Citation : 2023 Latest Caselaw 3774 Raj
Judgement Date : 28 April, 2023
[2023/RJJD/006421]
HIGH COURT OF JUDICATURE FOR RAJASTHAN AT JODHPUR D.B. Civil Misc. Appeal No. 1482/2019
1. Executive Engineer, Survey and Investigation Lift Division First, IGNP, Rawatsar.
2. The State of Rajasthan through District Collector,
Hanumangarh. ----Appellants
Versus
M/s Ramewshwar Lal Manaram, Sarvodaya Basti, Behind
Vishwakarma Mandir, Bikaner. ----Respondent
For Appellant(s) : Mr. Pankaj Sharma, AAG with
Mr. Dhairyaditya Singh Rathore
For Respondent(s) : Mr. Harish Kumar Purohit with
Mr. Shashank Joshi
HON'BLE MR. JUSTICE ARUN BHANSALI
HON'BLE MS. JUSTICE REKHA BORANA
Judgment
28/04/2023
Reportable
(PER HON'BLE MS. JUSTICE REKHA BORANA)
1. The present appeal has been preferred against the order
dated 25.01.2019 passed by the Commercial Court, Jodhpur
(hereinafter referred to as 'the learned Court below') in Civil Misc.
'A' Case No.46/2018 (NCV no.32/2018) whereby the objections
under Section 34 of the Arbitration and Conciliation Act, 1996 (for
short 'the Act of 1996') preferred by the appellant-State against
the award dated 04.12.2014 passed by learned Arbitrator have
been rejected. Vide the award, the learned Arbitrator had
proceeded on to pass an award for an amount of Rs.25,42,748/-
qua price escalation in favour of the applicant-firm with interest @
[2023/RJJD/006421] (2 of 17) [CMA-1482/2019]
10% per annum and has proceeded on to reject the counter-claim
as preferred by the non-applicants State Department.
2. The facts of the case are as under :
An agreement was entered into between firm M/s
Rameshwar Lal Manaram and the State for "Construction work of
pumping station 3rd at Sahwa K.M. 63.200". Vide the work order
dated 27.10.1997, work valuing to Rs.1,41,52,086/- was awarded
to the applicant-firm and the stipulated period for completion of
the work was 18 months. During the progress of work, an
additional work valuing to Rs.69,17,847/- was also allotted to the
firm. The complete work could not be completed within the
stipulated period of 18 months and was infact completed on
05.04.2003. The firm then applied for extension of time and vide
order dated 06.11.2003, time extension up to the date of
completion i.e. 05.04.2003 was granted by the Department with a
penalty of 0.10% of the tender amount. In the circumstances, the
firm raised a claim for an amount of Rs.25,42,748/- along with
interest qua price escalation. When the request/claim of the firm
was not acceded to, it prayed for the dispute to be referred to
arbitration and on its application under Section 11 of the Act of
1996, vide order dated 08.11.2013, sole arbitrator was appointed
for adjudication of the dispute.
3. Before the learned Arbitrator following two claims were
raised by the applicant-firm :
(i) Rs.25,42,748/- qua price escalation and
[2023/RJJD/006421] (3 of 17) [CMA-1482/2019]
(ii) Rs.22,37,618/- qua interest on the principal amount from
21.09.2005 to 20.01.2014 + pendente lite & future interest.
4. In response to the claim of the firm, a counter-claim for an
amount of Rs.16,24,860/- was raised by the State Department
qua the damages/loss caused to the State due to delay in
execution of the work which was later amended to
Rs.1,59,45,028/-.
5. On basis of the pleadings as made by both the parties, the
following nine issues were framed by the learned Arbitrator :
"1. Whether the applicant firm is a registered partnership firm or not ?
.....Applicant
2. Whether the applicant firm did not give the pro-rate progress as provided under clause-2 of the agreement ? If not then what is effect of it on the claim ?
.....Non-applicants
3. Whether the applicant failed to complete the work within stipulated period or extended period as required under clause 45 and 45-A of the agreement ?
