Citation : 2022 Latest Caselaw 446 Tel
Judgement Date : 4 February, 2022
HON'BLE SRI JUSTICE P.NAVEEN RAO
AND
HON'BLE SMT. JUSTICE P.SREE SUDHA
CITY CIVIL COURT APPEAL NOs.147 & 200 OF 2002
Date: 04.02.2022
CCCA No.147 of 2002:
Between:
Dokwal Refinery, Light Industrial Area,
Rampur Road, Adilabad, rep.by its Partner
Mahender Kumar Dokwar, s/o. L.Dinesh
Kumar, Aged about 44 years, r/o.H.No.6-5-85,
Cinema Road, Adilabad.
.... Appellant
And
A.P.State Co-operative Marketing Federation
Limited, having its Office at 7th Floor,
Parishrama Bhavan, No.5-9-58/B,
Basheerbagh, Hyderabad, rep.by its
General Manager and two others.
.... Respondents
This Court made the following:
PNR,J & PSS,J CCCA Nos.147 & 200 of 2002
HON'BLE SRI JUSTICE P.NAVEEN RAO AND HON'BLE SMT. JUSTICE P.SREE SUDHA
CITY CIVIL COURT APPEAL NOs.147 & 200 OF 2002
COMMON JUDGMENT: (per Justice P.Sree Sudha)
1. Learned VII Additional Chief Judge, City Civil Court,
Hyderabad, passed common judgment dated 12.04.2002 in
O.S.No.294 of 2000 and O.S.No.140 of 1998. Aggrieved by the said
common judgment these appeals are preferred. CCCA No.147 of
2002 is preferred by M/s.Dokwal Refinery and CCCA No.200 of
2002 is preferred by MARKFED. Parties are referred to as arrayed
in O.S.No.294 of 2000.
2. Heard learned Advocate General for 'MARKFED', learned
Assistant Solicitor General for Central Government and learned
counsel Sri S. Balchand for plaintiff.
3. M/s.Dokwal Refinery filed O.S.No.294 of 2000 for recovery of
sum of 24.24,395/- with interest at the rate of 24% per annum
against A.P. State Cooperative Marketing Federation Limited
(Defendant No.1) (for brevity, 'MARKFED'), Union of India
(Defendant No.2) and the Chief Director of Purchase, Army
Purchase Organisation, New Delhi (Defendant No.3). Though the
plaintiff filed the suit against all the defendants, it claimed the
amount against the first defendant only and the second and third
defendants were set ex parte.
4. The averments in the plaint in O.S.No.294 of 2000 disclose
the facts, to the extent relevant, as under:
PNR,J & PSS,J CCCA Nos.147 & 200 of 2002
The plaintiff is a partnership firm registered under the
Partnership Act with the Registrar of Firms with Registration
No.01284 of 1990. The first defendant entered into an agreement
with the plaintiff on 07.10.1994 for purchase of 500 metric tonnes
of cotton seed refined oil to be supplied to the third defendant from
November, 1994 to January, 1995 at the rate of Rs.36,430/- per
metric tonne. The plaintiff complied the terms of contract. The
total value of 500 metric tonnes of cotton seed refined oil was
1,82,18,351.56 Ps. Out of this, the first defendant paid an
amount of 1,65,94,009.85 Ps. After excluding 54,419/-
towards short supply, the balance amount of 16,76,082.83 Ps.,
is due from the first defendant. Though repeatedly demand was
made to clear the dues, dues were not paid. The first defendant
took shelter under Clause 7 of the agreement, which, in effect
requires first defendant to pay the amounts to plaintiff only when it
receives the amount from the defence authorities and that the
army authorities have not released the balance payment to the first
defendant.
5. There was yet another contract between the first defendant
and the army authorities with regard to supply of channa daal. The
plaintiff is not aware of such transaction between them. There is
no dispute regarding supply of cotton seed refined oil as per the
contract. As such, the first defendant is not entitled to withhold
the amount payable by it. All the previous payments were released
by army authorities in favour of the first defendant and the first
defendant in turn, after deducting one percent commission, paid
the amounts to the plaintiff and withholding amount of PNR,J & PSS,J CCCA Nos.147 & 200 of 2002
16,76,082.83 Ps. by the first defendant is unreasonable and
unjust.
