Citation : 2022 Latest Caselaw 2321 Tel
Judgement Date : 6 June, 2022
W.P.No.37418 of 2021
1
THE HONOURABLE SMT. JUSTICE P.MADHAVI DEVI
WRIT PETITION No.37418 of 2021
ORDER:
This Writ Petition has been filed seeking a writ of
mandamus declaring the action of the Respondent company in
refusing to execute Gas Sales Agreement with the petitioner and
demanding payments from the petitioner on the ground of non-
payments of alleged disputed amounts under the Gas Sales
Agreement dated 21.02.2011 and 05.01.2016 as arbitrary, illegal
and consequently to direct the Respondent to execute the Gas Sales
Agreement on such lawful terms as may be mutually agreed upon
without insisting for payment of the alleged outstanding dues
payable by the petitioner under the Gas Sales Agreement dated
21.02.2011 and 05.01.2016 and to pass such other orders as this
Court may deem fit and proper in the circumstances of the case.
2. Brief facts leading to filing of this Writ Petition are that
the petitioner is a company incorporated under the provisions of
Companies Act, 1956 and is engaged in the business of generation
of electricity and supply of electricity to end users including the State
Governments. It is submitted that upon receiving the necessary W.P.No.37418 of 2021
sanctions, the petitioner had set up a plant at Ramanathapuram
District, Tamil Nadu for the said purpose. The Respondent, namely
Gas Authority of India Limited (GAIL) is a Public Sector Undertaking
(PSU) under the Ministry of Petroleum & Natural Gas (MoP & NG)
incorporated in the year 1984. It is a Government Company
primarily engaged in the transmission/distribution and marketing of
gas in India and is also engaged in other aspects of gas value chain
including exploration, production, transmission, extraction,
processing of natural gas and its related processes, products and
services.
3. On 21.02.2011, the petitioner and the Respondent
entered into an agreement for purchase of gas at the price as fixed
by the Government under the Administered Pricing Mechanism
(APM) and the agreement is called as Gas Sales Agreement (GSA-I)
and the same was extended from time to time with the last
Addendum dated 29.01.2018 extending the period of agreement till
30.06.2021. There was second Gas Sales Agreement dated
05.01.2016 (GSA-II) whereby the Respondent had agreed to sell
natural gas with the maximum daily contracted quantity (DCQ) being
reckoned as 2,98,000 SCMD sourced from ONGC at the plant and W.P.No.37418 of 2021
the petitioner agreed to purchase the gas at the price as per the
market for the Market Driven Priced (MDP) Gas and the GSA-II was
valid till 05.07.2021. It is submitted that as per the terms of GSA-I
and GSA-II, the petitioner purchased the gas from the Respondent
from time to time as per the terms agreed to between the parties
and made payments towards the same.
4. While the matter stood thus, on 04.06.2020 at around
11.00 PM, a major explosion had occurred at the plant of the
petitioner causing fire in the 110 KV switch yard PT and eventually
resulted in the breakdown of the switch yard. As a result, the power
plant tripped and no power was being generated and the operations
in the plant had to be stopped. Consequently, the petitioner
addressed a letter dated 05.06.2020 to the Respondent informing
that due to the events that transpired on 04.06.2020 and
05.06.2020 which constitute a 'force majeure' event as under the
aforesaid agreement, the petitioner would not be able to accept the
gas supplies for consumption until reinstatement of power
generation equipment in the plant. Vide the said letter, it was also
requested that during the period of shutdown of the plant, the gas
supply will not be eligible for claiming MGO and thus no invoices W.P.No.37418 of 2021
may be raised against MGO i.e. Minimum Guarantee Obligation till
such time, the force majeure event is cleared and the plant goes
into operation. Since there was no response from the Respondent,
the petitioner addressed another letter dated 16.06.2020. In
response to the petitioner's letter dated 05.06.2020, the Respondent
addressed a letter dated 17.06.2020 stating that the breakdown of
the switch yard is not covered under 'Force Majeure' Event and
hence, the request of the petitioner is not acceptable. It was further
informed that the gas supplies to the petitioner shall be resumed
only after clearing all the outstanding dues along with applicable
interest and reinstatement of valid LC in terms of the Agreement.
The Respondent also raised invoices on 10.07.2020 demanding the
payment from the petitioner. The petitioner vide letter dated
18.07.2020 replied explaining as to how the events constituted a
'force majeure' event and how the same was beyond the reasonable
control of the petitioner and the steps being taken by it to preserve
the plant. The petitioner therefore requested the Respondent to
refrain from any invoices/claims till such time, the 'force majeure'
event is cleared.