.....Non-applicants
4. Whether the respondents had allowed the price escalation benefit to the applicant for the period from 09.11.1997 to 08.11.2000. If yes then what is effect thereof ?
.....Applicant
5. Whether the applicant had given the consent for the statement of time extension sent by the Engineer In charge to the state government for extension of time ?
.....Non-applicants
6. Whether, the nominal penalty dis-entitled to the applicant for benefit of price escalation under clause-45 and 45-A of the agreement ?
.....Non-applicants
7. Whether the applicant is liable to pay the damages to the respondents as claimed by the respondents in its counter claim ?
.....Non-applicants
[2023/RJJD/006421] (4 of 17) [CMA-1482/2019]
8. Whether the applicant is entitled to get the interest on the due amount ? If yes, then for what period and on what rate ?
.....Applicant
9. Relief ?"
6. Learned Arbitrator proceeded on to decide all the issues
except issue no.4 in favour of the applicant-firm and consequently,
passed the award as above mentioned in favour of the applicant-
firm. Aggrieved against the said award in favour of the applicant
and rejection of its counter-claim, the State Department preferred
objections under Section 34 of the Act of 1996 before the
Commercial Court, Jodhpur, which have also been rejected vide
order impugned dated 25.01.2019, against which the present
appeal has been preferred.
7. Learned Additional Advocate General Shri Pankaj Sharma
appearing for the appellant-State submitted that the learned Court
below has erred in rejecting the objections as preferred by the
State in a wholly cursory manner without even going into the facts
of the case and without analysing the issues in question. Learned
AAG submitted that the learned Court below has not even dealt
with the objections as raised by the Department and therefore,
the order impugned deserves to be set aside.
8. So far as the impugned award is concerned, learned AAG
submitted that the award qua price escalation has been granted in
favour of the firm by learned Arbitrator in terms of clause 45 of
the agreement whereas a bare reading of clause 45 would make it
clear that the same would not even apply in the present matter.
Learned counsel submitted that clause 45 comprised of 3 implied
[2023/RJJD/006421] (5 of 17) [CMA-1482/2019]
conditions : firstly, the stipulated period of contract ought to be
more than 12 months; secondly, the valuation of the work ought
to be above Rs.1 cr. and thirdly, the work ought to have been
completed within the stipulated/extended period without any delay
on part of the contractor. Herein, admittedly, the delay of 55 days
was attributable to the contractor and therefore, all the conditions
of clause 45 having not been fulfilled, the clause would not apply.
Learned counsel further submitted that the basic and the most
essential issue as to whom the delay in completion of the work
was attributable, was not even framed by the learned Arbitrator
and no finding on this specific aspect has been recorded by the
learned Arbitrator. Therefore, in absence of a specific finding as to
whom the delay was attributable, clause 45, which pre-supposes
that no delay is attributable to the contractor, could not have been
held to be applicable.
9. Next ground raised by learned counsel for the appellants is
that the burden to prove the issues had been wrongly placed by
the learned Arbitrator on the non applicants-State as the burden
to prove Issue No.3 (framed in negative) that the firm completed
the work within the stipulated or the extended period was totally
upon the applicant-firm and the burden to prove the same could
not have been placed on the non applicant-Department. It has
been submitted that the onus upon a party cannot be to prove the
negative and therefore, the finding by the learned Arbitrator that
the non-applicants failed to prove that the applicant-firm did not
complete the work within the stipulated/extended period is totally
[2023/RJJD/006421] (6 of 17) [CMA-1482/2019]
contrary to the basic principles of law as well as the material
available on record.
