Citation : 2022 Latest Caselaw 289 Tel
Judgement Date : 28 January, 2022
HON'BLE SMT. JUSTICE P.SREE SUDHA
SECOND APPEAL No.658 of 2012
JUDGMENT
1. This Second Appeal is directed against the judgment and
decree dated 15.07.2010 in A.S.No.126 of 2005 on the file of the
Court of the XX Additional Chief Judge, City Civil Court,
Secunderabad, whereunder and whereby the appeal filed by
Secunderabad Cantonment Board represented by its Chief
Executive Officer challenging the judgment and decree dated
17.02.2005 in O.S.No.162 of 1997 on the file of the learned
III Senior Civil Judge, City Civil Court, Secunderabad, was
dismissed.
2. The appellant herein is the defendant and the respondent
herein is the plaintiff in O.S.No.162 of 1997. For the sake of
convenience, the parties hereinafter are referred to as they are
arrayed in the said suit.
3. At the time of admission of this appeal, the appellant is
permitted to serve personal notice to the respondent-plaintiff by
Registered Post with Acknowledgment Due. But, the postal
endorsement shows that the envelope was returned with an
endorsement 'unclaimed', which amounts to deemed service.
4. Heard the learned counsel for the appellant.
5. The following substantial questions of law are sought to be
raised by the appellant-defendant:
i) The plaintiff did not exhaust the remedy available within
the ambit of the Cantonment Act, 1924 (for short, 'the Act of 1924')
under Section 274 but approached the trial Court hastily and as
such the suit is liable to be dismissed. It was further contended
that the appellate Court erred in relying on the decision of this
Court in 3 ACES, HYDERABAD V/s. MUNICIPAL CORPORATION
OF HYDERABAD1 though it has no relevance to the case on hand.
ii) The appellate Court failed to appreciate Section 185 of
the Act of 1924 in true perspective and erred in decreeing the suit
against the Secunderabad Cantonment Board (for short, 'the
Board') defeating the very purpose of the Board with power and
authority to regularize construction and re-construction in public
interest.
iii) The respondent herein is only a General Power of
Attorney (GPA) Holder but not owner of the schedule property, but
it was not considered by both the Courts below.
iv) Respondent obtained for two separate plans but
constructed one building clubbing both the plans and violated the
building bye laws.
v) Though the Board issued notices to the respondent to
stop construction, it did not stop the construction and appeared
before the Board. Admittedly, the sanction was accorded only for
stilt, ground and two upper floors, but the respondent constructed
cellar, ground and three upper floors and as such the construction
of stilt and third floor is unauthorized. More over, the respondent
did not intimate about the commencement of construction or
AIR 1995 AP 17 (FB)
completion of the construction and it did not obtain plinth
checking certificate from the Board.
vi) D.W.1 admitted that they failed to maintain FSI as per
the sanction accorded by the Board and the said admission itself is
sufficient for dismissal of the suit. Further, D.W.1 also admitted
that stilt floor was converted into a regular floor and there was no
sanction for construction of the cellar and third floor and that the
respondent did not stop the construction activities in spite of
receiving the notices and proceeded with the construction.
vii) The appellate Court ought to have dismissed the suit
on the ground that the appellant is a civic body authorized to
check the unauthorized constructions within the cantonment and
the Board initiated proceedings in the interest of general public but
erred in holding that no deviations and does not call for resorting
to the extreme step of demolition.
6. The plaintiff filed O.S.No.162 of 1997 claiming that
Mrs.Sharada Srinivas and Mrs.Ranjani Rangarajan were joint
owners of the land admeasuring 1325 square yards in Sy. Nos.17
to 23 with a house bearing No.3-9-105, Krishna Bhavan,
Krishnapuri West Marredpally, Secunderabad, (hereinafter referred
to as 'suit schedule property'), having got the same by way of a
Memorandum of Settlement dated 16.07.1993 between Sri
B.K.Seshu and Smt.Sharada Srinivasan and Smt.Ranjani
Rangarajan. The plaintiff entered into a Development Agreement
with the joint owners on 20.10.1993 for development of the land by
constructing residential complex after demolishing the existing
structures. The joint owners also executed a General Power of
Attorney in favour of the plaintiff on 30.10.1993. They obtained
ULC Certificate dated 25.08.1980 from the Office of the Ministry of
Defence, New Delhi. They also applied for approval of the plans for
construction of multistoried complex under Section179 of the Act
of 1924. The Board sanctioned plans vide its Resolution No.28(4)
dated 04.12.1995 and Resolution No.40 dated 04.12.1995. The
sanctioned plan consists of stilt floor, ground, first and second
floors. As per the specifications mentioned in the plan, the plaintiff
constructed multistoried complex. While construction was going
on, the representative of the Board inspected the suit schedule
property for several times, but not raised any objection. Though
there are no deviations or alterations, the Board issued notice
under Section 185 of the Act of 1924 directing the plaintiff to
remove the unauthorized constructions only with an intention to
harass the plaintiff and by that time the plaintiff completed the
entire construction in the suit schedule property except the wiring
and plastering work in the second floor. The prospective
purchasers of the plots were also intended to join in their
respective plots. The plaintiff states that it commenced the
construction and completed the same within one year and
possession of flats were also delivered to the respective flat owners.
