Citation : 2023 Latest Caselaw 1289 Raj
Judgement Date : 3 February, 2023
[2023/RJJD/004202]
HIGH COURT OF JUDICATURE FOR RAJASTHAN AT
JODHPUR
D.B. Civil Misc. Appeal No. 1748/2022
Union Of India, Through HQ Chief Engineer, Military Engineering
Service, Jodhpur Zone, Pin 900066 C/o 56 APO
----Appellant
Versus
M/s Maheshwari Enterprises, 1St 'C' Gole Building Road,
Sardarpura, Jodhpur (Raj.), Through Its Authorised Signatory.
----Respondent
For Appellant(s) : Mr. Muktesh Maheshwari
For Respondent(s) : Mr. R.K. Purohit
HON'BLE MR. JUSTICE SANDEEP MEHTA
HON'BLE MS. JUSTICE REKHA BORANA
Judgment
03/02/2023
BY THE COURT : (PER HON'BLE BORANA, J.)
The present appeal has been preferred against the order
dated 12.05.2022 passed by the Commercial Court No.1, Jodhpur
(hereinafter referred to as 'the learned Court below') whereby the
objections under Section 34 of the Arbitration and Conciliation Act,
1996 (for short 'the Act of 1996') preferred by the appellant-Union
of India against the arbitral award dated 29.04.2019 have been
rejected.
The facts of the case are that some disputes arose between
the parties, out of the contract executed between them for the
work CA NO CEJZ/JODH/25/2004-05: PROVN OF DEF OTM
ACCN FOR 12 CORPS ARMY AVN BASE OF RALAWAS AT
JODHPUR. For resolution of the disputes as arisen, the sole
Arbitrator was appointed who entered into reference vide his letter
dated 24.11.2017. Vide the award dated 29.04.2019, the learned
[2023/RJJD/004202] (2 of 6) [CMA-1748/2022]
Arbitrator proceeded on to allow four claims and reject four claims
out of the eleven claims raised by the claimant. Three claims were
withdrawn by the claimant. Therefore, objections qua the allowed
four claims were filed by the Union of India before the learned
Court below. The learned Court below proceeded on to reject all
the objections as preferred by the appellant-Union of India against
which the present appeal has been preferred.
Only two grounds have been raised in the present appeal,
firstly that the learned Arbitrator has erred in entertaining the
total time barred claims and in rejecting the objections of the
Union on the said issue. Secondly, that the award qua Claim No.2
had been wrongly allowed by the learned Arbitrator in favour of
the claimant totally in contravention of Condition No.7 of the
contract.
First ground raised by learned counsel for the appellant is
that the claims regarding escalation amount (Claim No.1) as well
as the losses due to delay in payment of final bill (Claim No.10)
were grossly time barred and therefore, could not have been
entertained by the learned Arbitrator.
A perusal of the order impugned reveals that the learned
Court below has specifically observed that the final bill was paid to
the claimant by the respondent-Union on 15.10.2014 and
subsequently, during pendency of the arbitral proceedings, the
amount of Rs.5,94,564/- was paid on 22.02.2019. Prior to
22.02.2019, the amount as claimed by the claimant was never
denied to be paid by the respondent-Union. It is only on
22.02.2019 that a part payment of Rs.5,94,564/- was made and
the payment of remaining amount as claimed was denied. Prior to
[2023/RJJD/004202] (3 of 6) [CMA-1748/2022]
this payment, the same was never denied rather proceedings for
computation of the amount payable were being undertaken by the
Department. Therefore, the limitation, if any, would commence
only on/after 22.02.2019 when the remaining claim of the
claimant was denied by the respondent-Union.
Further, learned Court below has observed that the ground of
the claims being time barred was never raised by the Union before
the learned Arbitrator but still the question of limitation being a
ground based on public policy, the same was being entertained
and adjudicated. After a thorough analysis of the fact, the learned
Court below held that the claims of the claimant were within the
limitation as provided in terms of law.