10. Learned counsel further submitted that it was an admitted
fact on record that qua the delay of 55 days attributable to the
contractor, a penalty @ 0.10% was imposed on the firm and the
same was never challenged. Meaning thereby, the time extension
was granted with a penalty and therefore also, clause 45 & 45-A of
the agreement would not apply. Learned counsel submitted that
the award is therefore, patently illegal and strictly in violation of
Section 28(3) of the Act of 1996. In support of his contentions,
learned counsel relied upon the Hon'ble Apex Court judgments in
the matters of (i) Oil & Natural Gas Corporation Ltd. Vs. SAW
Pipes Ltd., (2003) 5 SCC 705; (ii) Murlidhar Aggarwal and
Another Vs. State of Uttar Pradesh and Others, (1974) 2
SCC 472; (iii) Oil and Natural Gas Corporation Limited Vs.
Western GECO International Limited, (2014) 9 SCC 263 and
(iv) State of Chhattisgarh and Ors. Vs. Sal Udyog Private
Limited, AIR 2021 SC 5503.
11. Per contra, Shri Harish Purohit, learned counsel appearing
for the respondent contractor/firm submitted that the award as
passed by the learned Arbitrator is perfectly in consonance with
the material available on record in so far as it was clearly proved
on record that the stipulated period for completion of work was 18
months i.e. 546 days. The work was completed in 1972 days with
a delay of 1168 days out of which only 55 days was attributable to
the contractor and the complete remaining delay was admittedly
attributable to the State Department. Moreover, it is admitted on
[2023/RJJD/006421] (7 of 17) [CMA-1482/2019]
record that an additional work amounting to Rs.69,17,907/- was
awarded to the contractor and therefore, 267 extra days for
completion of work ought to have been granted to the firm qua
the additional work. Consequently, the stipulated period for
completion of work ought to be 813 days (546 + 267) and after
deducting 1168 days from 1972 days, the calculation comes out to
be 804 days in which the work has been completed. Meaning
thereby, 813 days were available to the firm for completion of
work against which it has completed the work in 804 days.
Therefore, by any extent, it cannot be held that the work was
completed with a delay which could even be considered to be
attributable to the firm. Therefore, learned Arbitrator rightly held
the firm to be entitled for the price escalation amount and the
objections against the award as passed by the learned Arbitrator
have rightly been rejected by the Commercial Court.
12. Learned counsel further submitted that the findings as
reached by the learned Arbitrator were based on documents of the
Department itself wherein it was specifically admitted that the
delay of 1168 days was attributable to the State Department and
an additional time of 267 days ought to have been granted to the
firm for completion of the work. Therefore, the Department being
bound by its own documents cannot urge that the reliance of the
learned Arbitrator on the said documents was bad. Learned
counsel also urged that none of the objections as raised, fell within
the purview of Section 34 of the Act and therefore too, their
rejection being perfectly valid, deserves to be upheld.
[2023/RJJD/006421] (8 of 17) [CMA-1482/2019]
13. In rejoinder, learned counsel for the appellants submitted
that the documents i.e. time extension application and the
hindrance statement as relied upon by the learned Arbitrator were
the internal communications between the officers of the
Department in the nature of recommendation and the same were
not the orders which could not have been considered to be a piece
of evidence and therefore, could not have been relied upon by the
learned Arbitrator to hold that the contractor was not responsible
for the delay.
14. Heard learned counsel for the parties and perused the
material available on record.
15. Before adverting into the adjudication on the grounds as
raised, it is relevant to note that an application under Order 41
Rule 27, CPC has been preferred in the present appeal by the
State Department with a prayer to take certain documents on
record annexed as Annexure-A/1 along with the application. The
said documents are five letters written by the Department to the
firm during progress of the work whereby the firm was called upon
to submit the price escalation bills, if any. It has been submitted
that inspite of being called upon, the firm failed to submit any bill
qua price escalation at the relevant point of time and therefore, its
claim qua price escalation could not have been entertained by the
learned Arbitrator subsequently.
16. Besides the above application, an application for amendment
of the memo of appeal has also been preferred with the
submission that as certain documents have been prayed to be
taken on record, the pleadings qua the said documents needs to
[2023/RJJD/006421] (9 of 17) [CMA-1482/2019]
be made in the present appeal and therefore, the appellants be
permitted to amend the present memo of appeal.