W.P.No.37418 of 2021
5. On 22.07.2020, the Respondent addressed a letter to
the petitioner stating that the petitioner is in appropriately portraying
the breakdown of switch yard as 'force majeure' event, which is
untenable, unjust and irrational. The petitioner was therefore
requested to take steps to rectify the defect for resumption of gas
supply and that all the contractual obligations including take or
Pay/MGO obligations and invoicing are applicable and that the
petitioner is liable to make payments.
6. The Respondent, thereafter, issued debit notes dated
22.06.2021 informing that the account of the petitioner has been
debited with
a) An amount of Rs.5,25,16,178/- towards Take or Pay
Obligation for MDP Gas for the FY 2020-21.
b) An amount of Rs.2,84,10,302/- towards Take or Pay
Obligation for APM Gas for the FY 2020-21.
7. These debit notes were however, disputed by the
petitioner vide letter dated 26.07.2021 stating that the Debit Notices
cannot be raised due to occurrence of a 'Force Majeure' Event and
that no amounts are liable to be paid. However, the Respondent W.P.No.37418 of 2021
addressed letters dated 05.08.2021 and 08.09.2021 seeking
payment of the invoices raised against the petitioner. The
correspondence between the petitioner and the Respondent with
regard to the above debit notes continued and further on
30.10.2021 the Respondent raised two provisional debit notes
i) for annual MGO-RMD-MDP Gas for FY 2020-21 to the tune of
Rs.6,19,69,090/- and
ii) for annual MGO-RMD-APM Gas for FY 2020-21 to the tune of
Rs.3,35,24,156/-.
8. It is submitted that on 09.12.2021 the petitioner
addressed a letter to Respondent informing that their power plant is
likely to resume operations during January, 2022, thus, requested
the Respondent to initiate necessary steps to resume gas supply to
the power plant. However, the Respondent addressed a letter dated
10.12.2021 to the petitioner calling upon the petitioner to clear the
outstanding dues to the tune of Rs.10,97,92,303/- payable on
account of MGO, interest on delayed payments etc so as to proceed
with signing of new Gas Sales Agreements towards gas sale and
supply. The petitioner replied that fresh/new Gas Sales Agreement
for the upcoming years are independent of the old Gas Sales W.P.No.37418 of 2021
Agreements and the claims made thereunder and any demand on
the petitioner to pay the alleged outstanding dues in order to enter
into fresh Gas Sales Agreements is coercive and arbitrary.
9. It is submitted that the petitioner had suffered great
losses as a result of the explosion that occurred at the plant and
therefore, refusal of the Respondent to execute fresh Gas sales
Agreements for the upcoming years but insisting on payment of the
dues of the earlier years when there was a dispute with regard to
the same is unjust and arbitrary and constitutes an abuse of power.
Challenging the said action of the Respondent in not entering into
fresh Gas Sales Agreements and insisting for payment of the
amounts as raised in the debit notes under the previous
agreements, this Writ Petition has been filed.
10. Learned counsel for the petitioner has drawn attention
of this Court to the earlier agreements i.e. GSA-I and II entered into
by the petitioner with the Respondent and also the request made by
the petitioner for supply of Gas in order to resume the generation of
power by the petitioner.
W.P.No.37418 of 2021
11. Learned standing counsel appearing for the Respondent
raised preliminary objections about the maintainability of this Writ
Petition. It is submitted that as per the GSA-I and II, this Court
lacks territorial jurisdiction. It is submitted that the office of the
Respondent is situated at Delhi and the Gas Sales Agreement in
question was executed in Chennai and the Gas Supply under the
said Agreement shall be made from the Gas Fields from the State of
Tamilnadu and the contract in question was awarded by GAIL,
Chennai. Therefore, according to the learned counsel for the
Respondent, the action impugned in this Writ Petition has taken
place in Chennai. Therefore, no cause of action either in full or in
part has arisen in the State of Telangana over which this Court is
having territorial jurisdiction and therefore, this writ petition is liable
to be dismissed on the very same ground.
