Citation : 2022 Latest Caselaw 832 Tel
Judgement Date : 22 February, 2022
1
HIGH COURT FOR THE STATE OF TELANGANA
AT HYDERABAD
****
WP No.29440 of 2021 Between:
UNION OF INDIA, REP. BY MINISTRY OF RAILWAYS, RAILWAY BOARD, NEW DELHI ...Petitioner
&
KRISHNAPATNAM RAILWAY COMPANY LIMITED ...Respondent
DATE OF JUDGMENT PRONOUNCED: 22-02-2022
SUBMITTED FOR APPROVAL:
1. Whether Reporters of local newspapers may be allowed to see the Judgment?
Yes/No
2. Whether the copies of judgment may be marked to Law Reporters/Journals Yes/No
3. Whether Your Lordships wish to see the fair copy of the Judgment?
Yes/No
______________________________ A. RAJASHEKER REDDY, J
*THE HON'BLE THE CHIEF JUSTICE SATISH CHANDRA SHARMA & *THE HON'BLE SRI JUSTICE A. RAJASHEKER REDDY + WP No.29440 of 2021
% 22-02-2021
# UNION OF INDIA, REP. BY MINISTRY OF RAILWAYS ...Petitioner
&
$ KRISHNAPATNAM RAILWAY COMPANY LIMITED ...Respondent
< GIST:
> HEAD NOTE:
! Counsel for Petitioner: Ms.Madhavi Divan, Addl. Solicitor General for Union of India, Ministry of Railways ^Counsel for Respondent : Sri Avinash Desai
? Cases referred
1. (2011) 5 SCC 532
2. (2022) 1 SCC 75
3. (2005) 8 SCC 618
4. (2019) SCC Online SC 1602
5. (1984) 4 SCC 679
6. 2021 SCC Online SC 766
7. AIR 1982 SC 149
HON'BLE THE CHIEF JUSTICE SATISH CHANDRA SHARMA & HION'BLE SRI JUSTICE A.RAJASHEKER REDDY
WP No.29440 of 2021
ORDER :: (per Hon'ble Sri Justice A. Rajasheker Reddy, J)
Writ petition has been filed by the Ministry of Railways to set
aside the orders dated 18-06-2020 and 29-04-2021 passed by the
learned Arbitral Tribunal on the grounds of patent lack of inherent
jurisdiction; violation of public policy, as also to declare the dispute
raised by the respondent-Krishnapatnam Railway Company Limited as
inarbitrable and not capable of settlement by Arbitration and further
order to remove the privileged documents from the record, which
includes sensitive Governmental file notings concerning the subject
matter.
2. Brief facts of the case, in nutshell, as emerged from the
pleadings are:- In December 2002, the Ministry of Railways launched
National Rail Vikas Yojna to improve rail transport facility capacity
and port connectivity by upgrading railway infrastructure. In the
backdrop of this initiative, the Railways sanctioned Project Railway on
22-03-2006 for construction and implementation of broad-gauge rail
link connectivity between Obulavaripalle at Km 0.000 and
Krishnapatnam at Km 111.129.
3. The petitioner and the respondent entered into Concession
Agreement in year 2007 in respect thereof wherein the respondent was
required to complete the project within a period of 5 years among
other things. The Concession Agreement inter-alia included
performance and execution of all activities related to the development,
financing, design, construction, operation and maintenance of the
Project Railway by the respondent. During the course of execution of
the Project Railway work, in year 2012 the respondent made a
representation seeking for apportionment of various charges including
"Terminal Costs" and "Apportioned Earnings for the length of the
PKPK Siding" and it is entitled to get an amount of Rs.500 crores from
November, 2008 to March, 2017, which the Ministry of Railways
refused initially by issuing Circular dated 02-08-2016 wherein it
said that there was no such provision in the Concession Agreement to
give a cause to the respondent to make such extra contractual
demands. However, it has come on record that after receiving similar
representations from SPVs of other Zonal Railways, the matter was
considered afresh and the petitioner conceded to such claims and
accordingly issued two Circulars dated 10-08-2017 and 15-11-2017
wherein the claims, as the one made by the respondent and all other
SPVs was allowed for payment from the date of issuance of the two
Circulars prospectively, not retrospectively thereby the claim of the
respondent for payment of Terminal Costs and Apportioned Earnings
for the length of the PKPK Siding was considered prospectively. This
gave rise to invocation of the Arbitration Clause enshrined in the
Concession Agreement and Arbitral Tribunal was formed.