17. During the course of the arguments, learned AAG did not
press both these applications and therefore, the same are
dismissed as not pressed.
18. Coming on to the ground as raised by learned AAG to the
effect that clause 45 has wrongly been held to be applicable by
the learned Arbitrator, there is no dispute regarding the first two
conditions of the stipulated period of contract being more than 12
months and valuation of the work being above Rs.1 crore. So far
as the third condition is concerned, it stipulated that the work
ought to have been completed within the stipulated/extended
period without any delay on part of the contractor. The issue
whether there was any delay on part of the contractor in
completion of the work has been dealt by the learned Arbitrator
while deciding Issue No.3 and it has been specifically held that
there was not a single day's delay which could be attributable to
the contractor. The said finding of the learned Arbitrator is based
on the letters dated 01.10.2003 (Ex.20) and 06.10.2003 (Ex.5)
whereby it has been specifically observed by the Superintending
Engineer as well as the Chief Engineer that in view of the
additional work allotted to the firm, an extra time of 267 days
ought to have been granted for completion of the work and on
computing the said additional days, the delay of not even a single
day could be attributable to the contractor. In both these letters, it
has also been specifically observed that the State Department did
not incur any loss because of the delay in completion of the work.
[2023/RJJD/006421] (10 of 17) [CMA-1482/2019]
In view of the above two letters exhibited on record, the learned
Arbitrator decided in favour of the applicant and held that clause
45 would be applicable and the contractor would be entitled to the
price escalation amount in terms of the said clause. Letter dated
06.10.2003 (Ex.5) whereby the time extension case was
forwarded/recommended read as under :
"QeZ }kjk mDr ck/kkvksa ds dkj.k dk;Z iw.kZ djus esa dqy 1972 fnol
dk le; fy;k x;k tcfd vuqcU/k ds vuqlkj dk;Z 546 fnu esa iw.kZ djuk
FkkA vuqcU/k vuqlkj :i;s [email protected]& dk dk;Z vkoafVr Fkk ftls 546 fnu
esa iw.kZ djuk Fkk ysfdu QeZ ls :i;s [email protected]& dk vfrfjDr dk;Z Hkh
djok fy;k x;kA mDr vfrfjDr dk;Z ds fy;s QeZ dks 267 fnol dk le;
vkSj fn;k tkuk pkfg;s FkkA bl izdkj dk;Z 546 + 267= 813 fnol esa
iw.kZ djuk FkkA dk;Z esa dqy 1168 fnol dh ck/kk mRiUu gqbZ gS & vr % QeZ
}kjk dk;Z 1972 - 1168 = 804 fnol esa iw.kZ fd;k gS tks fd mfpr gSA
mijksDr of.kZr ck/kk,a mfpr ,oa Bsdsnkj ds fu;a=.k ls ckgj gSA v/kh{k.k
vfHk;[email protected]/k'kk"kh vfHk;Urk us ;g izekf.kr fd;k gS fd dk;Z nsjh ls iw.kZ gksus
esa jkT; ljdkj dks fdlh izdkj dh gkfu ugha gqbZ gSaA"
(Emphasis supplied)
19. Relying upon the above documents, the learned Arbitrator
concluded his findings on Issue No.3 as under :
"I have considered the arguments raised by both the parties and perused the documentary evidence produced in this regard. According to the reply given by D.W.-1 in his cross examination it is admitted fact that the contents of the said letters Ex-5 and Ex-20 are correct and there is no averment of 55 days delay attributable on the part of the contractor in the said letters. In these circumstances, I am agree with the arguments of the applicant that he had completed the said work within 804 days excluding the delay of 1168 days attributable on the part of the government, while, the said work had to be completed within 813 days. Under this issue the non
[2023/RJJD/006421] (11 of 17) [CMA-1482/2019]
applicants have to prove that the applicant failed to complete the said work within stipulated period or within extended period. In this respect, it is an admitted fact that the state government have granted the time extension up to 05.04.2003. Thus, the extended period of the said work became up to 05.04.2003. There is no dispute between the parties that the work had been completed up to 05.04.2003. In this respect, the non applicants argued that the government extended time up to 05.04.2003 but with penalty of 0.10% of tender amount, which disentitled the applicant to get the benefit of price escalation. As regard the extended period, it is an admitted fact that the government had extended the time of the said work up to 05.04.2003, therefore, there is no dispute between the parties in this regard. As regard the effect of the penalty, the separate issue no.06 has been framed, therefore, I will discuss this point under issue no.06. In conclusion I hold that the non applicants have failed to prove that the applicant had not completed the said work within stipulated period or extended period. But the applicant completed the said work within extended period. Further, I hold that the applicant completed the said work within 804 days excluding the delay of 1168 days attributable on the part of the government. It is an admitted fact that said work had to be completed within 813 days while the applicant completed the said work 9 days before the stipulated period. Thus, the non applicants have failed to prove this issue in their favour. Hence, the issue no.3 is decided against the non applicants."