12. The second objection taken by the learned counsel for
the Respondent is that under Article 15 of the GAS, there is a clause
for arbitration for settlement of any dispute arising out of the said
agreement, if the same cannot be resolved amicably in conciliation
proceedings and the venue of the said arbitration shall be at New
Delhi. Therefore, according to him, since the contract was signed in W.P.No.37418 of 2021
Chennai and the territory of the State of Telangana has no
connection with the agreement in question or its performance or the
disputes arising thereunder, hence, this Court is not having territorial
jurisdiction to entertain the present Writ Petition or to adjudicate the
dispute raised by the petitioner. It is also submitted that earlier, the
petitioner filed Arbitration Application No.35 of 2020 in this Court
under Section 11 of the Arbitration & Conciliation Act, 1996 for
appointment of an Arbitrator for resolution of alleged dispute arising
out of the Gas Transmission Agreement dated 05.04.2017 and by
order dated 28.12.2020, this Court dismissed the said Application on
the ground that this Court has no territorial jurisdiction to entertain
the said application. The copy of the said order is filed and marked
as Ex.R1. Therefore, according to the learned counsel for the
Respondent, viewing from any angle, this Writ Petition is not
maintainable in this Court. The Respondent therefore, raised the
above preliminary objections. A copy of the above mentioned order
of this Court is also filed before this Court.
13. Learned counsel for the Respondent also placed reliance
upon the following two other decisions:
W.P.No.37418 of 2021
i) Nagarjuna Cerachem (P) Ltd., Hyderabad v. GAIL (India) Ltd.,
Hyderabad reported in 2004 (6) ALD 259 (DB)
ii) Consortium of Sai Rama Engineering Enterprises and Megha
Engineering and Infrastructures Ltd., Hyderabad v. Oil and
Natural Gas Corporation Ltd., New Delhi and others reported
in 2016 (2) ALD 495.
14. Learned counsel for the petitioner, on the other hand,
disputed the argument of the Respondent stating that this Court has
territorial jurisdiction over the issues raised in the present Writ
Petition as the registered office of the petitioner is situated in
Hyderabad and principal place of business of the petitioner is placed
in Hyderabad and further that all the communication from the
Respondent was received by the petitioner in Hyderabad at its
registered office and therefore, the cause of action arose partly
within the territorial jurisdiction of this Court. In this regard, he
placed reliance upon the judgment of this Court dated 25.10.2018 in
Writ Appeal No.1430 of 2018. It is submitted that the jurisdiction of
a High Court to issue Writs is not restricted only to the territories in
relation to which it exercises jurisdiction and the writs can as well be
issued to any Government, authority or person situated/resided W.P.No.37418 of 2021
beyond its territorial limits provided, the cause of action, wholly or in
part has arisen within the territory in relation to which it exercises
jurisdiction and that even if a small fraction of cause of action arises
within the territory in relation to which the High Court exercises
jurisdiction, it shall have jurisdiction to entertain the Writ Petition
notwithstanding the fact that the situs of the office of all the
Respondents is situated outside its territorial jurisdiction. He placed
reliance upon the decision of this Court in United Shippers Ltd., vs.
Volta Impex P.Ltd. and Ors., reported in 2008 (4) ALD 665. He
further submitted that in respect of the earlier agreements and the
disputes relating thereto, the petitioner has already invoked the
arbitration clause and the arbitration proceedings are pending, but
this being an application made for fresh supply of gas, under a fresh
agreement, he submits that the earlier clause of arbitration would
not apply to the present circumstances.
15. Learned counsels for both the parties vehemently
contested the issue. Having regard to the rival contents and the
material on record, this Court finds that at the outset, the
preliminary objection of the Respondent has to be considered and
decided.
W.P.No.37418 of 2021
16. Admittedly, the registered office of the Respondent is at
Chennai and the agreement has also been signed at Chennai and
the supply of gas is also from Chennai. In so far as the arbitration
application is concerned, this Court has considered that the
arbitration clause in the agreement itself contains the venue of
arbitration and therefore irrespective of where the cause of action
has arisen, as the place is mentioned in the arbitration clause, the
Courts in which the arbitration is to be carried on have the territorial
jurisdiction of appointing the arbitrator. New Delhi was the venue as
mentioned in the arbitration clause, therefore, this Court has held
that this Court has no territorial jurisdiction to appoint the arbitrator
to resolve the dispute between the parties. This Court however,
finds that the said order would not ipso facto apply to the case on
hand.
