Tuesday, 12, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

The Singareni Collieries Company ... vs V. Prabhakar Reddy
2025 Latest Caselaw 4907 Tel

Citation : 2025 Latest Caselaw 4907 Tel
Judgement Date : 17 April, 2025

Telangana High Court

The Singareni Collieries Company ... vs V. Prabhakar Reddy on 17 April, 2025

Author: Abhinand Kumar Shavili
Bench: Abhinand Kumar Shavili
     THE HON'BLE SRI JUSTICE ABHINAND KUMAR SHAVILI
                           AND
      THE HON'BLE SMT. JUSTICE TIRUMALA DEVI EADA

                   APPEAL SUIT No.256 OF 2005

JUDGMENT:

(Per Hon'ble Smt. Justice Tirumala Devi Eada)

This is an appeal filed by the appellant - plaintiff, being

aggrieved by the judgment and decree, dated 18.11.2004 passed

in O.S.No.04 of 2001 by the learned I Additional District Judge at

Karimnagar (for short "the trial Court").

2. The parties are addressed herein as they were arrayed in

the suit before the trial Court for the sake of convenience and

clarity.

3. The case of the plaintiff before the trial Court is that the

plaintiff company is engaged in mining industry and it involves

exploration, excavation, extracting and winning of coal. The

defendant is a contractor and he was entrusted with the work of

blast, hole drilling and earth work excavation of various

rocks/earth cutting, loading, transportation, dumping etc., by

using machines as per the scope of work at Ramagundam Open

Cast Project-II. The order was placed on the defendant on

15.09.1998. As per the said order, the defendant executed 89% of

the work worth 88.84 L.B.Cubic Meters and stopped the work on AKS,J & ETD,J AS No.256_2005

31.07.1999 and the final bill was settled for a volume of 90.68

L.B.Cubic Meters. It is their case that on 14.02.2000, the survey

team and check survey team, surveyed the work done by the

defendant and recorded the measurements and the final bill was

settled according to the said measurements. But subsequently,

the plaintiff company called fresh tender for further excavation

work and the work was entrusted to M/s.A.B.C.Engineering Work,

Vijayawada on 12.02.2000. Subsequently, the plaintiff company

conducted the re-survey of the work done by the defendant for the

purpose of handing over the remaining work to ABC Company and

they noticed some discrepancies in the quantity of the work done

by the defendant, therefore, they conducted re-survey in the

month of March, 2000 and their resurvey revealed that the data

entered into the computer was erroneous and the same was

informed to the defendant and was asked to attend the proposed

joint survey on 16.04.2000. The defendant requested the plaintiff

to postpone the survey till 25.04.2000, accordingly the same was

postponed and on 19.04.2000, the plaintiff received a letter from

the defendant questioning the authority of the plaintiff company

in conducting joint survey and did not attend the survey on

25.04.2000. The plaintiff company proceeded with the resurvey

and it was found that the initial team and check survey team had AKS,J & ETD,J AS No.256_2005

wrongly recorded the quantity of work as 90.68 L.B.Cubic Meters

and that the excess volume of work was found to be 1.84

L.B.Cubic Meters and the value of the said work was estimated at

Rs.56,75,520/- and that they have initiated disciplinary

proceedings against the concerned officers. It is their contention

that there was no defacing of levels due to natural factors like

rains etc., The defendant completed the work in the month of

July, 1999, while the re-survey was conducted in April, 2000 and

they addressed a letter dated 21.06.2000 to the defendant

informing him that they have paid an excess amount and they

would recover the same from the running bills of other works

being executed by the defendant. The defendant replied to the

said letter requesting the plaintiff company not to recover the

amount from the running bills and also filed two suits i.e.

O.S.No.44 of 2000 and O.S.No.77 of 2000 before the Senior Civil

Judge, Peddapalli and obtained temporary injunction restraining

the plaintiff from recovering the said amounts from the running

bills. Therefore, the plaintiff's grievance is that 1.84 L.B.Cubic

Meters was erroneously recorded in excess to the work executed

by the defendant and thus, the plaintiff is entitled for the recovery

of the sum paid for the said work. Hence, the suit.