(Emphasis supplied)
20. It is admitted on record that the total delay caused in
completion of work was 1168 days out of which delay of only 55
days was attributable to the contractor. The application for
extension of time along with hindrance statement as
recommended by the Executive Engineer to the higher authorities
had been placed on record by the applicant as Exhibit-A-16. A
detailed and day-wise statement of delay caused and the reasons
for such delay have been mentioned in the application. For ready
reference, reproduction of the said details is made as under :
[2023/RJJD/006421] (12 of 17) [CMA-1482/2019]
Period S.No Hindrance From To Days
1. Hkwfe dk eqvkotk u feyus ds dkj.k fdlkuksa }kjk 11-11-97 5-12-97 26 days dk;Z esa ck/kk igqapkus ds dkj.k
2. foHkkx }kjk ikuh rFkk LVhy miyC/k u djokus ds 21-1-98 11-3-98 50 days dkj.k
3. Earthing arrangement dk dk;Z u gksus ds 12-3-98 30-4-98 50 days dkj.k
4. MªkbZax esa ifjorZu ds dkj.k 1-5-98 21-5-98 21 days
5. vkaf/k;ksa ls jkLrs can gksus ls eSfVjh;y dh dSfjt u 1-6-98 15-7-98 45 days gks ikus ds dkj.k
6. fMyhojh VSad dh Mz̀kbZax Qkbuy gksus ls fMyhojh 1-8-98 9-10-98 70 days VSad ds fu"kku u feyus ds dkj.k
7. foHkkx }kjk ikuh miyC/k u djokus ds dkj.k 7-12-98 16-12-98 10 days
8. dsUnzh; m|ksx'kkyk [k.M }kjk Vsªl jsd ds pSuy 30-12-98 3-1-99 5 days fQV u djus ds dkj.k
9. foHkkx }kjk ikuh miyC/k u djokus ds dkj.k 18-4-99 15-5-99 28 days
10. foHkkx ds ikl L.O.C. dk vHkko gksus ls iwjk 1-10-99 30-11-99 46 days Hkqxrku u feyus ds dkj.k ¼/kheh izxfr] 75 izfr'kr ck/kk½ 61x75/100=46 fnu
11. deZpkjh gM+rky dh otg ls batu can gksus ls ikuh 22-1-2000 28-2-2000 38 days miyC/k u gksus ds dkj.k
12. vkaf/k;ksa ls jkLrs can gksus ls eSfVjh;y dh dSfjt u 16-4-2000 30-8-2000 137 days gks ikus ds dkj.k
13. foHkkx ds ikl L.O.C. u gksus ds dkj.k 1-9-2000 31-10- 61 days
14. [k.Mh; LVksj esa lhesUV miyC/k u gksus ds dkj.k 1-11-2000 30-6-2001 242 days
15. vkaf/k;ksa ls jkLrs can gksus ls eSfVjh;y dSfjt u gks 1-7-2001 11-8-2001 42 days ldus rFkk foHkkx }kjk ikuh miyC/k u djokus ds dkj.k
16. foHkkx ds ikl L.O.C. dk vHkko gksus ds dkj.k 1-12-2001 11-5-2002 122 days Hkqxrku iwjk u feyus ds dkj.k ¼/kheh izxfr 75 izfr'kr ck/kk 162x75/100=122 fnu½
17. vkaf/k;ksa ls jkLrs can gksus ds dkj.k eSfVjh;y dh 12-5-2002 8-9-2002 120 days dSfjt u gks ldus ds dkj.k
18. Bsdsnkj }kjk /kheh xfr ls dk;Z djus ds dkj.k 55 days Total 1168 days
21. The recommendation as made by the concerned Executive
Engineer on the above mentioned application for extension of time
was as under :
"Since the hindrance statement stated by contractor is partially genuine and beyond the control of contractor and department. Initially the land owners
[2023/RJJD/006421] (13 of 17) [CMA-1482/2019]