6. Earlier, the plaintiff filed W.P.No.2144 of 1996 against the
first defendant, which was allowed on 26.03.1996 directing the
Government of India to release the payment in favour of the first
defendant and the first defendant in turn directed to pay the same
to the plaintiff. Aggrieved by the said direction, the Government of
India, Ministry of Defence, carried the matter W.A.No.624 of 1996
before the Division Bench. The Division Bench allowed the appeal
and dismissed the writ petition by decision dated 19.06.1996 on
the ground that it is a civil dispute and there is no performance of
public duty. Dissatisfied with the said observation of the Division
Bench, the plaintiff preferred SLP No.16564 of 1996, but it was
dismissed on 02.09.1996.
7. The plaintiff contended that its rights cannot be effected
because of the breach of terms and conditions committed by the
first defendant in another contract with army authorities. There is
no dispute regarding the supply of cotton seed refined oil by the
plaintiff to the first defendant and in turn the first defendant to
second and third defendants. There is no privity of contract
between the plaintiff and the second and third defendants directly
and thus the plaintiff is not claiming any decree against the second
and third defendants. Therefore, the plaintiff issued notice under
Section 80 CPC on 19.06.1997 to the first defendant and the
second defendant and that the second and third defendants are
pro forma parties, and as such the plaintiff is entitled to
16,76,082.83 Ps along with interest at the rate of 24% per PNR,J & PSS,J CCCA Nos.147 & 200 of 2002
annum from 21.09.1995 to 31.07.1997 to an extent of
7,48,312.17 Ps and thus for a total amount of 24,24,395/-.
The plaintiff also states that the transaction between them is a
commercial transaction and that there is trade usage and custom
for charging interest at the rate of 24% per annum. As the first
defendant illegally withheld the amount due to the plaintiff, the
plaintiff also entitled for interest at the rate of 24% per annum.
8. As per Clause 12 of the agreement dated 07.10.1994, the
plaintiff addressed a letter dated 07.03.1997 to the first defendant
to appoint an Arbitrator, for which the first defendant sent reply
dated 19.04.1997 stating that there is no dispute between the
parties and there is no necessity for appointing an Arbitrator. As
the first defendant is not ready and willing to refer the matter to
the Arbitrator, the plaintiff filed the suit for recovery of the amount
along with interest.
9. The first defendant filed written statement contending that
they are dealing with procurement and supply of various food
grains and it had filed tender with the third defendant for supply of
cotton seed refined oil from November, 1994 to January, 1995 and
had allotted 500 metric tonnes of cotton seed refined oil to be
supplied at the rate of 36,430/- per metric tonne. As per the
terms of the tender schedule, if oil plant is not owned by the
tenderer, the plant may be taken on lease and as such the plaintiff
approached the first defendant and he agreed to give on lease their
Unit and accordingly, both the parties entered into a separate lease
agreement. The plaintiff in a letter dated 06.10.1994 had agreed to
supply cotton seed refined oil to the defence authorities on behalf of PNR,J & PSS,J CCCA Nos.147 & 200 of 2002
the first defendant and also furnished bank guarantee to the third
defendant for an amount of 18,39,800/- towards security
deposit. The first defendant further contended that as per Clause 7
of the agreement dated 07.10.1994, the amount if any due and
payable to the plaintiff for supply of cotton seed refined oil can be
made only when the payments are made by the second and third
defendants to the first defendant. The second and third defendants
had already preferred a claim in ARC No.4F/96 pertaining to the
channa dall contract before the Arbitrator and it was dismissed
and thereby the second and third defendants still continue to
withhold the due amounts payable to the first defendant, and as
such the first defendant filed O.S.No.140 of 1998 seeking recovery
of the said amount and that the alleged claim of interest by the
plaintiff is untenable and it is not entitled for any interest since it
was not specified in the agreement dated 07.10.1994.
