the delay of 514 days in filing the Commercial Court

Appeal.

30. I.A.No.1 of 2025 is accordingly dismissed for the reasons

stated above. Consequently, COMCA.No.1 of 2025 stands rejected.

There shall be no order as to costs.

_________________________________ MOUSHUMI BHATTACHARYA, J

_____________________________ B.R.MADHUSUDHAN RAO, J

Date: 25.07.2025 va/bms

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 

LatestLaws Partner Event : IJJ

 
 
Latestlaws Newsletter