objected the work as land compensation was not given to them. After that drawings of pumping station was revised due to change in water allowance as the decision of state govt. Further in summer season heavy wind storms are common in this area due to which the roads generally get blocked and carriage of material becomes difficult. Many times supply of water is also interrupted. So in view of these reasons the hindrance statement is genuine. So extension in time limit up to 5-4-2003 is recommended with a token penalty of Rs.10000/- only.
There is no loss to the deptt. In delayed completion of the work."
(Emphasis supplied)
22. A bare perusal of the above documents i.e. the hindrance
statement and the recommendation of the concerned Executive
Engineer relied upon by the learned Arbitrator leaves no doubt
that the finding as reached by the learned Arbitrator is totally in
consonance with the material available on record. In view of the
specific admission of the Department itself that the work was
delayed due to the reasons beyond control of the contractor or the
State Department, the learned Arbitrator or the Commercial Court
could not have reached to any other conclusion contrary to the
said admissions of the Department itself. In the specific opinion of
this Court firstly, there was no other conclusion/view possible in
the present matter and secondly, even if any other/second
conclusion/view is possible, as is the settled proposition of law,
the same cannot be substituted in place of the conclusion/view as
arrived/taken by the learned Arbitrator.
23. Consequently, the finding of the learned Arbitrator that
clause 45 of the agreement would be applicable to the present
matter and the contractor is entitled for the price escalation
[2023/RJJD/006421] (14 of 17) [CMA-1482/2019]
amount and the rejection of the objections as raised by the State
qua the said finding by the Court below does not deserve any
interference by this Court.
24. So far as the ground raised by the learned AAG that the
burden to prove that the firm had not completed the work within
the stipulated or the extended period was wrongly placed on the
State is concerned, it is clear on record that the claim qua price
escalation as raised by the firm was denied by the State on the
ground that the work was not completed within the stipulated
period and therefore, clause 45 would not apply. It is the basic
proposition of law that a party who pleads a fact is under an onus
to prove the same. The fact of the firm having not completed the
work within the stipulated period had been pleaded/averred by the
respondent-Department and therefore, the onus definitely was on
it to prove the same. The case of the firm was that it had
completed the work within 804 days which was within the period
of 813 days, the period which ought to have been
computed/stipulated for completion of the original plus the
additional work allotted to the firm. It was the defence of the
State that the stipulated period was 546 days and the firm did not
complete the work within the said period. Therefore, the onus to
prove the said fact was rightly placed on the respondent-State
who pleaded the same. Hence, the ground as raised by the
learned AAG cannot be held to be tenable.