The plaintiff would aver that it did not violate the rules and
regulations or bye laws of the Board. In view of the notice issued
by the Board, it may resort to demolish the structures, in which
event the plaintiff would sustain great financial loss, and as such,
the plaintiff gave reply notice on 04.03.1997 for regularizing the
constructions. The plaintiff further aver that there is no necessity
to the Board to issue notice under Section 273 of the Act of 1924
and that the suit is filed only for mere injunction and requested
the Court to grant permanent injunction restraining the Board
from interfering with the peaceful possession in respect of the suit
schedule property or demolition of the structures.
7. In the written statement filed by the defendant, it is
contended that Mrs.Sharada Srinivas and Mrs.Ranjani Rangarajan
were joint owners. They gave building application for permission to
construct a residential complex. Plans were sanctioned on
04.12.1995 permitting them to construct multistoried building
consisting of stilt, ground, first and second floors. The total plot
area as per the sanctioned plan and title documents was 1175
square yards. Both of them obtained permission for construction of
their respective buildings under two separate sanctioned plans.
During routine site inspection, the concerned area Supervisor
Mr.M.Phani Kumar found that the plaintiff was constructing one
residential complex buy clubbing two sanctions and deviated from
the original sanctioned plan and when the construction was in
progress the representative of the Board inspected the suit
schedule property and raised an objection. The plaintiff
constructed RCC columns in the setback area, which is in gross
violation of the sanctioned plan and against the building byelaws.
The cellar floor was constructed unauthorisedly which was not
sanctioned and thus the Board treated it as unauthorized
construction and the owners are guilty of committing the offence
punishable under Section 184 of the Act of 1924. A preliminary
show cause notice was issued under Notice No.EB/House No.3-9-
105/M'pally/4597 dated 06.11.1996 directing the plaintiff to
remove the unauthorized construction. As the plaintiff did not stop
the construction in spite of receipt the said show cause notice, a
notice under Section 185 of the Act of 1924 was issued on
09.12.1996. The said notice was issued after passing resolution by
the elected representative of the people under Resolution CBR
No.3(2) dated 26.11.1996. The set backs are not provided and the
common areas are encroached. Cellar floor was unauthorisedly
constructed and construction was in gross violation of the building
byelaws. The photographs of the unauthorized construction were
filed as Document Nos.1 and 2, attested copy of the report of the
Supervisor filed as Document No.3, office copy of the notice under
Section 185 of the Act of 1924 was filed as Document No.4 and the
sanctioned plan is filed as Document No.5. It is further contended
that the plaintiff or the owners had the absolute right to prefer an
appeal before the Competent Authority under Section 274 of the
Act of 1924, but it did not choose to avail the said facility or the
remedy available to it under the statute. The plaintiff did not give
reply to the show cause notice. As the right of hearing was
provided and the plaintiff had an opportunity of preferring an
appeal against the proceedings under Section 185 of the Act of
1924, the suit is not maintainable and that the plaintiff
approached the Court seeking equitable relief of injunction but
suppressed the material facts and did not exhaust the remedy
available under the Act of 1924, and as such the suit is liable to be
dismissed. It is also stated that no statutory notice in terms of
Section 273 of the Act of 1924 was issued by the plaintiff and thus
the suit is bad in law for want of notice. Either in the plaint or in
the affidavit filed in support of the interlocutory application for
dispensing with the notice, no grounds are elucidated, and thus,
the suit is to be dismissed for non-issuance of mandatory notice. It
is also stated that the fact finding regarding deviations and the
unauthorized construction falls within the domain of the Board
and the Board has the required experts, and as such the suit is to
be dismissed. As the right of appeal was also provided to the
plaintiff under the Act of 1924, the proceedings under Section 185
of the Act of 1924 were initiated only after providing the reasonable
opportunity and after passing of the resolution by the elected
representative of the people, the suit is not maintainable. It is also
stated that the suit is filed by the plaintiff but not the true owners
of the property and as such the suit is bad for non-joinder of
necessary parties and thus requested to dismiss the suit.
