Monday, 18, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

State Of Rajasthan vs M/S Bharti Construction Company
2024 Latest Caselaw 5390 Raj/2

Citation : 2024 Latest Caselaw 5390 Raj/2
Judgement Date : 21 August, 2024

Rajasthan High Court

State Of Rajasthan vs M/S Bharti Construction Company on 21 August, 2024

Author: Pankaj Bhandari

Bench: Pankaj Bhandari, Praveer Bhatnagar

[2024:RJ-JP:32448-DB]

        HIGH COURT OF JUDICATURE FOR RAJASTHAN
                    BENCH AT JAIPUR

           D.B. Civil Miscellaneous Appeal No. 2930/2020

1.       State Of Rajasthan
2.       Chief Engineer, Irrigation Department, (Presently Water
         Resources Department) Rajasthan.
3.       Executive Engineer, Chawali Irrigation Project Presently
         Chawli    Canal         Division        Jhalawar      Through     Executive
         Engineer, Chawli Irrigation Project Present Chawli Canal
         Division Jhalawar Rajasthan.
                                                                       ----Appellants
                                       Versus
M/s     Bharti    Construction          Company,            Kushalbagh     Banswara
Rajasthan
                                                                     ----Respondent
For Appellant(s)             :     Mr. B.S. Chhaba, AAG with
                                   Mr. Avinash Choudhary, Adv.
                                   Ms. Shruti Pareek, Adv.
                                   Ms. Kavita Bhargawa, Adv.
For Respondent(s)            :     Mr. Sanjay Mehrish, Adv. with
                                   Mr. Rakesh Kumar Saini, Adv.



           HON'BLE MR. JUSTICE PANKAJ BHANDARI
          HON'BLE MR. JUSTICE PRAVEER BHATNAGAR

                                    Judgment

RESERVED ON                                 ::                         23/07/2024
PRONOUNCED ON                               ::                         21/08/2024
(Per. Pankaj Bhandari, J)


1.          Appellant-State          has      preferred        the   instant   appeal

aggrieved by the judgment dated 16.11.2019 passed by the

Commercial Court, Kota, whereby the application filed by the

appellant-State under Section 34 of the Arbitration and

Conciliation Act, 1996 (hereinafter referred to as 'the Act of 1996')

was rejected and the award dated 09.11.2015 was confirmed.

[2024:RJ-JP:32448-DB] (2 of 8) [CMA-2930/2020]

2. Succinctly stated the facts of the case are that the

Superintending Engineer, Irrigation Circle, Jhalawar invited tenders

on 19.11.1996 for the work of construction of Earthen Dam from

R.D. (-) 60m to R.D. 1290m of Chauli Irrigation Project, Pirwa,

District Jhalawar. The respondent-claimant submitted the tender,

which was found lowest and accepted by the competent authority

of the Government and the same was communicated to the

claimant. An Agreement was executed between the parties on

28.03.1997. The claimant submitted their claims before the

learned Arbitrator amounting to Rs.14,24,721/- towards enhanced

rate for extra work beyond 50% in the work of head outlet sluice;

Rs.52,24,900/- towards extra lead of sand and filter material;

Rs.181.18 lacs on account of infrastructure overhead expenses

and loss of profit being retained longer on the contract;

Rs.41,65,750/- on account of idling of men and machineries and;

Rs.45,38,686/- towards the increase in the rate of minimum

wages.

3. The defence of the appellant-State was that the

contractor before submitting the tender must have verified all the

facts about the site i.e. source of material, labour, borrow area,

quarry sites and other necessary information useful for the

execution of the work. The contractor is not entitled for payment

of extra lead as per Clause-63 of the Agreement. The appellant-

State also stated in their reply that delay in executing the work

within the stipulated period is due to failure of the contractor to

accelerate the work. Several letters were written to the contractor

in this regard, but no attention was paid by the contractor. In

regard to the excess quantity of the work, it is pleaded in the

[2024:RJ-JP:32448-DB] (3 of 8) [CMA-2930/2020]

reply by the appellant that there was no mutual agreement

regarding executing the additional quantity of work and thus, the

contractor is not entitled for any payment in this regard.