25. So far as the imposition of the penalty on the firm having not
been challenged is concerned, the same cannot be also of any
consequence as firstly, even if it is assumed that there was some
[2023/RJJD/006421] (15 of 17) [CMA-1482/2019]
delay in completion of the work on part of the firm, it was
admittedly a delay of 55 days only. The total delay in completion
of work in the present matter was of 1168 days out of which only
55 days were held to be attributable to the firm even by the
Department. As held in P.M. Paul Vs. Union of India; AIR 1989
SC 1034, "Escalation" is a normal incident arising out of gap of
time in this inflationary age in performing any contract. The
purpose why a price adjustment/escalation clause is essential to
be incorporated in agreements and why the said amount deserves
to be granted was discussed by the Hon'ble Apex Court in the case
of National Highway Authority of India Vs. M/s
Progressivemvr (JV); (2018) 14 SCC 688 and it was observed
as under :
".....After all, what is the purpose of giving price adjustment ? The Clause relating to price adjustment indicates that certain component which go into the execution of the projects like labour component, cement component, steel component, plant and machinery and spares component, bitumen component etc. may not remain static insofar as their price is concerned. There is a possibility that from the date when the price of these components was quoted by the contractor in his bid, there may be increase or decrease in the said price from time to time during the execution of the contract. It is for this reason, Clause relating to price adjustment is provided so as to give effect to the rise or fall in the costs to the contractor."
26. Admittedly, in the present matter, the delay of 1113 days
was attributable to the Department and the firm could not have
been denied the price escalation qua the said period. Even if it is
held that the delay of 55 days was attributable to the firm, how
could it have been denied the price escalation qua the huge period
of 1113 days, the delay for which it could not have been held to
[2023/RJJD/006421] (16 of 17) [CMA-1482/2019]
be responsible. In Food Corporation of India Vs. A.M. Ahmed
and Company and Others; (2006) 13 SCC 779, the Hon'ble
Apex Court specifically held that even in absence of an escalation
clause in contract, the Arbitrator is within his jurisdiction to award
escalation charges if the delay is not attributable to the contractor
himself. It being an admitted case on record that the delay of
1113 days was on part of the Department, the award of the claim
qua price escalation to the contractor was a necessary corollary
and the award of the same by the learned Arbitrator cannot
therefore be termed to be perverse or illegal. The same therefore
does not deserve any interference by this Court.
27. The ground regarding the Commercial Court having cursorily
rejected the objections as raised by the Objector State also does
not find any merit with this Court as a bare perusal of the order
dated 25.01.2019 makes it clear that the Commercial Court has,
after thoroughly discussing the ambit of Section 34 of the Act and
after appreciating the findings of the learned Arbitrator with the
available scope, reached to well reasoned conclusions on the
objections. The Court below rightly held that none of the
objections as raised, fell within the purview of Section 34 of the
Act and therefore, the award impugned did not deserve any
interference.
28. So far as the judgments relied upon by learned counsel for
the appellants are concerned, there is no dispute on the settled
proposition of law that failure on the part of the Arbitrator to
decide in accordance with terms of the contract governing the
parties, would certainly attract the "Patent illegality ground". There
[2023/RJJD/006421] (17 of 17) [CMA-1482/2019]
is no dispute even on the proposition of law that the award which
is on the face of it, patently in violation of statutory provisions
cannot be said to be in public interest and such award would
definitely be termed to be patently illegal, thereby attracting the
ground of being against the "public policy of India". But then, the
question is whether the said proposition of law would be applicable
to the present matter. As observed in the preceding paras, the
findings as arrived by the learned Arbitrator in the present matter
are neither in breach of any of the conditions of the agreement
nor are they contrary to the material available on record. The
findings are rather based on the specific admissions of the
Department itself. Therefore, the same cannot, in terms of any
provision of law, be termed to be perverse, patently illegal or
against the fundamental policy of Indian law. The judgments as
cited therefore, have no application to the present matter.
29. In view of above analysis, this Court does not find any
ground to interfere with the award dated 04.12.2014 as passed by
the learned Arbitrator and the order dated 25.01.2019 passed by
the Commercial Court, Jodhpur. The present appeal being devoid
of merits, is hence dismissed.
(REKHA BORANA),J (ARUN BHANSALI),J
Vij/-
Powered by TCPDF (www.tcpdf.org)
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!