8. Basing on the above pleadings, oral and documentary
available on record and the cross-examination of D.W.1, extracted
in page Nos.6 and 7 of the judgment, the trial Court observed that
the plaintiff made construction of the building within the area
owned by it and there is no complaint from the neighbours or
anybody. The trial Court relied upon a decision reported in
3 ACES, HYDERABAD's case (supra) in which it was held that if
the deviations made during the construction are not in public interest
or cause public nuisance or are hazardous or dangerous to public
safety including the residents there in and are minor, minimal or
trivial, which do not effect public at large, the Corporation will not
resort to demolition. The trial Court further observed that the main
objection of the defendant is that though the plaintiff obtained two
sanctioned plans, it constructed one multistoried building and that
itself cannot be considered as violation. The trial Court also
observed that the construction of the building was in accordance
with the sanctioned plan and thus it need not prefer an appeal
against the notice issued by the Board as the plaintiff filed only
suit for injunction simplicitor, it is maintainable and accordingly
granted permanent injunction.
9. Aggrieved by the above judgment, the defendant preferred an
appeal vide A.S.No.120 of 2005 and the appellate Court confirmed
the judgment of the trial Court on the ground that constructions
are not illegal and as per the sanctioned plans and that the
constructions are not in the public property and no nuisance was
caused to the public and no complaints were given by the public.
The appellate Court also observed that regularization can be done
by collecting compound fee as per the decision reported in 3 ACES,
HYDERABAD's case (supra). Aggrieved by the said judgment, the
defendant preferred this appeal.
10. The substantial question of law before this Court would be:
(1) Whether the plaintiff can approach this Court without preferring appeal before the Appellate Authority as per Section 274 of the Act of 1924?
2) Whether there are deviations and violations in constructing the building and thus Secunderabad Cantonment Board can demolish the structures?
11. A Cantonment Board is a civic administration body in India
under control of the Ministry of Defence. The board comprises
elected members besides ex-officio and nominated members as per
the Cantonments Act, 2006. The Board is bound by the provisions
of the Act of 1924, which was amended subsequently. Mrs.Sharada
Srinivas and Mrs.Ranjani Rangarajan were the joint owners of the
suit schedule property, entered into Development Agreement with
the plaintiff company and also executed general power of attorney
in favour of the plaintiff company. They obtained ULC from the
Ministry of Defence on 25.08.1980 and also obtained sanctioned
plans separately vide Cantonment Board Resolution No.28(4) and
40 dated 04.12.1995. The plaintiff company filed a suit for
permanent injunction.
11. The case of the appellant/defendant is that the plaintiff
company obtained two separate sanctioned plans, but constructed
one residential complex by clubbing two sanctioned plans and it
amounts to deviation from the original sanctioned plan. It is its
further case that when the construction was in progress, it issued
a notice and raised an objection. The plaintiff constructed RCC
columns in the setback area and that the stilt floor was
constructed unauthorisedly without any sanction, and thus, the
same is to be treated as unauthorized construction and the owners
are guilty of committing an offence under Section 184 of the Act of
1924. Therefore, the appellant/defendant issued a preliminary
show cause notice on 06.11.1996 to demolish the unauthorized
constructions. When the plaintiff failed to oblige the same after
resolution dated 26.11.1996, the appellant/defendant issued
another show cause notice dated 09.12.1996 under Section 185 of
the Act of 1924. The crux of the contention of the
appellant/defendant is that against the above said show cause
notice, the plaintiff has to prefer an appeal before the Competent
Authority under Section 274 of the Act of 1924, but it failed to do
so.
12. It is apposite to extract Section 274 of the Act of 1924, which
reads as under:
'274. Appeals from executive orders.--(1) Any person aggrieved by any order described in the third column of Sch.V may appeal to the authority specified in that behalf in the fourth column of the said schedule.