17. Learned counsel for the petitioner has placed reliance
upon the judgment of this Court in the case of Writ Appeal No.1430
of 2018 the relevant portion of the said judgment is as reproduced
hereunder:
"7. The Apex Court in Nawal Kishore Sharma case (supra 1), after exhaustively taking note of binding precedents on Article W.P.No.37418 of 2021
226(2) of Constitution of India, has held that if part or fraction of cause of action arises within the territorial jurisdiction of High Court, then, the writ petition is maintainable before the High Court where the fraction of cause of action has arisen. The Apex Court in Nawal Kishore Sharma case (supra 1), was dealing with a fact situation where the rejection order was received by the petitioner, where he was residing at the time of communication. The operative portion of the judgment reads thus;
"The interpretation given by this Court in the aforesaid decisions resulted in undue hardship and inconvenience to the citizens to invoke writ jurisdiction. As a result, Clause 1(A) was inserted in Article 226 by the Constitution (15th) Amendment Act, 1963 and subsequently renumbered as Clause (2) by the Constitution (42nd) Amendment Act, 1976. The amended Clause (2) now reads as under:-
"226. Power of High Courts to issue certain writs
-
(1) Notwithstanding anything in article 32, every High Court shall have power, throughout the territories in relation to which it exercises jurisdiction, to issue to any person or authority, including in appropriate cases, any Government, within those territories directions, orders or writs, including writs in the nature of habeas corpus, mandamus, prohibition, quo warranto and certiorari, or any of them, for the enforcement of any of the rights conferred by Part III and for any other purpose.
(2) The power conferred by Clause (1) to issue directions, orders or writs to any Government, authority or person may also be exercised by any High Court exercising jurisdiction in relation to the territories within W.P.No.37418 of 2021
which the cause of action, wholly or in part, arises for the exercise of such power, notwithstanding that the seat of such Government or authority or the residence of such person is not within those territories.
On a plain reading of the amended provisions in Clause (2), it is clear that now High Court can issue a writ when the person or the authority against whom the writ is issued is located outside its territorial jurisdiction, if the cause of action wholly or partially arises within the Court's territorial jurisdiction. Cause of action for the purpose of Article 226 (2) of the Constitution, for all intent and purpose must be assigned the same meaning as envisaged under Section 20(c) of the Code of Civil Procedure. The expression cause of action has not been defined either in the Code of Civil Procedure or the Constitution. Cause of action is bundle of facts which is necessary for the plaintiff to prove in the suit before he can succeed. The term 'cause of action' as appearing in Clause (2) came for consideration time and again before this Court".
In Kusum Ingots & Alloys Ltd. vs. Union of India and Another, (2004) 6 SCC 254, this Court elaborately discussed Clause (2) of Article 226 of the Constitution, particularly the meaning of the word 'cause of action' with reference to Section 20(c) and Section 141 of the Code of Civil Procedure and observed:-
"9. Although in view of Section 141 of the Code of Civil Procedure the provisions thereof would not apply to writ proceedings, the phraseology used in Section 20(c) of the Code of Civil Procedure and clause (2) of Article 226, being in pari materia, the decisions of this Court rendered on interpretation of Section 20(c) CPC shall apply to the writ proceedings also. Before proceeding W.P.No.37418 of 2021
to discuss the matter further it may be pointed out that the entire bundle of facts pleaded need not constitute a cause of action as what is necessary to be proved before the petitioner can obtain a decree is the material facts. The expression material facts is also known as integral facts.
10. Keeping in view the expressions used in clause (2) of Article 226 of the Constitution of India, indisputably even if a small fraction of cause of action accrues within the jurisdiction of the Court, the Court will have jurisdiction in the matter."
Their Lordships further observed as under:- "29. In view of clause (2) of Article 226 of the Constitution of India, now if a part of cause of action arises outside the jurisdiction of the High Court, it would have jurisdiction to issue a writ. The decision in Khajoor Singh has, thus, no application.
30. We must, however, remind ourselves that even if a small part of cause of action arises within the territorial jurisdiction of the High Court, the same by itself may not be considered to be a determinative factor compelling the High Court to decide the matter on merit. In appropriate cases, the Court may refuse to exercise its discretionary jurisdiction by invoking the doctrine of forum conveniens."
8. In the case on hand, the petitioner received letter dated 01.08.2018 within the territorial jurisdiction of this Court and hence it cannot be held that only the Courts in Delhi have jurisdiction to entertain the writ petition. The decision relied on by 1st Respondent is distinguishable on fact and the legal principles considered and decided by the Apex Court.
