Citation : 2024 Latest Caselaw 2564 Tel
Judgement Date : 8 July, 2024
THE HON'BLE THE CHIEF JUSTICE ALOK ARADHE
AND
THE HON'BLE SHRI JUSTICE ANIL KUMAR JUKANTI
WRIT APPEAL No.808 of 2024
JUDGMENT:
(Per the Hon'ble the Chief Justice Alok Aradhe)
Mr. K.R.Kaushal Karan, party-in-person representing
the appellant-M/s. V.K.A. Constructions.
Mr. I.V.Siddhivardhana, learned Special Government
Pleader for the respondents.
2. This intra court appeal emanates from an order
dated 02.01.2024 passed by learned Single Judge in
W.P.No.10777 of 2019, by which writ petition preferred by
the appellant has been disposed of.
3. Facts giving rise to filing of this appeal briefly
stated are that the appellant claims to be the firm
registered as a Special Class Contractor with Government
of Telangana and is engaged in executing road works on
contract basis with various Departments of the State
Government including the respondents. The Engineer-in-
::2::
Chief (R&B), National Highways, floated a tender on
30.12.2016 for the work of "Widening & Strengthening of
Nadergul to Sagar PWD Road (via) Adibatla, Kongarakalan,
Mangalpally from KM 0/0 to 17/5 (Working Reach from
KM 0/0 to 9/0) in Ranga Reddy District". The appellant
participated in the aforesaid tender and was declared as
successful bidder. A letter of acceptance dated 15.02.2017
was issued to it by the Superintending Engineer (R&B),
National Highways. According to the appellant, it
proceeded with the work which was awarded to it after
obtaining working drawings. However, it is the case of the
appellant that it was forced to do the work which was
beyond the specified working reach without any written
approval. It is the case of the appellant that 90% of the
project work is complete. However, even payment of
admitted bills has not been made to it.
4. The appellant therefore approached the
Superintending Engineer (R&B), National Highways on
28.11.2018 seeking release of payments due to it. The
appellant thereafter by communication dated 28.12.2018, ::3::
delivered to the appellant on 11.01.2019, was asked to
resume the work notwithstanding the fact that the work
awarded to it was not in existence. The appellant
thereupon on 18.01.2019 invoked clause 23.1 of the
conditions of contract and requested the Executive
Engineer (R&B), National Highways to treat the contract as
closed. It is the case of the appellant that under the
coercion exercised by the respondents, the appellant
sought extension of time upto 30.06.2019 to execute the
balance work. It is the case of the appellant that the time
for completion of the remaining work was extended upto
30.06.2019 without any liquidated damages. Thereafter,
the contract awarded to the appellant is terminated on
04.05.2019.
5. The appellant thereupon filed a writ petition
before the learned Single Judge namely W.P.No.10777 of
2019, in which a writ of mandamus was sought seeking the
quashment of termination notice dated 04.05.2019 as well
as subsequent ratification dated 21.05.2019. The
appellant sought a direction to the respondents to make ::4::
payment of the admitted amount of bill to the tune of
Rs.62,30,212.00.
6. Learned Single Judge by an order dated
02.01.2024 disposed of the writ petition namely
W.P.No.10777 of 2019 with the direction to the
respondents to make payment of the admitted amount of
the bill. However, it was held that the issue pertaining to
termination of contract requires adjudication of disputed
questions of fact which may not be adjudicated in a
summary proceeding under Article 226 of the Constitution
of India. The appellant therefore relegated to avail of the
alternative remedy provided to it under the law. In the
aforesaid factual background, this intra court appeal has
been filed.
7. Party-in-person submitted that he has not
abandoned the work and the Superintending Engineer
(R&B), National Highways, has not ratified the order of
termination dated 04.05.2019. It is further submitted that
the order of termination of the contract dated 04.05.2019
is arbitrary and is violative of fundamental right of the ::5::
appellant to carry on business. It is further submitted that
though appellant was ready and willing to perform the
remaining part of the contract, yet the appellant was not
allowed to do so and was forced to apply for extension of
time after the period of contract has expired. It is therefore
submitted that order of termination of contract dated
04.05.2019 be set aside and the appellant be permitted to
carry out the balance work. In support of his submission,
party-in-person has relied on decision of Supreme Court in
ABL International Ltd. v. Export Credit Guarantee
Corporation of India Ltd. 1.
8. We have considered the submission made by
party-in-person and have perused the order dated
02.01.2024 in W.P.No.10777 of 2019.
9. Learned Single Judge in paragraph 24 of the
order dated 02.01.2024 in W.P.No.10777 of 2019 has
recorded as follows:
"24. In the above conspectus of facts, the following disputed questions arise for consideration:
1 (2004) 3 SCC 553 ::6::
a) Whether there was any default on the part of the respondent authorities in handing over drawings/design to the petitioner and whether petitioner was pressurized to go ahead without the said drawings;
b) Whether the bills of the petitioner were withheld from time to time;
c) Whether the petitioner was pressurized to apply for extension of time and additional work was done by the petitioner on oral instructions of the authorities;
d) Whether the respondents No.6 and 7 stopped the work of the petitioner citing public criticism and for any other reason;
e) Whether the petitioner rightly invoked clause 23 of the conditions of the contract vide letter dated 18.01.2019 for closure of contract and to settle the account to the extent of the work done;
f) Whether the petitioner sought extension of time under pressure from the respondent authorities by not releasing the bill payments;
g) Whether rider "without positive price variation"
insisted upon by the respondent No.4 vide letter dated 18.03.2019 for extension of time granted by the respondent No.2 up to 30.06.2019 is valid;
h) Whether the termination notice dated 04.05.2019 is antedated and the action of the respondents No.4 and 5 is malafide;
i) Whether there is deficiency in the work done by the petitioner;
j) Whether the petitioner defaulted in completing the work within the period of contract and extended period by way of extension of time;
::7::
k) Whether there was loss caused to the respondent-department due to alleged abandoning of the work by the petitioner."
10. Undoubtedly, it is true that if a State or its
instrumentality acts in an arbitrary, unfair and irrational
manner even in contractual plea, this Court in exercise of
powers under Article 226 of the Constitution of India can
entertain the petition and can interdict such an arbitrary
action. However, it is equally well settled legal proposition
that High Court in exercise of powers under Article 226 of
the Constitution of India does not adjudicate the disputed
questions of fact (See Shubhas Jain v. Rajeshwari
Shivam 2). Similar view was taken in Radha Krishan
Industries v. State of Himachal Pradesh 3 and it has been
held that if in case disputed questions of fact arise for
determination in a writ petition, the High Court may
decline to exercise the writ jurisdiction.
11. In the instant case, whether the rescission of
the contract is arbitrary or is irrational or the power to
rescind the contract has been exercised in consonance with
2 2021 SCC OnLine SC 562 3 (2021) 6 SCC 771 ::8::
the terms and conditions of the contract depends upon
adjudication of disputed questions of fact which cannot be
gone into in a summary proceeding under Article 226 of
the Constitution of India. Therefore, the learned Single
Judge has rightly declined to exercise the extraordinary
jurisdiction under Article 226 of the Constitution of India
and has relegated the appellant to avail of the alternative
remedy available to it in law.
12. For the aforementioned reasons, we do not find
any ground to differ with the view taken by the learned
Single Judge.
13. In the result, the Writ Appeal fails and is hereby
dismissed.
Miscellaneous applications, if any pending, shall
stand closed. There shall be no order as to costs.
_______________________________ ALOK ARADHE, CJ
_______________________________ ANIL KUMAR JUKANTI, J Date: 08.07.2024 KL
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!