10. O.S.No.140 of 1998 is filed by A.P. State Cooperative
Marketing Federation Limited against the Secretary to
Government, Government of India, Chief Director of Purchase and
Dokwal Refinery for recovery of 38,49,477.16 Ps. The first
defendant averments in the plaint are almost identical to the
averments in the plaint in O.S.No.294 of 2000 with regard to
supply of cotton seed refined oil and contended that even after
dismissal of ARC No.4F/96 pertaining to the contract of channa
dall, the second and third defendants withheld the amount due
and payable to it and as such it is entitled for the said amount
along with interest from 04.11.1995 to 28.02.1998. The first
defendant issued statutory Notice No.159/12/96 dated PNR,J & PSS,J CCCA Nos.147 & 200 of 2002
24.12.1996. It also made the plaintiff as third defendant to the
suit to bring out the true facts relating to the suit transaction.
11. The second and third defendants filed written statement
denying all the averments of the plaint. They further stated that
the amount of 2,47,06,250/- is due from first defendant in
connection with risk purchase loss to procure 3375 metric tonnes
of channa daal for defence services from the MARKFED. The
Arbitrator passed award in favour of the Union of India on
26.03.1997. They have not given any reply to the statutory notice
as the matter is pending before the Arbitrator. A separate suit was
filed by third defendant (Plaintiff) against MARKFED for recovery of
24,24,395/- in O.S.No.1423 of 1997 on the file of the learned
Additional Judge, City Civil Court, Hyderabad, but the outcome of
the suit is not known to them. As per para 22 of the general terms
and conditions of contract, there is an arbitration clause for
deciding any dispute and the venue of the arbitration proceedings
would be in the premises of the Government of India, Ministry of
Defence, New Delhi. Hence, the suit is not maintainable on the
ground of jurisdiction and the matter be referred to the Arbitrator.
12. The plaintiff as third defendant filed separate written
statement contending that the suit is bad for mis-joinder of the
parties as it is neither necessary nor proper party to the suit. The
plaintiff further stated that it is not aware of the internal
arrangement between the first defendant, and the second and third
defendants. It completed its part of supplies and entitled for
balance amount and it is nothing to do with the transactions
between the first defendant and the second and third defendants.
PNR,J & PSS,J CCCA Nos.147 & 200 of 2002
There is no dispute regarding the quantum of amount payable to
it.
13. O.S.No.294 of 2000 was transferred to try along with
O.S.No.140 of 1998, and thus, both the suits were clubbed and
tried together and a common judgment was passed.
14. The trial Court framed the following issues:
In O.S.No.294 of 2000:
"1. Whether the plaintiff is entitled for the relief of recovery of suit amount as prayed for ?
2. To what relief ?
In O.S.No.140 of 1998:
1. Whether the plaintiff is entitled to recover the suit amount as prayed for?
2. Whether this Court has no jurisdiction to entertain the suit as pleaded ?
3. Whether defendant-3 is not a necessary and proper party to the suit as claimed ?
4. To what relief ?"
15. The trial Court on appreciation of entire evidence dismissed
both the suits. With regard to the first issue in O.S.No.294 of 2000,
the trial Court held that as per Clause 7 of the agreement entered
into between the plaintiff and the first defendant unless the first
defendant received amounts from the second and third defendants,
it is not liable to pay the same to the plaintiff. So also in the first
issue in O.S.No.140 of 1998. As per Clause 18 of Ex.B12 the first
and second defendants are having lien over the amounts due to the
plaintiff in channadaal contract and thus the plaintiff is not entitled
to recover the amount. In the second issue it was held that there is PNR,J & PSS,J CCCA Nos.147 & 200 of 2002
no jurisdiction for the Courts in Hyderabad and in the third issue
it was held that the third defendant (plaintiff) is a proper and
necessary party.
16. Learned counsel for plaintiff contended that suit contract
was completely performed by it and there is no dispute regarding
the quantum of amount due to them. The defence department has
not withheld payment under suit contract for non-fulfilment of any
of the terms and conditions of the supply agreement, but they
withheld the amount due from MARKFED in another contract. He
would submit that it was illegal for defendants 2 and 3 to withhold
the amount due to supply cotton seed refined oil causing hardship to
plaintiff for no fault of him. He would further submit that the trial
Court erred in interpreting Clause-7 in the agreement relating to
payment. Back to Back payment in the agreement does not mean
that unless the first defendant receives amount from the second
and third defendants, there was no liability and obligation on the
first defendant to make payment to the plaintiff. He therefore
submitted that his appeal deserves to be allowed by setting aside
the common judgment dated 12.04.2002.