A perusal of the record shows that the stipulated dates of
commencement of work in question were 18.02.2005 (Phase I)
and 18.02.2005 (Phase II) respectively. The stipulated dates of
completion of work were 17.11.2005 (Phase I) and 17.11.2006
(Phase II) respectively. However, the work of Phase II could not be
completed in stipulated time and the same was extended four
times by the Union. Ultimately, the work was completed on
17.11.2005 (Phase I) and 05.02.2009 (Phase II) respectively. The
final bill qua the work was submitted by the claimant on
25.12.2010 which remained under consideration and kept on
travelling from one officer of the Department to another for a
period of more than 4 years. The final bill as passed by the
Department was accepted by the contractor 'under protest' and
the same was ultimately paid on 15.10.2014. Thereafter, the
question as to - 'whether the escalation amount as claimed by the
contractor was to be deducted or not' remained under
[2023/RJJD/004202] (4 of 6) [CMA-1748/2022]
consideration with the Department and in the meanwhile, the
dispute was referred to the Sole Arbitrator. The claim was
preferred by the claimant on 22.07.2017 and that by the Union
was filed on 04.07.2017. The learned Arbitrator entered into
reference on 24.11.2017.
From an analysis of the overall facts, it is clear that by any
angle, the cause of action, if any, for the claims arose to the
claimant on 15.10.2014 when the payment of final bill was made
to him. As per the record, the claims were raised by the claimant
on 22.07.2017 i.e. within a period of 3 years of 15.10.2014. It is
clear that the dispute, if any, arose between the parties only after
the payment of final bill to the contractor i.e. on 15.10.2014. The
claims had been raised by the contractor clearly within a period of
3 years of the said date and the same were specifically within the
limitation. So far as the payment of Rs.5,94,564/- on 22.02.2019
during the arbitral proceedings is concerned, the same is clearly a
further acknowledgment of the claim of the claimant and
therefore, the same definitely gave further period of limitation to
the claimant to raise its claim qua the unpaid amount regarding
the said claim. By all means, the claim of the claimant cannot be
termed to be time barred and therefore, the finding of the learned
Court below cannot be interfered with.
The second ground has been raised regarding Claim No.2
qua the 'losses due to omission of construction of Watch Tower'
towards which, an amount of Rs.1,51,200/- with interest @9%
has been awarded by the learned Arbitrator. It has been submitted
by learned counsel for the appellant that Condition No.7 of the
agreement/General Conditions of Contract specified/authorised for
[2023/RJJD/004202] (5 of 6) [CMA-1748/2022]
variation of the work by the Accepting Officer. Therefore, the claim
qua the losses due to omission of construction of Watch Tower
could not have been awarded to the claimant. Learned counsel
submitted that during the course of execution of the work, it was
found by the Authorised Officer that the Watch Tower was not
required to be constructed and therefore, the same was directed
not to be constructed. The said act was within the power of the
Accepting Officer in terms of Condition No.7 of the contract, which
provides as under :
"The Accepting Officer, or person specifically authorized by him on his behalf, may vary by the way of addition to and/or deduction from the work so described provided that the contract sum be not thereby varied on the whole by more than percentage set out in the tender documents."
A perusal of the above condition makes it clear that the
Accepting/Authorised Officer could have varied the terms of the
contract to the extent permissible under the terms of the contract.
The said authorisation or power of the Officer is not disputed but
if, in terms of the conditions of the contract, any work is
undertaken by a contractor prior to the same being varied, he
cannot be denied the amount qua the costs incurred by him for
completion of the said amount of work. Admittedly, in the present
case, the fabrication of two Watch Towers by using 4400 Kgs steel
had already been carried out by the claimant prior to the
communication of letter dated 13.10.2008 whereby, he was
directed not to execute the work of construction of Watch Towers.
Admittedly, the letter dated 13.10.2008 was issued after a lapse
of more than 3 years from the date of commencement of the
work. So far as the fabrication of two Watch Towers is concerned,
[2023/RJJD/004202] (6 of 6) [CMA-1748/2022]
the same was recorded in the Measurement Book/Work Diary and
has also not been denied by the respondents. In view of the
admitted facts, the firm was very much entitled for payment of
costs which had already been incurred by it till that date and the
same cannot be denied to it on the basis of a letter communicated
to it after the completion of the said amount of work. Therefore,
the amount as awarded in favour of the claimant by learned
Arbitrator qua Claim No.2 after deduction of the amount equal to
the scrap value cannot be said to be in contravention of any
condition of the contract and the same has therefore, rightly been
affirmed by the learned Court below.
No other ground has been raised in the present appeal.
In view of the above observations, this Court is not inclined
to interfere with the order dated 12.05.2022 or the arbitral award
dated 29.04.2019.
The appeal being devoid of merit is therefore, dismissed.
The stay petition as well as all pending applications also
stand dismissed.
(REKHA BORANA),J (SANDEEP MEHTA),J
18-Vij/-
Powered by TCPDF (www.tcpdf.org)
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!