AKS,J & ETD,J AS No.256_2005

4. The defendant filed written statement denying the

averments of the plaint. The defendant further stated that he

undertook similar works over a period of time and completed them

without any adverse remarks and that he was executing similar

works at the time of filing his written statement and as per the

terms of the contract, the levels, depths and quantities, there

would be plus or minus 10% variation. The approximate quantity

expected to be removed was 100 L.B.Cubic Meters with 10%

variation. He further stated that while the excavation work was

going on, periodical payments were made to the defendant on the

measurements recorded by the survey team and after the

completion of work also the survey team and check survey team

surveyed the work and recorded the final measurements and

depending on their report, the plaintiff has paid him for the final

quantity of work i.e. 90.68 L.B.Cubic Meters. It is also his case

that the survey team after taking final measurements issued a

certificate dated 09.12.1999 showing the quantity of the final bill

and based on the said measurements, the defendant submitted a

final bill and the same was paid by the plaintiff on 14.01.2000 i.e.

seven months after the completion of work. A certificate was also

issued by the General Manager on 01.03.2000 and after nine

months of completing the work, the General Manager and Chief AKS,J & ETD,J AS No.256_2005

Vigilance Officer addressed two different communications on

12.04.2000 alleging certain discrepancies. The defendant further

expresses doubt with regard to the possibility of the survey being

accurate as the rainy season passed by, which might have caused

variation in the levels of the work. The defendant submitted in

the written statement that the said doubt was expressed by him

vide his letter to the plaintiff company but the General Manager

without clarifying his doubt has sent a reply that re-survey was

proposed to be conducted on 25.04.2000 and that he again

addressed a letter on 21.04.2000 but the plaintiff insisted on the

defendant's participation without answering any of the questions

raised by him and proceeded with the re-survey. Therefore, the

case of the defendant is that the result of the re-survey does not

bind him and he denied the liability to make any payments to the

plaintiff company.

5. Based on the above pleadings, the trial Court has framed

the following issues for trial.

"1. Whether 1.84 L.B.Cubic Meters quantity was recorded in excess by the subordinate officials of the plaintiff company, in collusion with the defendant and the value of the said work is Rs.56,75,520/-?

AKS,J & ETD,J AS No.256_2005

2. Whether the plaintiff is entitled for the above said value of the work with interest as prayed for in the plaint?

3. To what relief?"

6. At the time of trial, the plaintiff got examined PWs 1 to 5

and got marked Exs.A1 to A33. On behalf of the defendant, DWs

1 and 2 were examined and Exs.B1 to B16 were marked.

7. Considering the evidence on record, the trial Court has

dismissed the suit. Aggrieved by the said judgment and decree,

the present appeal is filed by the plaintiff.

8. Heard the submissions of Sri J.Prabhakar, learned Senior

Counsel for the appellant and Sri M.Jayaram Reddy, learned

counsel for the respondent.

9. The learned appellant counsel has submitted that the

judgment and decree of the trial Court is contrary to law and facts

of the case and that the trial Court has misconstrued the scope

and ambit of the suit and that the trial Court has come to a

conclusion that the appellant is entitled for compensation on the

principle of quantum meruit but has finally rejected his claim,

which is not proper. He further argued that the contractor who is

the defendant played fraud upon the company and therefore, he is AKS,J & ETD,J AS No.256_2005

not entitled to get the benefit of excess payment. He further

argued that certain officials of the plaintiff company got colluded

with the contractor and therefore, the excess amount was paid to

the defendant and as such, they are entitled to claim the same.

The decision to conduct resurvey was intimated to the defendant

but he failed to appear in a joint survey and thus, the findings of

the re-survey are binding on the defendant and that the defendant

is liable to return the excess amount received by him. It is his

argument that the plaintiff has proved the error in the

measurement but still the trial Court failed to consider the same

and misunderstood the statement of PWs 1 and 2 in respect of the

actual extent of disturbed area. Thus, he prayed to set aside the

decree of dismissal and prayed to allow this appeal.

10. The learned respondent counsel has submitted that the

plaintiff has totally failed to prove its case and that conducting a

resurvey was not proper on part of the plaintiff and that

measurements could have been varied due to the rain and the

intervening factors. He further argued that the defendant was

paid the amount after the survey team and check survey team

have conducted survey and submitted the quantity of work that

was completed by defendant to the company and that after a

proper scrutiny, the bill was paid to the defendant and that the AKS,J & ETD,J AS No.256_2005

defendant has been executing so many works with the plaintiff

company and at the relevant time of filing the suit also he was still

proceeding with other works entrusted by the plaintiff company.