(2) No such appeal shall be admitted if it is made after the expiry of the period specified in that behalf in the fifth column of the said schedule.
(3) The period specified as aforesaid shall be computed in accordance with the provision of the Limitation Act, 1963 (36 of 1963), with respect to the computation of periods of limitation thereunder.'
13. As per Section 276 of the Act of 1924, on the admission of an
appeal, all the proceedings to enforce the order and all prosecutions
of any contravention thereof shall be held in abeyance and as per
Section 278 of the Act of 1924, every order of the appellate
Authority shall be final. If at all the plaintiff approached the
appellate Authority provided under the Act of 1924, the
appellant/defendant should have suspended the show cause
notice issued under Section 185 of the Act of 1924 after giving due
opportunity to the plaintiff. But the plaintiff, despite receipt of the
said show cause notice, did not give any reply and did not avail the
remedy of appeal under Section 274 of the Act of 1924, instead it
approached the Civil Court for permanent injunction. The
appellant/defendant in its written statement itself raised the above
issue before the trial Court, but the trial Court misinterpreted the
facts and section of law and held that the suit filed by the plaintiff
is maintainable.
Admittedly, there are deviations in the construction of the
building. P.W.1 during his cross-examination clearly admitted that
he made construction by clubbing two separate sanctioned plans.
Defendant accorded sanction for ground, first and second floors,
but he constructed cellar, ground plus three floors. Stilt
permission was accorded for parking purpose, but he constructed
cellar. In fact, stilt floor above the cellar floor was significantly
converted to regular floor. He failed to maintain FSI as per sanction
accorded by the Board. He also admitted that there is no sanction
for construction of cellar and third floors. He added that he
addressed a letter dated 04.03.1997 to grant permission for cellar,
but he did not receive any reply from the Board. He has not issued
commencement notice, not obtained plinth checking certificate and
not obtained completion certificate.
14. D.W.1 was the Supervisor of the appellant/defendant Board,
who deposed that a residential complex was constructed by
clubbing two different sanctioned plans. The plaintiff violated the
sanctioned plan by not maintaining the FSI 0.5 as per the sanction
accorded by the Board and it failed to maintain setbacks and
constructed RCC columns and common areas are encroached. The
plaintiff made cellar unauthorisedly and violated the sanctioned
plan by constructing the cellar and third floor unauthorisedly. The
plaintiff failed to submit any notice prior to the commencement
and failed to obtain any plinth checking certificates from the
Board. The plaintiff also constructed additional floors without
there being any sanction. The plaintiff did not stop construction
activities even after issuance of the preliminary show cause notice
and show cause notice and proceeded with the construction
unauthorisedly. In the notice issued under Section 185(1) of the
Act of 1924, the plaintiff was directed to remove the unauthorized
construction within thirty days and it has not preferred any appeal
provided under Section 274 of the Act of 1924 and willfully failed
to avail the remedy available under the statute, and thus it clearly
violated the building byelaws of the appellant-defendant and the
unauthorized construction cannot be compounded and it cannot
be regularized and that the plaintiff not even given completion
notice of the construction to the appellant-defendant. D.W.1 gave
report under Ex.B1. Basing on the said report, show cause notice
was issued under Ex.B2 and notice under Section 185(1) was
issued under Ex.B3 along with sanctioned building plan under
Ex.B4. D.W.1 worked in the said place till the middle of 1997 and
later one Mr.Iqbal was posted as incharge of the suit schedule
area.
15. Learned counsel for the appellant-defendant relied upon
case law reported in FRIENDS COLONY DEVELOOPMENT
COMMITTEE V/s. STATE OF ORISSA2 holding to the effect that
stringent actions by ruthlessly demolishing illegal constructions and
non-compoundable deviations is necessary. Unwary purchasers of
such buildings to be compensated. In DIPAK KUMAR
MUKHERJEE V/s. KOLKATA MUNICIPAL CORPORATION3, the
Hon'ble Apex Court held that illegal and unauthorized constructions
of buildings and other structures not only violate the municipal laws
and the concept of planned development of the particular area but
also affect various fundamental and constitutional rights of other
persons. The failure of the State apparatus to take prompt action to
demolish such illegal constructions has convinced the citizens that
AIR 2005 SUPREME COURT 1
AIR 2013 SUPREME COURT 927
planning laws are enforced only against poor and all compromises
are made by the State machinery when it is required to deal with
those who have money power or unholy nexus with the power
corridors. The builder conveniently walks away having pocketed the
money leaving behind the unfortunate occupants to face the music in
the event of unauthorized constructions being detected or exposed
and threatened with demolition. The unwary purchasers who shall
be the sufferers must be adequately compensated by the builder.
