Citation : 2022 Latest Caselaw 6065 Raj/2
Judgement Date : 7 September, 2022
HIGH COURT OF JUDICATURE FOR RAJASTHAN
BENCH AT JAIPUR
S.B. Arbitration Application No. 58/2020
M/s Kishan Sahay Meena, 6MB-280, Indra Gandhi Nagar,
Jagatpura, Jaipur (Raj.). 302017, Through Its Proprietor Sh.
Kishan Sahay Meena.
----Applicant
Versus
Union Of India, Through The Executive Engineer, Jaipur Central
Devision-II, CPWD, A.G. Colony, Bajaj Nagar, Jaipur.
----Respondent
For Applicant(s) : Mr. Dinesh Kumar Mishra
For Respondent(s) : Mr. Anand Sharma with
Mr. Namandeep Singh
HON'BLE MR. JUSTICE PANKAJ BHANDARI
Order
RESERVED ON :: 31/08/2022
PRONOUNCED ON :: 07/09/2022
1. The applicant has filed this arbitration application under
Section 11(6) of the Arbitration and Conciliation Act, 1996 seeking
appointment of an arbitrator.
2. It is pleaded in the arbitration application that a contract was
entered into between the applicant and the non-applicant for
construction of office building and boundary wall for Income Tax
Department at Dausa. The contract was awarded to the applicant
vide letter of award dated 23.10.2013. It is also pleaded that the
work in question was completed on 20.09.2015 and the same was
handed-over to the non-applicant. The bills of the applicant have
not been cleared. The applicant complied with the conditions of
the agreement and when the non-applicant did not accede to the
(2 of 6) [ARBAP-58/2020]
request of appointment of an arbitrator, the applicant was left with
no other alternative, but to approach the Court for appointment of
an arbitrator.
3. In reply to the said application, the non-applicant has stated
that the claim was not filed within limitation as per the General
Conditions of the Contract and thus, the applicant is not entitled to
have an arbitrator appointed.
4. It is contended by the counsel for the applicant that the
applicant has complied with the conditions provided in the
agreement. It is also contended that as per the terms of Clause 25
of the agreement, the applicant initially applied to the Executive
Engineer and when the Executive Engineer did not pass any order,
the applicant applied to the Superintending Engineer vide letter
dated 02.06.2019. It is further contended that when the
Superintending Engineer also did not pass any orders, the
applicant gave a notice to the Chief Engineer on 06.08.2019 to
refer the dispute to the Dispute Resolution Committee (hereinafter
referred to as "DRC"). Another notice dated 01.11.2019 was given
to the Chief Engineer to refer the matter to the DRC, but the Chief
Engineer vide its letter dated 04.06.2020 rejected the prayer
stating therein that the claims are time-barred as per Clause 25 of
the General Conditions of the Contract.
5. Counsel for the applicant has place reliance on Sagar
Constructions through Shri Subash Chand Saini Versus
Government of NCT of Delhi: ARB.P. No.856/2021 decided by
the Delhi High Court on 06.10.2021. Reliance is also placed on
M/s. Uttarakhand Purv Sainik Kalyan Nigam Limited Versus
Northern Coal Field Limited: Special Leave Petition (C)
No.11476 of 2018 decided by the Apex Court on 27.11.2019.
(3 of 6) [ARBAP-58/2020]
Reliance is further placed on Bharat Sanchar Nigam Ltd. & Ors.
Versus Nortel Networks India Pvt. Ltd.: (2021) 5 SCC 738 and
M/s. Rakesh Enterprises Versus Union of India: S.B. Arbitration
Application No.100/2019 decided by a Coordinate Bench of this
Court on 12.02.2021.
6. Counsel for the non-applicant has placed reliance on Simpark
Infrastructure Pvt. Ltd. Versus Jaipur Municipal Corporation: 2013
(1) WLN 111.
7. I have considered the submissions and have carefully gone
through the material on record.