He therefore submitted that the defendant has been enjoying good

reputation and that he never committed any default and he never

enjoyed any benefit of excess payment and that the defendant is

not liable to pay any amount to the appellant herein and he

therefore, prayed to dismiss the appeal by upholding the decree of

the trial Court.

11. Based on the above rival contentions, this Court frames the

following points for consideration:

1. Whether any excess amount was paid by the plaintiff company to the defendant in lieu of the work done by the defendant? If so, whether the plaintiff is entitled to recover the same?

3. Whether the judgment and decree of the trial Court is sustainable under law and in the facts?

4. To what relief?

12. POINT NO.1:

a) The admitted facts are that the defendant was entrusted

with excavation work by the plaintiff company and that the

defendant completed the work on 31.07.1999. It is also admitted

that a survey was conducted and the value of the work done by AKS,J & ETD,J AS No.256_2005

the defendant was assessed as 90.68 L.B.Cubic Meters and

money to that extent was paid to him on 14.02.2000 based on the

certificate issued by the Mine Survey Team and Check Survey

Team. The dispute lies with regard to the assessment made by

the resurvey team on behalf of the plaintiff company. It is the

contention of the plaintiff that after entrusting the remaining work

to M/s.ABC Engineering Work, they had conducted a survey to

assess the amount of work that is to be entrusted to M/s.ABC

Engineering Work and that they noticed some discrepancies in the

work that was completed by the defendant and the quantum of

work that was assessed by their team at the time of payment of

bill to the defendant. Therefore, they wanted to conduct a joint

survey and thereafter, inspite of the doubts raised by the

defendant, they have addressed a letter to the defendant and

proceeded to conduct the resurvey and on this survey, they

noticed that 1.84 L.B.Cubic Meters of difference was noticed in

the work carried out by the defendant, thus, it is their case that

they want the defendant to refund the amount paid in lieu of that

excess assessment of work that was done in the earlier survey

when compared to the resurvey, while the defendant denies the

same. His case is that he has completed the work to a tune of

90.68 L.B.Cubic Meters and it was assessed by the check survey AKS,J & ETD,J AS No.256_2005

team and mine survey team and thereafter, the plaintiff company

has paid him the amount, so the question of difference in

assessment does not arise and that he has not received any

excess amount.

b) In the evidence of PW1, it is elicited that the following

discrepancies were noticed by the joint survey team:

a) The reduced levels obtained in joint survey differed at many places to a tune of 0.5 M. to 3.0 m which was considered to be abnormal.

b) The data entry into the computer done by the Mine Survey Team, when compared to their own field books differed at nearly 400 entries.

c) According to the check survey plans, the reduced levels at about 1200 places are not tallyup with the field book of the check survey.

d) When the results of mine survey and check survey are compared in the sectional areas the variations are abnormal, the error in positive side in certain lines are compensated with the error on negative side in other lines, thus compensating the error, the aggregated quantity was tallied, from this they came to know that the survey was not conducted in scientific manner.

c) In the cross examination of PW1, he stated that the

discrepancies were noted by them only when it was brought to

their notice through M/s.ABC Engineering Work. It is elicited

through him that they have issued disciplinary proceedings AKS,J & ETD,J AS No.256_2005

against their officers of Mine Survey Team and Check Survey

Team who were alleged to have made wrong entries with regard to

the quantities of work done by the defendant. It is further elicited

that the enquiry proceedings were completed and the results are

awaited. The officers against whom the disciplinary proceedings

were initiated were not examined in this case but he produced the

statement recorded by them during the course of enquiry.

d) A perusal of the statement of K.Nagabhushanam reveals

that the representatives of the defendant approached the survey

officers and requested to see the plans for the purpose of tallying

them with the mine plan and the statement of one

M.Venkatesham, the Assistant Survey Officer, is to the effect that

the defendant's representative was involved while noting the field

reading in the field book and also while entering the field data into

the computer, which gave scope for manipulating the field data.

But PW1 could not state whether there was a garland drain

around the catchment area in which the suit quarry is located.

Moreover, PW1 admitted that the suit quarry is in a low lying

area. This falsifies the case of the plaintiff. The contention of the

plaintiff was that the suit quarry is not in low lying area and that

the rains and the natural calamities would result only in an

advantage to the defendant and that the suit quarry is not a low AKS,J & ETD,J AS No.256_2005

lying area but the defendant contended that the suit quarry was

in a low lying area and it is prone to the natural calamities such

as rain, which would make all the difference with regard to the

levels, thus, the admission of PW1 that the suit quarry is in a low

lying area supports the case of the defendant. It is further elicited

through PW1 that the resurvey was made only in a portion of the

suit quarry and he also stated that it took place in a deeper side

portion of the quarry and that he did not prepare any plan of the

quarry resurvey and any field book in the resurvey. He further

admitted that he has not mentioned in Ex.A12 whether the

re-survey was being conducted in the entire quarry or in a portion

of the quarry and it is also admitted by him that the resurvey was

done after nine months of stoppage of work by the defendant.