4. Pursuant to the constitution of the Arbitral Tribunal, the
respondent filed its Statement of Claim as also amended claim. During
the pendency of the Arbitral proceedings, the Ministry of Railways
(petitioner) has filed an application under Section 16 of the Arbitration
and Conciliation Act, 1996, (in short, "the Act") wherein the
jurisdiction of the Arbitral Tribunal to entertain and commence the
Arbitration proceedings was challenged, was considered and rejected
by order dated 18-06-2020. The respondent also filed two applications
for discovery and production of documents wherein a reply was filed
by the petitioner and by order dated 29-04-2021, they were allowed
and directed the petitioner for production of documents, which reads
as under:-
"Conclusion:19. The application is allowed in respect of Requests (1), (2) and (3) and production as per paras 8, 12, and 14 above shall be as under:
(i) The Respondent shall produce true legible photocopy of the file notings relating to the Claimant, as sought in Request (1), within 15 days and furnish a copy to the Claimant.
(ii) The Respondent shall, within three weeks, permit inspection of the files sought as per Requests (2) and (3) by the Claimant's representative and Counsel on a date mutually agreed between the counsel, at the office of the respondent.
(iii) On inspection, the Claimant shall furnish to the Respondent, a list of the required documents in the said files referred in Requests (2) and (3).
(iv) The Respondent shall produce the said documents (certified photocopies) required by the Claimant, and furnish copies to the Claimant, within 10 days of the claimant furnishing the list of the required documents."
Both the orders dated 18-06-2020 and 29-04-2021 are
impugned in this writ petition.
5. Ms.Madhavi Divan, learned Additional Solicitor General
appearing for the Ministry of Railways (petitioner herein) argued that
the learned Arbitral Tribunal has overstepped its jurisdiction and has
permitted adjudication of issues applicable to all SPVs concerned and
failed to appreciate that the dispute initiated by the respondent
involves rights in-rem cannot be subject to private dispute resolution
by way of Arbitration and, as such, the Arbitral Tribunal lacks
inherent jurisdiction. It is stated that issues pertaining to sharing of
the revenue for the Siding/Lines constructed outside the Project
Railway and Concession Agreement does not provide for such claims,
any award passed for payment of Terminal Costs and Apportionment
Revenues retrospectively, would override the Policy Circulars of the
Ministry of Railways and lead to mushrooming of claims by other
SPVs. It is also argued that the respondent is not seeking for
resolution of his claims in personam but has disguised its challenge
against the decision envisaged in the Policy Circulars as a contractual
dispute under the Concession Agreement. It is also argued that the
documents required to be produced are privileged documents and
there would be serious breach of confidentiality they being privileged
documents. It is stated that the respondent overlooked the mandatory
pre-arbitral step of good faith negotiations and conciliation as provided
under the Concession Agreement which was defined with sufficient
clarity and specificity.
6. Sri Avinash Desai, learned counsel for the respondent, on the
other hand, submits that the petitioner having submitted to the
jurisdiction of the Arbitral Tribunal by nominating an Arbitrator and
also having made a counter claim, cannot challenge the jurisdiction
thereof which itself goes to show that the Arbitral Tribunal does not
suffer from patent lack of jurisdiction. Learned counsel contended that
no appeal has been provided against an order dismissing an
application filed under Section 16 of the Act or an interlocutory order
directing production of documents, as such the petitioner ought to
have waited till the passing of the final award and challenge the same
if aggrieved, as no rights of the parties are decided on merits at this
stage.
7. Having heard learned counsel on both side, the core issue that
arise for consideration in the instant petition is:-
Whether the impugned order rejecting the objection raised by the
petitioner that the adjudicatory effect of the Arbitral Tribunal on Policy
issues would be a judgment in-rem, and such disputes is to be decided
by Courts/Tribunals and not by the Arbitral Tribunal as it is a forum
agreed by the parties, and the order refusing to expunge certain file
notings from the record, in the facts and circumstances of the case, is
sustainable in law ?
8. The petitioner sought to challenge the order passed in an
application under Section 16 of the Act on the ground that the Arbitral
Tribunal failed to appreciate that the respondent is challenging the
Policy Circulars issued by the petitioner in the guise of a contractual
dispute and the dispute involves rights-in-rem as such cannot be
adjudicated through Arbitration. The impugned order is also traversed
on the ground that as per the terms of the agreement, the claim
sought in relation to the PKPK Siding fall outside the scope of
Concession Agreement and thus not amenable to the Arbitration.