W.P.No.37418 of 2021
18. In the above judgment, this Hon'ble Court has held that
even if a part or fraction of cause of action arises within the
territorial jurisdiction of a High Court, then the writ petition is
maintainable before the said High Court, where the fraction of cause
of action has arisen. As seen from the above facts, the Apex Court
in Nawal Kishore Sharma was dealing with a situation where the
rejection order was received by the petitioner, where he was
residing at the time of communication, therefore, it was held that
the place where the petitioner received the letter of rejection is
within the territorial jurisdiction and hence can entertain the Writ
Petition.
19. In the case of M/s.United Shippers Ltd., vs. Volta Impex
P.Ltd. and Ors., reported in 2008 (4) ALD 665 also it was held that
the High Court within whose jurisdiction the cause of action arises
wholly or in part, would also have jurisdiction to entertain an
application under Article 226 and to issue a Writ to any Government
authority or person irrespective of the fact that the seat of said
government or authority was located beyond its territorial
jurisdiction.
W.P.No.37418 of 2021
20. On the other hand, the Respondent has relied upon the
judgment of this court in the case of Nagarjuna Cerachem (P) Ltd.,
Hyderabad v. GAIL (India) Ltd., Hyderabad. In the said case, the
question before the court was whether a writ was maintainable
when there was a clause for arbitration in the agreement. It was
held that, admittedly when there was an arbitration clause in the
agreement, the dispute will have to be referred to arbitration and it
is not permissible to entertain the writ petition. The other judgment
relied upon by the respondent is in the case of Consortium of Sai
Rama Engineering Enterprises and Megha Engineering and
Infrastructures Ltd., Hyderabad v. Oil and Natural Gas Corporation
Ltd., New Delhi and others. In this case, the issue was with regard
to territorial jurisdiction of the High Court of judicature of Hyderabad
for the State of Telangana and for the State of Andhra Pradesh,
where bank guarantee was given at Hyderabad but since it was
conditional and there being no allegation of breach of contract, it
was held that the same cannot be invoked and further there was no
pleading as to how part of cause of action has arisen within the
territorial jurisdiction of High Court at Hyderabad. Therefore, both
these judgments are not exactly on similar issue before this Court.
W.P.No.37418 of 2021
21. In the case on hand, as rightly pointed out by the
learned counsel for the petitioner, the petitioner has requested the
respondent for entering into a fresh agreement for supply of gas and
for this purposes, there is no agreement which is signed yet and
therefore, there was no arbitration clause and further, even in the
letter of the Respondent dated 10.12.2021, the petitioner was
informed that unless the outstanding dues payable by the petitioner
on account of MGO, interest on delayed payments etc., which as on
date is Rs.10,97,92,303/- is paid, the Respondent will not be able to
proceed for signing the requisite agreements towards start of gas
supplies, is received in the Hyderabad. Therefore, it is a fresh cause
of action and the situs of cause of action being in Hyderabad, this
Writ Petition is maintainable. It is pertinent to mention that vide
letter dated 10.12.2021, the Respondent themselves have
mentioned that old agreements (GSA/Term Sheet) have expired in
July, 2021 and new GSTA has to be signed for commencement of
gas supplies. Therefore, both the petitioner as well as the
Respondent have understood the request of the petitioner as a fresh
application for supply of gas and also that fresh terms and
conditions have be negotiated and fresh agreements have to be
signed. In view thereof, the dues which are payable by the W.P.No.37418 of 2021
petitioner under the old agreements are subject to the arbitration
clauses and the decision of this Court in Arbitration Application
No.35 of 2020 would be applicable and both the parties would have
to approach the concerned Court having territorial jurisdiction with
regard to arbitration.
22. In view thereof, this Court finds that this Writ Petition is
maintainable and accordingly, the preliminary objections of the
Respondent are rejected.
23. As regards, the issue, it is seen that the present case
with regard to entering into fresh agreement of sale of gas. This
Court finds that the Respondent cannot insist on payment of old
dues for entering into a fresh agreement. It is not disputed that the
GAIL is having 70% share in the market for supply of gas and is
therefore trying to pressurize the petitioner to make the payments of
disputed amounts for entering into fresh gas supply agreement.
24. In view of the same, the Respondent is directed to
consider the application of the petitioner independent of the earlier
agreements and take a decision on the application of the petitioner
expeditiously i.e. preferably within a period of thirty (30) days from W.P.No.37418 of 2021
the date of receipt of copy of this order and communicate the same
to the petitioner.
25. The Writ Petition is accordingly allowed. No order as to
costs.
26. Miscellaneous applications, if any pending, shall also
stands closed.
_________________________ JUSTICE P.MADHAVI DEVI Date: 06.06.2022 ns
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!