17. Learned Advocate General appearing for the AP MARKFED
(now Telangana MARKFED) contended that the second and third
defendants in purported exercise of their right of lien in connection
with risk purchase loss in another contract for supply of channa
daal erroneously did not release the amount due to it for supply of
cotton seed refined oil. As there is no difference or dispute regarding
supply and the amount receivable by the plaintiff, the second
defendant could not have withheld the amount. He would submit PNR,J & PSS,J CCCA Nos.147 & 200 of 2002
that as per Clause-7 of agreement, Ex.A2, MARKFED is not
required to pay to plaintiff unless the amount is paid by the 2nd
and 3rd defendants. Admittedly, the amount claimed by the
plaintiff is not paid by them. Therefore, the 1st defendant has not
defaulted in payment.
17.1. He further contended that Ex.B12 is a compilation of
conditions of contract covering contracts placed by the Central
Purchase Organisation of Government of India and the Department
of Supply, which is part of Ministry of Commerce. But the present
contract is under the Ministry of Defence and has no connection
with Ministry of Commerce and as such the terms and conditions
of such contract are not applicable to the present contract. There
is no clause regarding right of lien in the agreement relating to the
present suit.
17.2. He further contended that as per Para 22 of the Arbitration
Clause, they gave notice under Section 80 of CPC to the first and
second defendants, for which they did not respond and as such the
present suit is filed. In the written statement the defendants have
not taken the plea of arbitration, and therefore, it should be
construed that the second and third defendants have waived their
right to refer the matter to the arbitration. He therefore, earnestly
appealed to this Court to set aside the common judgment by
allowing the appeal.
18. He would submit that the defendants 2 and 3 have not
invoked the clause of right of set of, no additional Court fee was
paid and therefore they are not entitled to claim such adjustment.
Merely because award is passed in another contract holding that PNR,J & PSS,J CCCA Nos.147 & 200 of 2002
claim of 2,47,06,250/- as amount payable to defendants 2 and 3
towards risk purchase loss is no ground to withhold the amount
due under this Contract. Such withholding is not permissible
without availing the right of set of.
19. Learned Assistant Solicitor General submitted that the suit
is not maintainable in view of agreement to resolve the dispute by
arbitration as incorporated in Clause-12 of the Contract. He
further submitted that defendants 2 and 3 are entitled to withhold
the amount in view of Clauses-18 and 18A of the standard terms of
contract. As per the award of Arbitrator, the 1st defendant is due
to defendants 2 and 3 to a tune of 2,47,06,250/- and as the said
award amount is not paid, any amount payable by them can be
withheld. Thus, withholding the balance amount in contract to
supply cotton seed refined oil is valid.
ISSUE NO.1 IN O.S.NO.294 OF 2000 AND ISSUE NO.1 IN O.S.NO.140 OF 1998:
20. To appreciate respective submissions, relevant clauses to be
noticed are Clause-7 of Agreement (Ex.A2) and Clauses-21(a) and
(b) of Ex. B11 (identical to clauses 18 and 18-A of Ex.B12).
20.1. Clause-7 of Agreement-Ex.A2 reads as under:
'That the mode of payment of such supplies of stock by the SECOND PARTY to the FIRST PARTY would be in the manner of back to back arrangement that is to say as soon as the FIRST PARTY receive cheques in their favour from the aforesaid organisations the FIRST PARTY shall arrange the payment immediately on receipt of amounts from the Defence and issue their own cheques in favour of the SECOND PARTY for the identical amount as may be received by the FIRST PARTY by cheques from the said organisation minus 1% of value of the stocks supplied, towards their own commission. The SECOND PARTY will not have any right to payment till first party receives the same from Army Purchase Organisation, Ministry of Defence, New Delhi.' PNR,J & PSS,J CCCA Nos.147 & 200 of 2002
20.2. Clause 21(a) and (b) of Ex.B.11 reads as under:
" WITHHOLDING AND LIEN IN RESPECT OF SUMS CLAIMS.
(a) Whenever any claim or claims for payment of sum of money arises out of or under the contract against contractor, the purchaser shall be entitled to withhold and also have lien to retain such sum or sums in whole or in part from the security, if any, deposited by the contractor and for the purpose aforesaid, the purchaser shall be entitled to withhold the said cash security deposit or the security, if any, furnished as the case may be and also have a lien over the same pending finalisation adjudication of any such claim. In the event of the security being insufficient to cover the claimed amount or amounts or if security has been taken from the contractor, the purchaser shall be entitled to withhold and have a lien to retain to the extent of such claimed amount or amounts referred to supra, from any sum or sums found payable or which at any time thereafter may become payable to the contractor under the same contract or any person contracting through the Secretary pending finalisation or adjudication of any such claim.
It is an agreed term of the contract that the sum or money or monies so withheld or retained under the lien referred to above by the purchaser will be kept withheld or retained as such by the purchaser till the claim arising out of or under the contract is determined by the Arbitrator and the award is not objected by either competent partly in the court (if the contract is governed by the arbitration clause) or by the competent court as prescribed under clause 20 of DGS&D-68 (Revised) as the case may be, and that contractor will have no claim for interest or damages whatsoever on any account in respect of such withholding or retention under the lien referred to supra and duly notified as such to the contractor. For the purpose of this clause, where the contractor is a partnership firm or a limited company the purchaser shall be entitled to withhold and also have a lien to retain towards such claimed amount or amounts in whole or in part from any sum found payable to any partner or limited company as the case may be whether is his individual capacity or otherwise.
(b) LIEN IN RESPECT OF CLAIMS IN OTHER CONTRACTS:
Any sum of money due and payable to the contractor (including the security deposit returnable to him) under the contract may be withheld or retained by way of lien by the purchaser or Government or any other person or persons contracting through the Secretary against any claim of the purchaser or Government or such other person or persons in respect of payment of a sum of money arising out of or under any other contract made by the contractor with the purchaser or Government or with such other person or persons.
PNR,J & PSS,J CCCA Nos.147 & 200 of 2002
It is an agreed term of the contract that the sum of money so withheld or retained under this clause by the purchaser or Government will be kept withheld or retained as such by the purchaser or Government or till his claim arising out of in the same contract or any other contract is either mutually settled or determined by the Arbitrator and the award is not objected by either party in the competent court under clause 20 of DGS&D (Revised) as the case may be, and that the contractor shall have no claim for interest or damages whatsoever on this account or on any other ground in respect of any sum of money withheld or retained under this clause and duly notified as such to the contractor.
Other contract with the purchaser or the Government or any person."
21. MARKFED is an organisation dealing with procurement and
supply of food grains. It entered into two contracts with third
defendant to supply cotton seed refined oil and channa daal. They
are independent contracts and not connected to each other. Ex.A2-
agreement was entered between the first defendant-First Party and
plaintiff - M/s.Dokwal Refinery-Second Party. As per the said
agreement, M/s.Dokwal Refinery supplied 500 metric tonnes of
cotton seed refined oil to MARKFED for an amount of
1,82,18,351.56 Ps. This is pursuant to its contract with third
defendant to supply the oil. When once the contract is executed,
the plaintiff is entitled for the amount due to it. There is no
dispute regarding the quantum of amount to be paid by the first
defendant to the plaintiff. In fact, the first defendant also claimed
the said amount with interest from the second and third
defendants in O.S.No.140 of 1998. The first defendant also paid
an amount of 1,65,94.009.85 Ps. The dispute is only in respect
of payment of balance amount of 16,76,082.83 Ps. with interest.
22. The first defendant takes shelter under Clause 7 of Ex.A2
for not paying the balance amount. According to 1st defendant as PNR,J & PSS,J CCCA Nos.147 & 200 of 2002
the Ministry of Defence has not made the balance payment, it is
not under any obligation to release the balance amount. According
to 1st defendant Clause-7 is clear. M/s.Dokwal Refinery will not
have any right to payment till they receive the same from Army
Purchase Organization, Ministry of Defence, New Delhi. In the said
Clause, it is argued, also mentioned with regard to mode of
payment as, back to back arrangement i.e. if the first defendant
receives cheques in its favour, then it shall arrange the payment
immediately on receipt of amounts from the defence and issue
their own cheques in favour of M/s.Dokwal Refinery after
deducting one percent of the value towards their commission.
MARKFED contended that the amounts were not released by the
second and third defendants in their favour.
23. At the first blush said stand appears to be valid. However,
on a deeper consideration of evidence on record and on fair
assessment of relevant Clauses extracted above, the fortress built
around by the first defendant, thought as formidable, crumbles,
breaks the shutters and the truth bares open.
24. The basic facts are not in dispute. Supply of cotton seed
refined oil was a tripartite transaction. First defendant entered into
two separate contracts with defence authorities to supply cotton
seed refined oil and channa daal. The first defendant in turn entered
into contract with plaintiff to supply 500 metric tonnes of cotton
seed refined oil. As this agreement is in pursuance to the first
agreement with defence authorities, in clause-7 of the agreement
(Ex.A2), a default clause is incorporated leading to this long drawn
litigation. Though 500 metric tonnes of cotton seed refined oil was PNR,J & PSS,J CCCA Nos.147 & 200 of 2002
supplied and no concern is raised on quality and quantity of
supply, the first defendant has not released final payment of
16,76,082.83 to plaintiff on the ground that said amount is not
settled by defendants 2 and 3 by relying on clause-7. On the
contrary, Clause 21 of Ex.B11 vests discretion in the Ministry of
Defence to withhold/adjust money payable by it to MARKFED
under any contract if the Ministry is required to receive money
from MARKFED in any other contract. It is therefore necessary to
have a closer look at these two clauses. While clause-7 (Ex.A2)
disentitles plaintiff to compel the first defendant for payment,
question for consideration is can this restraint would continue to
apply when clause-21 of Ex.B11 is invoked by the Defence
Ministry.
25. As noticed herein above, first defendant failed to honour the
commitment to supply channa daal forcing the Ministry of Defence
to secure the commodity else where at a price higher than
mutually agreed. As the demand to pay the differential amount did
not yield proper response the defendants 2 and 3 invoked
arbitration clause; Arbitrator was appointed; Arbitrator passed
award for an amount of 2,47,06,250/-; this award has become
final. In terms thereof, the Defence Ministry is entitled to recover
the money from first defendant.
26. Coming to Clause-21 of Ex.B11, which is revised ABC
Specifications No.170A for Refined Mustard Oil, which is part of
invitation to tender bearing No.J-12031/1/94/Pur.IV, dated
12.09.1994 for supply of Edible Oil viz., Refined Mustard Oil/
Refined Cottonseed Oil (clauses-18 and 18A of standard form of PNR,J & PSS,J CCCA Nos.147 & 200 of 2002
contract) vests lien on the Defence Ministry to withhold/adjust
amount due to them from any other contract (channa daal) while
settling the amounts flowing out of a contract (cotton seed
refined oil). P.Ramanatha Aiyar's 'THE LAW LEXICON' defines
word lien as, "A lien, in a limited and technical sense, signifies the
right by which a person in possession of personal property holds
and retains it against the owner in satisfaction of a demand due to
the party retaining it; but in its more extensive meaning and common
acceptation it is understood and used to denote a legal claim or
charge on property, either real or personal, as security for the
payment of some debt or obligation; it is not strictly a right in or right
to the thing itself but more property constitutes a charge or security
thereon". Admittedly, amount of 2,47,06,250/- is due to Defence
Ministry from MARKFED due to its failure to supply channa daal. It
is the assertion of defendants 2 and 3 that they have exercised the
lien vested in their favour and withheld balance payment under
cotton seed refined oil supply contract in view of dues from
MARKFED.
27. Once a party to a contract exercises lien as per term of
contract and withholds/retains the amount payable to other party
by referring to liability of other party under different agreement, it
cannot be said any more that balance amount continues to be
treated as unpaid. Further, it is also fair to assume that the object
of Clause-7 in the agreement is only to restrain MARKFED from
delaying the payment to M/s.Dokwal Refinery even after receiving
the amounts from the first and second defendants. Thus, in the
facts of these cases, defence under Clause 7 is no more available to
1st defendant.