Another material admission by PW1 is that while excavating coal,

the overburden material would be disturbed upto a length of

2 meters from the blasting zone and that there is a possibility of

the black cotton soil in the catchment area and part of the quarry

getting eroded into the quarry especially during rainy season

subject to the provision of setting up of drains. He further

admitted that the water got stagnated in the quarry after the

defendant stopped his work and before the resurvey was done. It

is further elicited during his cross examination that there may be AKS,J & ETD,J AS No.256_2005

slight errors in noting the levels because of different instruments

used in the survey. It is further elicited through him that the

officers who were suspended by their company were again

reinstated but the process of their reinstatement and the result of

enquiry against them is not placed on record.

e) PW2 also stated that there were discrepancies which were

brought to their notice by M/s.ABC Engineering Work and on

such notice PW2 advised the mine survey team to conduct the

random survey. It is elicited through him during cross

examination that the pre-levels of undisturbed area and the

disturbed area entrusted to ABC Engineers was noted in the plan

but the said plan is not filed in the Court. He could not state

about the actual extent of the disturbed area pertaining to the

defendant.

f) PW3 is the survey officer and he is a member of joint survey

team and he stated that the mine survey team and check survey

team could not carry out the survey in a scientific manner and

that the joint survey was conducted only in the undisturbed

portion entrusted to the defendant, even the survey sheets are not

filed by them.

AKS,J & ETD,J AS No.256_2005

g) PW4 has stated that the survey sheets were handed over to

the representatives of the defendant and according to him the

check survey was conducted by one Ansari.

h) PW5 is a surveyor in the Survey Office of India and he also

could not state about the area in which the overburden was taken

away by the defendant and he further admitted that there may be

slight difference in the measurements.

i) The plaintiff filed the statement of Ansari under Ex.A26,

which shows that he conducted the check survey of pre-level in

the final survey of the defendant and that as the data between

check survey and the mine survey was completely tallying, he

submitted the report without any doubt and the said statement

shows that he was asked to conduct pre-level survey for the next

contractor and it is further revealed that Ansari has found that

there was no mark on the field survey at every 12 meter chain and

that he asked the survey officers to mark the staff stations and he

noticed that out of the old Ammonia print copy which refers to the

total plan, which was taken before giving the work to the

contractor, only one sheet was found to be available. The

boundaries fixed to the quarry of the defendant were also not

surveyed at the end of the contract and he could not state about AKS,J & ETD,J AS No.256_2005

the difference of the value in the defendant's quarry as per the re-

check survey, as the calculations were not completed by then.

The plaintiff's company has recorded the statement of

Nagabhushanam who is examined as PW4 herein. The said

statement is marked under Ex.A28. It is revealed from the said

statement that a blue print of the original plotting to prevent

alterations was taken out but the said blue print is missing.

Another statement under Ex.A27 is marked by the plaintiff which

pertains to M.Venkatesham who is the Assistant Survey Officer

and he expressed his inability to explain the difference in the

levels and further stated that it may be because of some geological

disturbance in the ground movement which caused a little

difference in the surface contours. He stated that he took the help

of the contractors and surveyors for reading out the data from the

field book and he did not tally the data entry with the field book

because of time constraint.

j) Another statement is marked under Ex.A25 which pertains

to R.Ravi Kumar the Senior Survey Officer. His statement reveals

that a pre-level survey was conducted for giving contract to

M/s.ABC Engineering Work and he has further stated that as per

the circular of the Director of CP and P, the company has to fix

the leveling points around the quarry at 12 meter interval to avoid AKS,J & ETD,J AS No.256_2005

confusion but they are not fixing the 12 meter grid points because

of insufficient man power and transport. It is further elicited from

him that the survey was not conducted in part of the quarry and

as the volumes of final survey and that of check survey tallied

well, he did not get any doubt about the final survey.