4. Learned Arbitrator had framed as many as seven issues

and along with these issues, decided five claims raised by the

claimant. Claim No.1 pertained to a claim of Rs.14,24,721/-

towards enhanced rate for extra work beyond 50% in the work of

head outlet sluice, was decided in favour of the claimant; Claim

No.2 is pertaining to Rs.52,24,900/- towards extra lead of sand

and filter material, was also decided in favour of the claimant;

Claim No.3 of Rs.181.18 lacs on account of infrastructure

overhead expenses and loss of profit, was rejected; Claim No.4 of

Rs.41,65,750/- on account of idling of men and machineries, was

partly allowed and Rs.4,09,200/- was awarded to the claimant

and; Claim No.5 of Rs.45,38,686/- towards increase in the rate of

minimum wages, was also rejected. Aggrieved by the award dated

09.11.2015, appellant-State filed an application under Section 34

of the Act of 1996 before the Commercial Court, Kota, which was

rejected vide order dated 16.11.2019. Thus, aggrieved by the

award dated 09.11.2015 as well as the Judgment and Order dated

16.11.2019, the appellant-State has preferred the present appeal

before this Court.

5. It is contended by Mr. B.S. Chhaba, Additional Advocate

General, appearing for the appellant-State that the learned

Arbitrator has misconducted the proceedings by not considering

the specific clause in the Agreement that no extra payment will be

made on account of extra/excess lead involved in carting the

material from longer lead. It is also contended that the learned

[2024:RJ-JP:32448-DB] (4 of 8) [CMA-2930/2020]

Arbitrator has failed to consider Clause No.2 & 63 of the

Agreement which provides that it was the duty of the contractor to

acquaint himself and it was specifically provided that it shall be

deemed that the contractor has carefully examined the work and

site conditions, special conditions, the specifications and drawings

and shall be deemed to have visited the site of the work and to

have fully informed himself regarding the local conditions. It is

contended that it was specifically provided in Clause No.63 of the

Agreement that no extra lead/lifts for any material for any item of

work whatsoever it may be due to any reason shall be paid to the

contractor on this account. The lead/source adopted are of

computing the rates. The contractor should verify the source/lead

before quoting the rates as no claim on account of change of

source/lead will be entertained.

6. It is contended that when there was a specific bar on

providing extra amount for lead, the learned Arbitrator has gone

beyond the terms of the Agreement and thus, the award should

have been quashed by the Commercial Court. It is argued that the

Arbitrator is bound by the terms of the Agreement and cannot go

beyond the same and thus, the Arbitrator has committed

misconduct in conducting the proceedings. It is further contended

that the learned Arbitrator has erred in awarding claim for

additional work which was contrary to Clause- 12A of the

Agreement. It is contended that the learned Arbitrator has further

erred in awarding idling charges and also awarding 12% p.a.

interest when there was no condition of interest in the Agreement.

It is argued that the award is contrary to public policy.

[2024:RJ-JP:32448-DB] (5 of 8) [CMA-2930/2020]

7. Counsel appearing for the respondent-claimant has

vehemently opposed the appeal filed under Section 37 of the Act

of 1996. It is contended that the scope under Sections 34 & 37 of

the Act of 1996 is limited. The Court cannot sit as Appellate Court

in matters of award passed by the Arbitrator. It is also contended

that the learned Arbitrator has rightly allowed the claim of

Rs.14,24,741/- towards enhanced rate for extra work beyond 50%

in the work of head outlet sluice as Superintending Engineer-I

(S.E.-I) and Executive Engineer had given assurance to the

claimant to execute the work & that payment will be made after

sanction and it is only on this assurance that the contractor

executed the work. It is contended that the learned Arbitrator has

properly dealt with the letters written by S.E. Irrigation and the

correspondence which took place between the Officers of the

Department. It is argued that the claimant cannot be held

responsible for inaction of Addl. Chief Engineer for not taking

decision with regard to extra lead of sand and filter material. It is

argued that quarry site of filter material and sand was specified

from Himmatgarh with a lead of 2 kms, but as the material was

not available as per specification, the claimant had to carry the

material from AHU river, which involved a lead of 55 kms. It is

argued that the claimant is entitled to extra lead as he had

submitted his tender considering the lead to be 2 kms. It is

contended that the Arbitrator has rightly awarded amount in lieu

of idling charges as the men and machinery of the claimant

remained idle due to lapses on part of the appellant.

8. We have considered the contentions.

[2024:RJ-JP:32448-DB] (6 of 8) [CMA-2930/2020]

9. It is settled preposition of law that the powers under

Sections 34 & 37 of the Arbitration Act can be exercised only if the

case falls within the purview of Section 34 of the Act. It is also

settled preposition of law that the Courts cannot sit over the

award passed by the Arbitrator as an Appellate Authority.

However, it is also settled preposition of law that if the Arbitrator

passes an award against the terms of the contract, the same can

be set aside by the Court. In the present case in hand, we have to

see whether the Arbitrator has passed the award against the

terms of the contract.

10. Learned Arbitrator in the present case has awarded

amount for excess lead as the sand was not available at a distance

of two kms. and was to be carried from a distance of 55 kms. from

the place of construction. It would be appropriate to reproduce

Clause No.12(a) & 63 of the contract:-

"12(a): The quantum of additional work for each item shall not exceed 50% of the original quantity given in the agreement and the total quantum of additional and or extra items shall not exceed 20% of the total contract value unless otherwise naturally agreed by the Engineer-in-Charge and the contractor.

63. Leads and Lifts: The unit price of individual item shall include all leads and all lifts and other items involved in execution of work as per specifications and drawings specified in the Schedule "G". No extra lead/lifts for any material for any item of work, whatsoever it may be due to any reason shall be paid to the contractor on this account. The lead/ sources adopted are for computing the rates. The contractor should verify the source/lead before quoting the rate as no claim on account of charge of source/lead will be entertained. The materials as per specifications (as entered in schedule 'A- 6') shall have to be used irrespective of source/lead taken for estimation purpose and entered in unit price and no claim on account on change of leads/source will be entertained."

11. A bare perusal of above clause reveals that it was the

duty of the contractor to acquaint himself and it was specifically

[2024:RJ-JP:32448-DB] (7 of 8) [CMA-2930/2020]

provided that it shall be deemed that the contractor has carefully

examined the work and site conditions, special conditions, the

specifications and drawings and shall presume that he has visited

the site of the work and carefully informed him regarding the local

conditions. A bare perusal of Clause-63 also reveals that no extra

lead/lifts for any material for any item of work whatsoever it may

be due to any reason shall be paid to the contractor on this

account. It was also mentioned that the lead/source adopted was

for computing the rates and that the contractor should verify the

source/lead before quoting the rates as no claim on account of

change of source/lead would be entertained. Thus, there was a

specific bar on payment of extra amount for change of

source/lead. There being a specific bar, it was beyond the scope of

the Arbitrator to go beyond the terms of the agreement. This issue

was also brought to the notice of the Arbitrator but the Arbitrator

has awarded claim on the ground that in the tender document, the

lead was shown at a distance of two kms. Thus, the Arbitrator has

awarded the amount on the ground of equity.

12. We are of considered view that the Arbitrator is a

creature of the agreement and he cannot go beyond the terms of

the agreement. If there is specific bar on payment of extra

amount on account of change of source/lead then the Arbitrator

was not competent to award the said amount. It is settled

preposition of law as held by the Apex Court in Oil & Natural Gas

Corporation Ltd. Vs. SAW Pipes Ltd. (2003) 5 SCC 705 that if the

Arbitrator has gone beyond the terms of the agreement, the

award can be set aside. Since the award on account of extra lead

[2024:RJ-JP:32448-DB] (8 of 8) [CMA-2930/2020]

is beyond the terms of the agreement, the same cannot be

sustained by this Court.

13. However, as far as the claim of Rs.14,24,741/- towards

enhancement rate for extra work beyond 50% is concerned, from

letter written by the S.E. Irrigation and the correspondence which

took place between the Officers of the Department, it is clear that

the extra work was done on the assurance given to the claimant

by the Superintending Engineer and the Executive Engineer. The

claimant was thus, entitled for the extra work that he had done

beyond 50%. The learned Arbitrator has not committed any error

in awarding the said amount. Thus, the objections to the claim of

Rs.14 lac on account of enhanced rate for extra work cannot be

sustained. Learned Arbitrator has also properly appreciated the

documents and evidence and has committed no illegality in

awarding Rs.4 lac for idling of resources.

14. Consequently, the appeal deserves to be and is

accordingly, partly allowed. The claim with regard to the extra lead

of sand is rejected, however, the rest of claim as awarded by the

Arbitrator is upheld. The decree be modified accordingly.

15. Pending applications, if any, stand disposed.

                                   (PRAVEER BHATNAGAR),J                                         (PANKAJ BHANDARI),J

                                   Chandan/









Powered by TCPDF (www.tcpdf.org)
 

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 

LatestLaws Partner Event : IJJ

 
 
Latestlaws Newsletter