PNR,J & PSS,J CCCA Nos.147 & 200 of 2002
28. Though learned Advocate General for the appellant in CCCA
No.200 of 2002, by referring to Ex.B.12, sought to contend that the
rules are meant for Ministry of Commerce but not Ministry of
Defence and as such the Clauses-18 and 18A are not applicable to
the defence authorities. To support his contention, learned
Advocate General did not file any rules pertaining to Ministry of
Defence. Ex.B.12 is standard conditions of contract governing
contracts placed by the Central Purchase Organization of
Government of India (now under Department of Supply) and are
incorporated in Clause 21 of terms and conditions of Contract
(Ex.B.11). As per these Clauses, the defence authorities are
entitled to withhold or retain by way of lien any amount payable to
the contractor under any other contract made by the contractor.
Therefore the argument of the learned Advocate General for the
appellant in CCCA No.200 of 2002 cannot be appreciated.
29. There is no illegality in withholding the amounts by the
Ministry of Defence due to the first defendant. More over, the loss
sustained by the defence authorities is much more than the
amount withheld by them. This issue is decided against the first
defendant and in favour of the second and third defendants.
30. The trial Court misdirected itself in assessing the issue and
thus finding of the trial Court on the first issue in O.S.No.294 of
2000 is liable to be set aside and is accordingly set aside. The first
defendant is directed to pay an amount of 24,24,395/- to the
plaintiff.
PNR,J & PSS,J CCCA Nos.147 & 200 of 2002
31. The plaintiff sought interest at the rate of 24% per annum as
it is a commercial transaction, but the first defendant contended
that as there is no such clause in the agreement, it is not liable to
pay the interest. It is true that there is no clause with regard to
payment of interest in the agreement, but as per Clause 7 when it
receives the amount from the defence authorities, it has to
immediately pay the same to the plaintiff. But the first defendant
withheld the amount and failed to pay the legally due amount to
the plaintiff. Though, commodity was supplied by the plaintiff on
time, there was inordinate delay in releasing the amount due.
Delay in settlement of amount due in a commercial transaction
certainly has adverse consequences. Therefore, the plaintiff is
entitled for interest at the rate of 12% per annum from the date of
suit till the date of realization.
32. Accordingly, the first defendant is directed to deposit the
amount of 24,24,395/- with interest at the rate of 12% per
annum from the date of petition till realization within three months
from the date of this judgment and the plaintiff is permitted to
withdraw the same immediately.
ISSUE No.2 in O.S.No.140 of 1998: .
33. Learned counsel for the plaintiff would further contend that
when it issued notice under Section 80 CPC to the second and
third defendants, they failed to reply and as such it filed the suit
for recovery of amount. Defendants 2 and 3 though raised
objection with regard to jurisdiction of the Court on the ground of
arbitration clause, but have not insisted the Court to decide the
issue of jurisdiction as a preliminary issue and allowed the Court PNR,J & PSS,J CCCA Nos.147 & 200 of 2002
to dispose of the matter on merits. Therefore, the trial Court erred
in deciding the issue against first defendant.
ISSUE NO.3 in O.S.No.140 of 1998:
34. On this issue, we are in respectful agreement with the view
expressed by the trial Court and needs no interference.
35. On the above analysis, C.C.C.A.No.200 of 2002 filed against
judgment and decree dated 12.04.2002 passed in O.S.No.140 of
1998 is dismissed, and C.C.C.A.No.147 of 2002 filed against
judgment and decree dated 12.04.2002 passed in O.S.No.294 of
2000 is allowed. There shall be no order as to costs.
36. Pending miscellaneous petitions, if any, in these appeals
shall stand closed.
__________________________ JUSTICE P.NAVEEN RAO
_________________________ JUSTICE P.SREE SUDHA Date: 04.02.2022 Pgs/pt/kkm PNR,J & PSS,J CCCA Nos.147 & 200 of 2002
HON'BLE SRI JUSTICE P.NAVEEN RAO AND HON'BLE SMT. JUSTICE P.SREE SUDHA
CCCA Nos.147 AND 200 OF 2002
Date: 04.02.2022
Pgs/pt/kkm
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!