k) Thus, through this oral and documentary evidence on

record, it is elicited that the original blue print about the plan of

work is missing. It is further elicited that though the plaintiff

alleged that their officials got colluded with the defendant and

have conducted the survey wrongly and gave a wrong finding of

excess work, they did not chose to place any evidence with regard

to the result of the disciplinary proceedings or they did not chose

to examine any of the said witnesses. But it is elicited, on the

other hand, that they were reinstated and they are working in

their company.

l) During the evidence of DW1 it was elicited that large

quantity of water flowed and percolated into the suit quarry, as a

result of which the large quantity of the soil, sand and silt got

collected in the suit quarry raising the bottom levels of the quarry

and that there was no garland drain around the suit quarry to

stop the flow of drain water. Due to blasting in the disturbed AKS,J & ETD,J AS No.256_2005

area, as admitted by the plaintiff there was a lot of disturbance

which resulted in storage and dumping of material over the

bottom level in the final excavation of the suit quarry. In the

cross examination of DW2, who is an employee of the defendant it

was elicited that there was no garland drain around the suit

quarry. The said fact is also elicited in the evidence of PW1 that

there was no garland drain around the suit quarry. Thus, the

possibility of rain water entering into the suit quarry and the

disturbed material surrounding the quarry entering into the suit

quarry cannot be ruled out as contended by the defendant.

m) The other documents relied upon by the plaintiff are with

regard to the communication made to the defendant and also the

data entry sheet, mine survey plan and the field entry book but as

discussed supra, they could not place the material that is relevant

to assess the discrepancies i.e. the original plans were not filed

and also they could not place it on record that the resurvey which

is done is perfect without any loss being caused by the natural

calamities. Therefore, there is no point in relying upon all these

documents which do not aid the plaintiff in any way to prove its

case.

AKS,J & ETD,J AS No.256_2005

n) The defendant in support of his case has filed the letters of

communication addressed by him to the plaintiff company and his

final bill pay sheet summary under Ex.B1, the work done

certificate issued by the General Manager, Ramagundam under

Ex.B3. All the other documents refer to the work orders issued by

the company and letters addressed by the defendant to the

plaintiff company.

o) Thus, an overall perusal of the evidence on record reveals

that the plaintiff could not place clinching evidence on record to

show that there was a difference in the quantity of work that was

actually done by the defendant and the assessment made by their

own team. Though fraud is alleged to be played by their own

employee in collusion with the defendant, the said fact is not

proved through the evidence of the witnesses whom they have

examined. Moreover, when it is brought out that the possibility of

change in the level due to the natural reasons such as rains, it

further strengthens the case of the defendant and at the same

time, it demolishes the case of the plaintiff. When the levels of the

quarry itself get changed due to natural calamities or the natural

factors such as rains and it is also brought out on record that the

defendant left the work in the month of July and the survey was

conducted after nine months, in the meantime the said quarry AKS,J & ETD,J AS No.256_2005

was prone to all the natural weather condition and the rains must

have caused certain damage as there was no garland drain

around the suit quarry and further the disturbed material around

the quarry must have entered into the quarry and therefore, the

re-survey conducted by the plaintiff cannot be held to have given

out the exact result. When the re-survey itself cannot be held to

give perfect result and it is based on several natural factors, the

same cannot be compared to the original final survey that was

conducted after the completion of work conducted by the

defendant. Thus, the discrepancy between the final survey and

the re-survey projected by the plaintiff cannot be held to be

genuine. When the discrepancy cannot be made out, the plaintiff

has no case at all to say that the excess amount was paid to the

defendant because of the discrepancy. Therefore, the plaintiff

failed to prove his case that he has paid excess amount due to the

miscalculation of the work done by the defendant. Hence, he is

not entitled to recover any amount from the defendant. Point

No.1 is answered accordingly.

13. POINT NO.2:

In view of the reasoned findings arrived at point No.1, it is

held that the judgment and decree passed by the trial Court do AKS,J & ETD,J AS No.256_2005

not need any interference and the same are held to be sustainable

in law and under the facts and circumstances of the case.

14. POINT NO.3:

In the result, the appeal is dismissed upholding the

judgment and decree, dated 18.11.2004 passed in O.S.No.04 of

2001 by the learned I Additional District Judge at Karimnagar.

No costs.

Miscellaneous Applications, if any, pending in this appeal

shall stand closed.




                                  ________________________________
                                  ABHINAND KUMAR SHAVILI, J



                                       ___________________________
                                        TIRUMALA DEVI EADA, J
Date:       .04.2025
ns
 

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter