Citation : 2024 Latest Caselaw 3815 Tel
Judgement Date : 18 September, 2024
HONOURABLE SRI JUSTICE K. LAKSHMAN
ARBITRATION APPLICATON NOs.224 OF 2023,
29 AND 52 OF 2024
COMMON ORDER:
Heard Mr. V.V.N.K. Sarath Saran, learned counsel for the
applicants and M/s M.V. Kini, Advocate Solicitor appearing for
respondent No.1. As per cause title, respondent Nos.2 and 3 are
proforma parties.
2. These three Arbitration Applications are filed under Section 11
of the Arbitration and Conciliation Act, 1996 (hereinafter 'the Act,
1996') for appointment of a Nominee Arbitrator to adjudicate the
disputes between the parties.
3. Considering the lis in these three Arbitration Applications is
identical and since the common questions of fact and law arise in
these three Applications, they are being heard together and disposed
of by this common order.
4. The Applicant, M/s Ramky-Barbik, is a Joint Venture formed
by two distinct entities engaged in executing various projects under
the purview of both the Central and State Governments. The
Respondent No. 1 is an authority responsible for the construction,
maintenance, and upkeep of National Highways. Respondent No. 2,
acting as the execution arm of the Chhattisgarh Public Works
Department, had floated a tender for the rehabilitation and
upgradation of several sections of NH-43 into a two-lane highway
with paved shoulders in Chhattisgarh under the NHDP-IV through an
Engineering, Procurement & Construction (EPC) basis.
5. The Applicant participated in the bidding process and was
awarded the contract for the execution of the work after being
adjudged as the lowest bidder. Subsequently, three different
agreements were executed concerning the project and all relevant
details are mentioned below;
Particulars Arb.Appl. Arb.Appl. Arb.Appl. Agreement 19.12.2014 28.01.2015 19.12.2014 Entered on Purpose of the 81.50 - 130 Kms 180-240 Kms 241-298 Kms Agreement (Rehab (Dhantari to (Bedma to (Dahikonda to & Up-gradation Kanker) Dhaikonda) Jagdalpur) NH3) to extent of Commencement & 24.03.2015 & 24.03.2015 & 24.03.2015 & Completion 23.09.2016 24.03.2017 24.03.2017 (Total Days) (550 Days) (730 days ) (730 days ) Letters issued by 28.03.2022, 24.07.2023 24.07.2023 the Applicant intimating the claims to the respondents Notice issued by 06.09.2022 27.09.2023 27.09.2023 the Applicant invoking Arbitration Clause Reply to Notice 18.10.2022 11.10.2023 11.10.2023 Claim Value (Rs.) 42,27,50,536 59,52,61,225 63,15,11,545
6. On 07.03.2019, Respondent No.1 took over the project from
Respondent Nos. 2 and 3 under a Tripartite Agreement. Respondent
No. 2 had been entrusted with the development, maintenance, and
management of the work by Respondent No. 3.
7. The applicant contended that Respondent No. 1, hereby
becomes an essential party to the contract, having assumed all rights,
obligations, benefits, responsibilities, and interests related to the
operation and maintenance of the project, previously held by
Respondent No. 3. Additionally, Respondent No. 1 took over the
associated assets and liabilities in accordance with the provisions of
the National Highways Authority of India Act, 1988.
8. Respondent Nos. 2 and 3 have been arrayed as Proforma
Parties since the original agreement for the work was signed between
the Applicant and Respondent No. 2 on behalf of Respondent No. 3.
9. Upon the agreements entered, the Applicant mobilized
sufficient manpower and machinery to ensure the timely completion
of the project. However, the Applicant encountered substantial delays
due to the failure of Respondent No. 2, acting on behalf of
Respondent No. 3, to fulfil its obligations. Various structures,
including private, governmental, and religious buildings, obstructed
the execution of the work. Despite the responsibility of Respondents
Nos. 2 and 3 to remove these structures in consultation with each
other, their failure of swift action resulted in delays and there were
dues payable to the applicant post completion of the project(s).
10. Applicant completed the said work in terms of the agreements
and certificates of completion were also issued in respect of the
aforesaid three contracts. Despite completion of the work in terms of
the agreements, issuance of notices of claim, respondents did not
settled the same. Therefore, it has issued notices invoking the
arbitration clause and nominated arbitrators and sought consent of
respondents. Despite receiving the notices, respondents did not give
consent, therefore, applicant filed the present applications.
11. The Applicant sought to resolve the issues amicably through
communication with the Respondents; however, these efforts were
unsuccessful. Respondent No. 1 subsequently denied liability under
the Contract, asserting that its involvement in the project was limited
to the completion of the Defect Liability Period and toll collection,
and that any claims related to the construction phase should be
directed to Respondent No. 2, acting on behalf of Respondent No. 3.
This stance, taken by Respondent No. 1, was in direct violation of
both the Tripartite Agreement and Sections 11, 12, and 13 of the
National Highways Authority of India Act, 1988.
12. Respondent No. 1 further contended that, as per the terms and
conditions of the agreement, it was only responsible for liabilities
arising from the operation and maintenance of the EPC project. Since
the claims raised by the Applicant pertained primarily to the
construction phase, and Respondent No. 1 was unaware of their
accuracy or authenticity, the Applicant was advised to address these
claims with Respondent Nos. 2 and 3. It is important to note that all
communications related to the invocation of arbitration under Clause
26.3, the request for amicable settlement under Clause 26.2, and the
intimation of claims under Clause 26.1, were duly sent to Respondent
Nos. 2 and 3, in addition to Respondent No. 1, yet no action was
taken by the Opposite Parties.
13. In its counter, Respondent No. 1 further contended that the
agreement dated 19.12.2014 was executed between the Applicant and
the respondent Nos.2 and 3/proforma parties for the rehabilitation and
upgradation of NH-43 in the State of Chhattisgarh under NHDP-IV
through an EPC basis, and not with Respondent No. 1. Therefore, the
claims raised in the current arbitration application, which pertain to
the construction phase, fall outside the purview of Respondent No. 1.
Consequently, Respondent No. 1 rejected the Applicant's claims,
instructing them to approach the Proforma Respondents for
resolution.
14. Considered the rival submissions and perused the record.
Disputes have arisen between the parties even after repeated attempts
to amicably settle the disputes regarding the non-payment of amounts
due to applicant. The applicant invoking Clause 26.3 from the
Engineering Procurement and Construction (EPC) of the parent
agreements, issued legal notices dated 06.09.2022 and 27.09.2023.
15. The said Clause 26.3 of the subject agreement is relevant andis
extracted hereinbelow;
26.3 Arbitration
26.3. 1 Any Dispute which is not resolved amicably by conciliation, as provided in Clause-26.2, shall in accordance with Clause
26.3.2. Such arbitration shall be held in accordance with the Rules of Arbitration of the International Centre for Alternative Dispute Resolution, New Delhi (the "Rules"), or such other rules as may be mutually agreed by the Parties, and shall be subject to the provisions of the Arbitration Act. The venue of such arbitration to shall be (Hyderabad), and the language of arbitration proceedings shall be English.
26.3.2 There shall be a Board of three arbitrators, of whom each party shall select one and the third arbitrator shall be appointed by the two arbitrators and in the event of disagreement between the two arbitrators, the appointment shall be made in accordance with the Rules.
16. The disputes between the parties arose when the Applicant
raised concerns regarding the outstanding dues for the completed
work, asserting that Respondent No. 1 is a necessary party to the
contract, having assumed all rights and liabilities pursuant to the
execution of the Tripartite Agreement dated 07.03.2019. Respondents
No. 2 and 3 have been arrayed as proforma parties in the present
proceedings, given that the agreement for the work in question was
originally signed with Respondent No. 2 on behalf of Respondent No.
3. The Applicant alleges that Respondents failed to fulfil its
contractual obligations, which led to considerable financial losses.
Despite numerous efforts by the Applicant to resolve the matter,
including issuance of a legal notice to initiate arbitration, the
Respondent evaded an amicable settlement of the dispute.
17. In the context of referring matters to the arbitration tribunal, the
role of the Court is now, in any event, severely circumscribed. The
guiding principles enshrined in the Arbitration and Conciliation Act,
1996, have always aimed at minimizing judicial intervention. In this
regard, Section 5 of the Act, is relevant which reads as under:
5. Extent of judicial intervention.--
Notwithstanding anything contained in any other law for the time being in force, in matters governed by this Part, no judicial authority shall intervene except where so provided in this Part.
18. Significant amendments were made to the Arbitration Act in
2015, particularly to Sections 8 and 11, with the objective of further
limiting judicial interference. The amended Section 8 of the
Arbitration Act now reflects this intent, mandating that the judiciary's
involvement in arbitration matters is restricted, except in cases where
it is prima facie evident that no valid arbitration agreement exists.
Section 8 is extracted herein;
8. Power to refer parties to arbitration where there is an arbitration agreement. -- (1) A judicial authority, before which an action is brought in a matter which is the subject of an arbitration agreement shall, if a party to the arbitration agreement or any person claiming through or under him, so applies not later than the date of submitting his first statement on the substance of the dispute, then, notwithstanding any judgment, decree or order of the Supreme Court or any court, refer the parties to arbitration unless it finds that prima facie no valid arbitration agreement exists.
(2) The application referred to in sub-section (1) shall not be entertained unless it is accompanied by the original arbitration agreement or a duly certified copy thereof.
Provided that where the original arbitration agreement or a certified copy thereof is not available with the party applying for reference to arbitration under sub-section (1), and the said agreement or certified copy is retained by the other party to that agreement, then, the party so applying shall file such application along with a copy of the arbitration agreement and a petition praying the court to call upon the other party to produce the original arbitration agreement or its duly certified copy before that court.
(3) Notwithstanding that an application has been made under sub- section (1) and that the issue is pending before the judicial authority, an arbitration may be commenced or continued and an arbitral award made.
19. The primary aim of amending Section 8, alongside Section 11,
was to curtail the scope of judicial authority in arbitration matters,
thereby reinforcing the autonomy of the arbitral process and ensuring
that parties could resolve their disputes with minimal interference
from judicial bodies, except where absolutely necessary where there
is prima facie no agreement for arbitration inter alia.
20. In the present case, it is ipso facto evident that all three parent
agreements, the Engineering, Procurement, and Construction
agreements executed by the parties on 19.12.2014 (two agreements
on same date) and 28.01.2015 expressly incorporate an arbitration
clause under Clause 26.3. There is no dispute regarding the existence
of such an arbitration agreement among the parties.
21. It is apposite to acknowledge that the High Court's jurisdiction
under Section 11 of the Arbitration and Conciliation Act, 1996, is
narrowly confined. The Court's sole responsibility is to ascertain
whether, prima facie, an arbitration agreement exists between the
parties.
22. Regarding the issue of waiver of Respondent No.1 were to be
examined in isolation under a petition filed pursuant to Section 11 of
the Act, the limited scope of the Court's review would necessitate
referring the question of waiver to the arbitral tribunal itself,
particularly given that the respondents are signatories to a subsequent
agreement intended to fulfil the obligations of the original (parent)
agreement containing the arbitration clause now invoked.This Court
at the referral stage cannot go into disputed questions of facts which
are to be decided by the arbitrator.
23. In DuroFelguera, S.A. v. Gangavaram Port Ltd.1 the Apex
Court, at para 59, has held as under:
"The scope of the power under Section 11(6) of the 1996 Act was considerably wide in view of the decisions in SBP and Co. [SBP and Co. v. Patel Engg. Ltd., (2005) 8 SCC 618] and BogharaPolyfab [National Insurance Co.Ltd. v. BogharaPolyfab (P) Ltd., (2009) 1 SCC 267 : (2009) 1 SCC (Civ) 117]. This position continued till the amendment brought about in 2015. After the amendment, all that the courts need to see is whether an arbitration agreement exists nothing more, nothing less. The legislative policy and purpose is essentially to minimise the Court's intervention at the stage of appointing the arbitrator and this intention as incorporated in Section 11(6-A) ought to be respected."