Decision in BOOZ ALLEN & HAMILTON INC vs. SBI HOME FINANCE
LTD.1 is relied for the proposition that there can be no arbitration for
enforcement of rights in rem.
(2011) 5 SCC 532
9. It is settled position of law that in order to maintain a writ
under Article 226 of the Constitution of India against the interlocutory
order passed by the Arbitral Tribunal, such an order meet the
standard of exceptional rarity. Interference by the High Court with the
arbitral proceedings and the orders passed in interlocutory
applications cannot be resorted to and interject the arbitral
proceedings, moreso at the stage where no rights of the parties are
decided; unless they make the standard of exceptional rarity. Section
5 of the Act specifically provides that notwithstanding anything
contained in any other law for the time being in force, no judicial
authority shall intervene except where specifically provided. Section 16
of the Act is self explanatory which speaks of the competence of the
Arbitral Tribunal to rule on its jurisdiction.
10. Section 37 of the Act specifically provides for the orders which
are appealable, and no appeal has been provided against an order
dismissing an application under Section 16 of the Act or even
interlocutory order directing production. The purpose of not making
such order appealable is to avoid judicial interference with arbitral
proceedings and to ensure that the parties raise all challenges to such
orders under section 34 of the Act only after the arbitral award is
passed. (see BHAVEN CONSTRUCTION THRU AUTHORISED
SIGNATORY PREMJIBHAI K. SHAH vs. EXECUTIVE ENGINEER
SARDAR SAROVAR NARMADA NIGAM LTD.)2
11. In BHAVEN CONSTRUCTION'S case (2 supra), Hon'ble Supreme
Court while considering the limitations of Articles 226 and 227 in the
context of a challenge to an order under Section 16 of the Act, as no
appeal lies against such order, at paragraph 18 held as under:-
"18. It is therefore, prudent for a Judge to not exercise discretion to allow judicial interference beyond the procedure established under the enactment. This power needs to be exercised in exceptional rarity, wherein one party is left remediless under the statute or a clear 'bad faith' shown by one of the parties. This high standard set by this Court is in terms of the legislative intention to make the arbitration fair and efficient."
12. The following view taken by the Hon'ble Supreme Court in SBP
COMPANY vs. PATEL ENGINEERING3, in our view, clinches the issue which
reads as under:-
(2022) 1 SCC 75
(2005) 8 SCC 618
"45. It is seen that some High Courts have proceeded on the basis that any order passed by an arbitral tribunal during arbitration, would be capable of being challenged under Article 226 or 227 of the Constitution of India. We see no warrant for such an approach. Section 37 makes certain orders of the arbitral tribunal appealable. Under Section 34, the aggrieved party has an avenue for ventilating his grievances against the award including any in between orders that might have been passed by the arbitral tribunal acting under Section 16 of the Act. The party aggrieved by any order of the arbitral tribunal, unless has a right of appeal under Section 37 of the Act, has to wait until the award is passed by the Tribunal. This appears to be the scheme of the Act. The arbitral tribunal is after all, the creature of a contract between the parties, the arbitration agreement, even though if the occasion arises, the Chief Justice may constitute it based on the contract between the parties. But that would not alter the status of the arbitral tribunal. It will still be a forum chosen by the parties by agreement. We, therefore, disapprove of the stand adopted by some of the High Courts that any order passed by the arbitral tribunal is capable of being corrected by the High Court under Article 226 or 227 of the Constitution of India. Such an intervention by the High Courts is not permissible.
13. In DEEP INDUSTRIES LTD. vs. OIL AND NATURAL GAS
CORPORATION LIMITED4 in similar fact situation the Supreme Court
observed thus: -
"22....The drill of Section 16 of the Act is that where a Section 16 application is dismissed, no appeal is provided and the challenge to the Section 16 application being dismissed must await the passing of a final award at which stage it may
(2019) SCC Online SC 1602
be raised under Section 34.... Even otherwise, entering into the general thicket of disputes between the parties does not behove a court exercising jurisdiction under Article 227, where only jurisdictional errors can be corrected..."