16. The plaintiff cannot justify his action on the ground that the
owners are joint owners and previously they have single
construction and as such though there are two separate
sanctioned plans, it can construct one multistoried residential
complex by clubbing both the plans. Merely because it entered into
a Development Agreement with the joint owners, it cannot alter the
sanctioned plans according to its convenience. In the process of
altering the sanctioned plans, it made several violations, it is
amply established by oral evidence of P.W.1 and D.W.1, and thus,
the appellant-defendant issued show cause notice directing it to
remove the unauthorized constructions. Instead of obliging the
same, the plaintiff proceeded with construction and also obtained
interim order from the civil Court without preferring an appeal
before the Appellate Authority under the Act of 1924. The plaintiff
stated that under Ex.A6 it addressed a letter to the appellant-
defendant to regularize the plan. In the said notice, the plaintiff
stated that on commencement of the construction its Engineer
advised it to join both the buildings together to provide more
spacious living areas and to save the costs considerably, and thus
it extended the slab, beams and columns slightly in to the setback
area. It further states that excavation for foundation it was
observed by the Engineer that the soil was extremely loose and not
conducive for foundation and since the neighbouring plot is lower
by about eight feet, the Engineer advised it to completely excavate
the property to avoid any structural problems and danger to the
building, and as such, the plaintiff requested for regularization of
the plans.
17. To the notice issued under Section 185 of the Act of 1924 on
09.12.1996, there is no date mentioned on the reply notice given
by the plaintiff, but the Secunderabad Cantonment Board received
it on 04.05.1997. The plaintiff filed the subject suit seeking
permanent injunction was on 30.04.1997. The argument of the
plaintiff is that in spite of issuance of reply notice under Ex.A6, the
appellant-defendant has not regularized the plan cannot be
countenanced as the plaintiff not only violated the sanctioned plan
but also made several deviations by discarding the show cause
notice. The appellant-defendant would contend that the plaintiff is
not the owner of the property and it is only a General Power of
Attorney Holder, but admittedly the joint owners of the suit
schedule property executed the General Power of Attorney in
favour of the plaintiff and authorized it to represent in any Court
cases and as such it cannot be said that the plaintiff is not
authorized to represent the true owners.
Section 273 notice under the Act of 1924 is on par with
Section 80 notice under CPC. It is argued by the learned counsel
for the appellant that without any proper reason, the said notice
was dispensed with, of course Board contested the injunction suit
and thus non-issuance of notice prior to the filing of plaintiff's suit
is not prejudicial to the rights of the Board. As per the judgment of
the Hon'ble Apex Court in SMT.HAANNURAMMABAI KALAL
(DECEASED) BY L.R. V/s. CANTONMENT BOARD, BELGAUM4, it
was held that the requirement of notice before instituting the suit is
not required where the relief sought is an injunction, and thus it
cannot be held as fatal to the suit.
18. During the course of arguments, learned counsel for the
appellant-defendant would submit that now the illegality
committed by the plaintiff cannot be compounded and the cellar
portion is to be kept only for parking purpose and the
unauthorized construction in the third floor is to be pulled down.
19. No doubt, the prospective purchasers who purchased the
property from the developer and residing in it from 1997 onwards
will sustain loss for no fault of them. Therefore, the said flat
owners are entitled for refund of the amount whatever they paid
towards purchase of flats along with interest from the builder.
20. On the above analysis, this second appeal is allowed. The
judgment and decree dated 15.07.2010 in A.S.No.126 of 2005 on
the file of the Court of the XX Additional Chief Judge, City Civil
Court, Secunderabad, and the judgment and decree dated
17.02.2005 in O.S.No.162 of 1997 on the file of the learned III
Senior Civil Judge, City Civil Court, Secunderabad, are hereby set
aside. There shall be no order as to costs.
2007 SCC OnLine Kar 416
21. Pending miscellaneous petitions, if any, shall also stand
closed in the light of this final judgment.
____________________ P.SREE SUDHA, J.
28th JANUARY, 2022.
PGS
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!