24. After 2015 amendment to the Arbitration and Conciliation Act,
1996, the scope under Sections - 11 (5) and 11 (6) of the Act, 1996 is
very limited. The said fact was also considered by the Apex Court in
(2017) 9 SCC 729
Vidya Drolia v. Durga Trading Ltd.2 laid down the test to exercise
power under Section 11 of the Act, 1996 as follows:
244. Before we part, the conclusions reached, with respect to Question 1, are:
244.1. Sections 8 and 11 of the Act have the same ambit with respect to judicial interference. 244.2. Usually, subject- matter arbitrability cannot be decided at the stage of Section 8 or 11 of the Act, unless it is a clear case of deadwood. 244.3. The court, under Sections 8 and 11, has to refer a matter to arbitration or to appoint an arbitrator, as the case may be, unless a party has established a prima facie (summary findings) case of nonexistence of valid arbitration agreement, by summarily portraying a strong case that he is entitled to such a finding.
244.4. The court should refer a matter if the validity of the arbitration agreement cannot be determined on a prima facie basis, as laid down above i.e. "when in doubt, do refer".
244.5. The scope of the court to examine the prima facie validity of an arbitration agreement includes only: 244.5.1. Whether the arbitration agreement was in writing? Or 244.5.2. Whether the arbitration agreement was contained in exchange of letters, telecommunication, etc.?
244.5.3. Whether the core contractual ingredients qua the arbitration agreement were fulfilled? 244.5.4. On rare occasions, whether the subject-matter of dispute is arbitrable?
25. Upon perusing the submissions and material placed on record,
it is prima facie evident that there are arbitral disputes between the
(2021) 2 SCC 1
applicant and the respondents which form the subject matter of
adjudication by an arbitrator.
26.25. As discussed supra, there is no dispute between the parties
regarding the Arbitration Clause contained in Clause 26.3 of the
agreement. However the respondent No.1 contended that the claims
raised by the applicant in the present applications pertains to the
period that pertains to construction phase and NHAI being unaware
about its execution and authenticity. In the light of the said
contention, it is apt to note that the applicant, respondent No.1, 2
entered into the aforesaid tripartite agreements on the specific terms
and conditions mentioned therein. Clause No.i and ii are relanvant
and the same are extracted below:-
i. That upon signing of this agreement, NHAI will perform all rights, obligations, benefits, responsibilities and interests in respect of operation and maintenance of the authority arising out of the EPC contract shall stand novated to and be performed by and between NHAI and the contractor (Applicant) with effect from 07.03.2019.
ii. As the project High Way is already entrusted to NHAI, all assets and liabilities of Ministry of Road, Transport and High Ways, pertaining to the project High Way will deemed to rest with NHAI, in accordance to para-12 under the head PROPERTY AND
CONTRACTS of the NHAI Act, 1988 with effect from 07.03.2019.
27. In the light of the same, the aforesaid contentions of the 1st
respondent are disputes that are to be adjudicated by the Arbitration
Tribunal. Therefore, it is appropriate to refer the dispute to
arbitration. The parties are at liberty take all the available defences
before the learned arbitrator.
28. In light of the aforesaid discussion and the law laid down by
the Supreme Court, the present arbitration application is allowed.
Accordingly, Sri Justice V. Ramasubramanian, Former Judge,
Supreme Court of India is appointed as the sole arbitrator to
adjudicate the disputes between the parties.
As a sequel thereto, miscellaneous applications, if any, pending
in these Arbitration Applications shall stand closed.
________________________ JUSTICE K. LAKSHMAN Date: 18.09.2024.
vvr.
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!