14. In RENUSAGAR POWER COMPANY LIMITED vs. GENERAL
ELECTRIC COMPNAY,5 the Supreme Court while holding that the test
is whether recourse to the contract would be necessary for the
purpose of determining whether the Tribunal has jurisdiction or not
held thus:-
"25.... Expressions such as "arising out of" or "in respect of" or "in connection with" or "in relation to" or "in consequence of" or "concerning" or "relating to" the contract are of the widest amplitude and content and include even questions as to the existence, validity and effect (scope) of the arbitration agreement."
15. A perusal of the order passed by the learned Arbitral Tribunal
goes to show that it had noted that the objection raised by the
petitioner that the claims being made by the respondent are outside
the scope of the Concession Agreement, go to the merits of the dispute
and not to the jurisdiction of the Arbitral Tribunal. By way of
application under Section 16 of the Act, the petitioner wanted the
(1984) 4 SCC 679
tribunal to examine at the threshold, the correspondence between the
parties and decide the issue as the claim may lead to a judgment in
rem. All claims of the respondent are based on and arising out of the
Concession Agreement and if the claim now made by the respondent is
outside such an agreement, the petitioner will have the liberty to raise
its objection to those claims in its defence as such seeking
enforcement of a right under a contract is enforcement of right in
personam and not right in rem and the decision in BOOZ ALLEN's
case is not applicable to the facts of the case. Curiously it is to be
seen that the petitioner is not altogether refusing the claims made by
the respondent, which according to it fall outside the scope of the
arbitration agreement between them, but only contend that the claims
cannot be granted under the terms of the Concession Agreement. It is
well within the Arbitral Tribunal's jurisdiction to determine whether
the claims of Terminal Costs and Apportioned Earnings for the PKPK
Siding are payable under the terms of the Concession Agreement or
outside thereof. As no appeal is provided against an order refusing the
relief in an interlocutory application, by way of this writ petition
under Article 226 of the Constitution of India, the petitioner cannot
seek this Court to traverse into the merits of the claims raised by the
respondent in the arbitral proceedings in this writ proceedings,
moreso when the Arbitral Tribunal seized of the matter and the
petitioner has also made counter claim. Inasmuch as the arbitration
has commenced, the petitioner ought to have waited till the award is
pronounced unless, of course, a right of appeal is available to it under
Section 37 of the Act even, at an earlier stage.
16. A foray to the writ Court from Section 16 application being
dismissed by the Arbitrator can only be if the order passed is so
perverse, that the only possible conclusion is that there is a patent
lack in inherent jurisdiction and it must be the perversity of the order
that must stare one in the face. (see PUNJAB STATE POWER
CORPORATION LTD. vs. EMTA COAL LTD6.) As a matter principle and
rule, all civil and commercial disputes arising out of a contract are
capable of being decided through arbitration unless they are
specifically excluded. A dispute would fall within the category of 'rights
in rem' only if the action brought before the Arbitral Tribunal is
(2021) SCC Online SC 766
against the world at large and not against a specific individual. The
Circulars dated 10-08-2017 and 15-11-2017 even if have universal
application to all SPVs and are in the nature of Policy decisions,
whether the respondent's claim arise out the terms of the Concession
Agreement and its entitlement or otherwise to the Terminal Costs and
Apportioned Earnings for the PKPK Siding, in accordance with the
IRFA Rules (Rules of Inter-Railway Apportionment of Earnings) as
provided under Clause 4 (2) (f) of the Concession Agreement, will have
to be necessarily decided in accordance with the arbitration clause in
the Concession Agreement.
17. The writ petition was heard elaborately and under the guise of
challenge to the impugned order on the ground of perversity the
petitioner cannot seek for a roving enquiry into the matter. No ground
is either shown or pointed out to show that the learned Arbitral
Tribunal lacks jurisdiction in view of the nature of claims being an
individual claims. The objections taken by the petitioner in the
application filed under Section 16 of the Act viz., i) arbitration
proceedings commenced prematurely without complying the pre-
arbitral step of resolving the issue, ii) subject matter is not arbitrable
as it relates to rights in rem; iii) claims made by the claimant are
beyond the scope of the arbitration agreement and iv) that the
concession agreement is insufficiently stamped are answered by the
Arbitral Tribunal point wise and we find no perversity in the
conclusion arrived therein. Further, this Court is not sitting in appeal
over the order of the Arbitral Tribunal and in exercise of power of
judicial review, only examines the decision making process and not
the decision itself. Considering the need and to upkeep the growing
financial promises in contractual matters and in view of the objects
sought to be achieved under the scheme of the Act, the Legislature
itself did not provide for appeal remedy against the dismissal of the
interlocutory applications filed under Section 16 of the Act and any
venture to appraise the matter on merits will defeat the purpose,
scheme and the object for which the Act is brought in.
