Monday, 18, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Raj.State Ind.Dev.And Inves. ... vs Rajendra Kumar (2025:Rj-Jd:17415)
2025 Latest Caselaw 11026 Raj

Citation : 2025 Latest Caselaw 11026 Raj
Judgement Date : 3 April, 2025

Rajasthan High Court - Jodhpur

Raj.State Ind.Dev.And Inves. ... vs Rajendra Kumar (2025:Rj-Jd:17415) on 3 April, 2025

Author: Vinit Kumar Mathur
Bench: Vinit Kumar Mathur
[2025:RJ-JD:17415]

        HIGH COURT OF JUDICATURE FOR RAJASTHAN
                      AT JODHPUR.
                     S.B. Civil First Appeal No. 143/1990

Rajasthan       State       Industrial         Development           &    Investment
Corporation, Udhyog Bhawan, Tilak Marg, Jaipur.
                                                                         ----Appellant
                                        Versus
Shri Rajendra Kumar son of Shri Bhanwar Lal Sethiya, Resident
of Marothi Sethiyan, Gawad, Bikaner.
                                                                     ----Respondent


For Appellant(s)              :     Mr. Falgun Buch.
                                    Ms Simran Mehta.
For Respondent(s)             :     Mr. Ajay Kumar Vyas.
                                    Ms Jatin Sankhla.



         HON'BLE MR. JUSTICE VINIT KUMAR MATHUR

Order

03/04/2025

Heard learned counsel for the parties.

The present appeal has been filed against the judgment and

decree dated 25.07.1990 passed by District Judge, Bikaner in Civil

Original Suit No.84/1986 whereby the suit preferred by the

respondent-plaintiff was decreed in his favour and the appellant-

defendant was directed to pay an amount of Rs.59,607.15.

Briefly the facts necessary to be noted are that the

respondent-plaintiff applied for allotment of an Industrial Plot

No.E-28 before the appellant-defendant for the purpose of

establishment of an Ice and Cold Storage factory on 06.03.1982.

Pursuant to the application of the respondent-plaintiff, the

appellant-defendant directed the respondent-plaintiff to deposit

the development charges amounting to Rs.16,000/-. The amount

[2025:RJ-JD:17415] (2 of 8) [CFA-143/1990]

as directed by the appellant-defendant was not deposited,

therefore, a show cause notice dated 30.04.1982 was served upon

the respondent-plaintiff by the appellant-defendant. When the

respondent-plaintiff did not respond to the said show cause notice,

once again, a notice was issued on 29.05.1982 to the respondent-

plaintiff to deposit the development charges. The respondent-

plaintiff did not deposit the amount asked for by the appellant-

defendant, therefore, ultimately the allotment was cancelled by

the appellant-defendant vide order dated 23.08.1982. The

respondent-plaintiff again approached the appellant-defendant for

allotment of plot No.E-28 vide letter dated 18.12.1982 assuring

the appellant-defendant that he will comply with all the terms and

conditions imposed upon him. In pursuance of the application

dated 18.12.1982, the respondent-plaintiff deposited the

development charges and therefore, the appellant-defendant

allotted Plot No.E-26 to the respondent-plaintiff. However, the

allotment of Plot No.E-26 was subject to deposition of Rs.2533.35

as interest, since, the respondent-plaintiff failed to comply with

the condition of depositing the interest amount, therefore, he was

served with a letter dated 15.10.1983 with request to deposit the

said amount. The appellant-defendant again informed the

respondent-plaintiff for execution of the lease agreement vide

letter dated 01.11.1983, but despite repeated communications,

the respondent-plaintiff did not deposit the requisite charges. Vide

communication dated 01.03.1984, the respondent- plaintiff sought

time to deposit second installment of the charges due to the

appellant-defendant. Finally, on 23.03.1984, a lease deed was

executed between the appellant-defendant and respondent-

[2025:RJ-JD:17415] (3 of 8) [CFA-143/1990]

plaintiff for allotment of Industrial Plot No.E-26 and possession of

the same was handed over to the respondent-plaintiff on

01.04.1984. In the lease agreement, a condition was imposed

that the respondent-plaintiff shall commence construction of his

industry within a period of six months from the date of execution

of the lease deed and start the production within a period of 24

months. The respondent-plaintiff did not start the construction

work of his industry, therefore, the appellant-defendant issued a

letter on 21.04.1984 informing the respondent-plaintiff that he

must commence the construction work within the stipulated

period. Once again, vide notice dated 08.08.1984, the appellant

reiterated the request made by it vide letter dated 21.04.1984.

Since, the respondent-plaintiff failed to comply with the

correspondences made and also failed to start the construction of

his industrial premises, the appellant-defendant cancelled

allotment of Plot No.E-26 made in favour of the respondent-

plaintiff vide order/letter dated 15.09.1984. The respondent-

plaintiff vide his letter dated 05.10.1984 filed an application for

extension of time for another six months for complying with the

condition mentioned in clause 2(d) of the lease agreement and for

furnishing the map and documents relating to the same. The

request made by the respondent-plaintiff was rejected by the

appellant-defendant vide letter dated 19.10.1984.

In these circumstances, the respondent-plaintiff instituted a

suit for claiming an amount of Rs.69, 607/- from the appellant-

defendant. In the suit proceedings, after completion of the

pleadings, 05 issues were framed. Learned trial court after dealing

with the evidence produced before it decreed the suit in favour of

[2025:RJ-JD:17415] (4 of 8) [CFA-143/1990]

the respondent-plaintiff by passing a degree of Rs.59,607.15 vide

its judgment and decree dated 25.07.1990.

Learned counsel for the appellant vehemently submitted that

since the respondent-plaintiff failed to comply with the repeated

request for depositing the amount due right from 1982 when Plot

No.E-28 & E-29 were allotted to him, therefore, the appellant-

defendant was well within its right to cancell the lease agreement

made in favour of the respondent-plaintiff for Plot No.E-26.

Learned counsel submits that all the due opportunities were

granted to the respondent-plaintiff to deposit the amount due to

the appellant-defendant, but despite having given opportunity of

hearing, he failed to deposit the amount due, therefore, the

appellant-defendant has not committed any illegality in cancelling

the lease agreement made in favour of the respondent-plaintiff.

Learned counsel further submits that there was a specific

condition in the lease agreement dated 23.03.1984 effective from

01.04.1984 that the respondent-plaintiff was required to

commence the construction of the Industry within a period of six

months from the date of execution of the lease deed and since,

the respondent-plaintiff failed to start construction activities, he

was served with two notices dated 02.04.1984 and 08.08.1984.

Since, the respondent-plaintiff did not respond to the above two

notices issued by the appellant, the appellant-defendant passed an

order on 15.09.1984 whereby the lease agreement was cancelled.

Learned counsel submits that the learned trial court has failed to

appreciate the controversy involved in the matter in a right

perspective and has committed error while recording the findings

on Issue Nos.1, 2 & 4 against the appellant-defendant. He further

[2025:RJ-JD:17415] (5 of 8) [CFA-143/1990]

submits that since the respondent-plaintiff has not commenced

the construction activities for almost five and half months from the

date of taking over possession of the leased land, therefore, there

was no reason to believe that he would commence the

construction activities within a period of fifteen days. Learned

counsel submits that the order of cancellation passed by the

appellant-defendant was just and proper, therefore, the

respondent-plaintiff was not entitled for any amount deposited by

him. Learned counsel submits that since the respondent-plaintiff

has failed to obey the condition of raising the construction within a

period of six months, the appellant cannot be burdened with the

refund of the amount deposited by the respondent-plaintiff. He,

therefore, prays that the appeal filed by the appellant-defendant

may be allowed and the judgment and decree dated 25.07.1990

passed by District Judge, Bikaner may be quashed and set aside.

Per contra, learned counsel for the respondent-plaintiff

submits that the learned trial court has considered the entire

evidence and has minutely dealt with the submissions made

before it while recording the findings on issues No.1, 2 & 4. He

submits that pith and substance of the entire case lies in a narrow

compass that the lease deed which was executed between the

parties on 23.03.1984 was having specific condition at clause 2(d)

wherein it was agreed that the appellant-plaintiff shall commence

the construction activities of his industry within a period of six

months and start the production within a period of 24 months i.e.

w.e.f. 01.04.1984. He submits that the period of six months was

coming to an end on 01.10.1984 and therefore, termination of

lease 15 days prior to the cutoff date was arbitrary and incorrect,

[2025:RJ-JD:17415] (6 of 8) [CFA-143/1990]

therefore, the respondent-plaintiff was well within his right to

commence the construction activities of his industry prior to

completion of six months and since the period of six months was

not over, the appellant-defendant terminated the lease before

expiry of that date i.e. 15.09.1984. Learned counsel submits that

the findings recorded by the trial court are just and proper,

therefore, the same do not call for any interference by this Court.

He submits that since termination of lease is dehors the law, the

respondent-plaintiff is entitled to claim the amount deposited by

him with the appellant-defendant.

I have considered the submissions made at the bar and also

gone through the relevant record of the case.

The chronology of facts mentioned above is not disputed by

the counsel for the parties. Therefore, it is clear that the lease

deed was executed between the parties on 23.03.1984 in

pursuance of which, possession of Plot No.E-26 was handed over

to the respondent-plaintiff on 01.04.1984. As per clause 2(d) of

the lease agreement, the respondent-plaintiff was to commence

the construction of Industry within a period of six months and

start the production within a period of 24 months. Since, the

respondent-plaintiff was not raising the construction despite lapse

of period of more than five months, therefore, two notices were

issued by the appellant-defendant on 21.04.1984 and 08.08.1984

requesting the respondent-plaintiff to start the construction of

industry. Since, the respondent-plaintiff did not start the

construction for about five and half months, therefore, the

appellant-plaintiff terminated the lease vide order dated

15.09.1984. For complying with the provisions of clause 2(d), the

[2025:RJ-JD:17415] (7 of 8) [CFA-143/1990]

period of six months was to complete on 01.10.1984, however,

the appellant-defendant terminated the lease deed on 15.09.1984

on the ground that the respondent-plaintiff failed to start

construction of his industry as agreed between the parties. As per

clause 2(d), the period of six months was coming to an end on

01.10.1984 and therefore, even if the appellant-defendant would

have considered that the respondent-plaintiff has failed to comply

with the condition of clause 2(d), the said decision of terminating

the lease deed was required to be taken after 01.10.1984. Since,

the construction activities were just required to be commenced,

therefore, it cannot be pre-empted that since the respondent-

plaintiff had not started the construction within a period of five

and half months, therefore, he will not start the same before

expiry of six months. It was not open for the appellant-defendant

to terminate the lease agreement prior to expiry of six months on

the ground that the respondent-plaintiff has not commenced the

construction of his industry within a period of six months. Since,

the period of six months was to expire on 01.10.1984, therefore,

the appellant was not justified in terminating the lease agreement

on 15.09.1984 on the ground that the respondent-plaintiff has

failed to start construction of his industry as agreed between them

in the lease deed. The learned trial court has elaborately dealt

with all the documents placed before it including the lease deed

executed between both the parties. The findings recorded by

learned trial court on issue No.1, 2 & 4 are perfectly justified and

do not call for any interference by this court.

In view of the discussion made above, I find no merit in the

appeal. Consequently, the appeal filed by the appellant-defendant

[2025:RJ-JD:17415] (8 of 8) [CFA-143/1990]

is dismissed. The judgment and decree dated 25.07.1990 passed

by District Judge, Bikaner in Civil Original Suit No.84/1986 is

upheld.

Since, interim order was passed by this court on 30.07.1992

and the respondent- plaintiff had deposited entire amount as

directed by this court, therefore, the respondent-plaintiff will be

free to withdraw the said amount from the court of District Judge,

Bikaner, in accordance with law.

(VINIT KUMAR MATHUR),J 298-Anil Singh/-

Powered by TCPDF (www.tcpdf.org)

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 

LatestLaws Partner Event : IJJ

 
 
Latestlaws Newsletter