18. The proposition put forth by the learned Addl. Solicitor General
that the respondent's claim for entitlement to Terminal Costs and
Apportioned Earnings also concerns the other SPVs and in the event
of allowing its claim may give rise to similarly placed SPVs raise such
claims, therefore it is a dispute in-rem cannot be appreciated for the
simple reason as going by the petitioner's own interpretation, if the
nature of present claim is considered as in-rem dispute, that would
mean that any decision taken by the Ministry of Railways even if it is
with respect to contractual rights of parties, cannot be subjected to
adjudication by arbitration though they affect contractual matters.
19. Coming to the objection for production of note filings, it has
come on record that the petitioner, while filing its statement of defense
before the Arbitral Tribunal, had itself heavily relied on the notings of
the File No.2012/Infra/18/5 of Infrastructure Directorate. Seemingly
the need for the respondent to file such applications for production of
documents arose as the petitioner sought to selectively rely on file
notings, the respondent sought production of the entire file notings in
order to facilitate a complete and fair adjudication. Even documents
produced by the petitioner would only be with respect to the claims of
the respondent. In this connection, the learned Tribunal recording as
under:-
"Admittedly, Respondent has not furnished all the notings relating
to the Claimant or the notings which led to the entering of the
Concession Agreement with the Claimant. As what is sought are only
the file notings relating to only the Claimant, the question of any of
those notings containing commercially sensitive information does not
arise."
20. The principle of protecting disclosure of documents relating to
the "affairs of the State" under Section 123 of the Indian Evidence Act,
1872, do not apply to the present case as the petitioner prima facie
failed to show how the documents in question related to the affairs of
the State, and its production for perusal would be against to public
interest and the petitioner cannot claim class privilege merely because
the documents are internal file notings. (see S.P Gupta vs. Union of
India7)
21. The contention that the Arbitral Tribunal overlooked the
mandatory pre-arbitral step of good faith negotiations and conciliation
as provided under the Concession Agreement cannot also be
appreciated for the reason as rightly observed in the impugned order,
AIR 1982 SC 149
nothing prevented the parties parallelly to make an endeavor to sort
out their disputes by way of negotiations and settle any or all the
disputes between them, as it would save the costs and expedite the
dispute resolution.
22. The scope of this Court in exercise of our jurisdiction in
proceedings for issuance of Writ of Certiorari as observed by the
Supreme Court in SYED YAKOOB vs. K.S.RADHA KRISHNAN, (1964)
5 SCR 64) observed that a writ of certiorari can be issued for
correcting errors of jurisdiction committed by inferior courts or
Tribunals: these are cases where orders are passed by inferior courts
or Tribunals without jurisdiction, or is in excess of it or as a result of
failure to exercise jurisdiction. A writ can similarly be issued where in
exercise of jurisdiction conferred on it, the court or Tribunal acts
illegally or improperly, as for instance, it decides a question without
giving an opportunity to be heard to the party affected by the order or
where the procedure adopted in dealing with the dispute is opposed to
principles of Natural Justice. None of the circumstances stated above
are appearing in the impugned order nor there are any compelling
reasons calling for our inference with the impugned order passed by
the learned Arbitral Tribunal.
23. On the above analysis of the matter, inasmuch as the
challenges raised by the petitioner do not go to the jurisdiction of the
Arbitral Tribunal, but rather, to the merits of the claim made by the
respondent, the writ petition is devoid of merits deserves to be
dismissed and it is accordingly dismissed. Miscellaneous applications,
if any pending, stand disposed of. There shall no order as to costs.
________________________________ SATISH CHANDRA SHARMA,CJ
_____________________________ A.RAJASHEKER REDDY,J
DATED: 22 --02--2022 NRG
THE HON'BLE THE CHIEF JUSTICE SATISH CHANDRA SHARMA & HION'BLE SRI JUSTICE A.RAJASHEKER REDDY
WP No.29440 OF 2021
DATED : 22-02-2022
NRG
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!