8. The only dispute, which has been raised by the non-
applicant, is that the claim was not raised within the time provided
under the General Conditions of the Contract and the same is
time-barred. From perusal of the record, it is evident that the
applicant-claimant has been writing letters to the Executive
Engineer from 03.01.2017 to clear his claim. He had also given a
notice for demand of justice on 23.02.2017. A notice was also
given to the Director General, CPWD on 20.03.2017, yet another
letter was written to the Executive Engineer on 06.10.2017 and
further, letters were written to the Executive Engineer (Civil) on
20.03.2018 and a reminder was also sent on 30.04.2018 & third
and final reminder was also given to the Executive Engineer on
12.10.2020. Thereafter, the applicant approached the
Superintending Engineer vide letter dated 02.06.2019. The
applicant also wrote letters dated 06.08.2019 and 01.11.2019 to
the Chief Engineer to constitute the DRC, but no heed was paid to
the letter and finally vide letter dated 04.06.2020, the claim was
rejected by the non-applicants being barred as per Clause 25 of
the General Conditions of the Contract.
(4 of 6) [ARBAP-58/2020]
9. The Apex Court in M/s. Uttarakhand Purv Sainik Kalyan
Nigam Limited Versus Northern Coal Field Limited (supra) set
aside the order of the High Court whereby the arbitration
application was dismissed being barred by law. The Apex Court
held that it is for the arbitrator to decide the issue of limitation.
10. In Sagar Constructions through Shri Subash Chand Saini
Versus Government of NCT of Delhi (supra), the Delhi High Court
held as under:
"43. After the 1997 amendment to Section 28 of the Indian Contract Act, 1872, not only the curtailment of the period of limitation is void, but also the extinction of right, if sought to be brought by the agreement within a specific period, which period is less than the period of limitation prescribed for the suit under the Contract in question, is also rendered void. In other words, after the amendment to Section 28 of the Indian Contract Act, 1872 by Act 1 of 1997, the distinction between curtailing of the period of limitation and extinction of the right itself, after the specified period, no longer exists."
It is also held by the Apex Court as under:
"14. The period of limitation for the disputes will commence from the date of cause of action till invocation of the agreement to refer the disputes to arbitration. The question whether the disputes are within the period of limitation falls within the jurisdiction of the Arbitral Tribunal and unless it is, ex facie, apparent that the disputes are barred by limitation, the parties are required to be referred to arbitration (See -Vidya Drolia & Ors. v Durga Trading Corporation: (2021) 2 SCC 1)."
11. In Bharat Sanchar Nigam Ltd. & Ors. Versus Nortel Networks
India Pvt. Ltd. (supra), the Apex Court held that period of
limitation for filing an application under Section 11 of the Act of
1996 would be governed by Article 137 of the First Schedule of
the Limitation Act. The period of limitation will begin to run on the
(5 of 6) [ARBAP-58/2020]
date when there is a failure to appoint an arbitrator. The judgment
referred to by the counsel for the non-applicant Simpark
Infrastructure Pvt. Ltd. Versus Jaipur Municipal Corporation
(supra) would not apply to the facts of the present case as in that
case the dispute was not resolved amicably in accordance with the
terms of the agreement and therefore, the application for
appointment of an arbitrator was rejected by the Court. However,
in the present case in hand, since the applicant has written
various letters to the Executive Engineer, then to the
Superintending Engineer and Chief Engineer and the DRC was not
constituted and thereafter, the applicant has approached to the
Court. It cannot be said that he had not tried to amicably resolve
the dispute in terms of the General Conditions of the Contract.
12. The Delhi High Court in Sagar Constructions through Shri
Subash Chand Saini Versus Government of NCT of Delhi (supra)
has held that in terms of Section 28 of the Indian Contract Act,
the period of limitation cannot be curtailed and the rights of the
parties cannot be extinct by an agreement. As per Section 45(3)
of the Indian Contract Act, the Court has power to condone the
delay in matters pertaining to arbitration. Thus, I am of the
considered view that the reasons assigned in rejecting the prayer
for appointment of an arbitrator vide letter dated 04.06.2020
cannot be accepted for the very reason that the time cannot be
curtailed in view of Section 28 of the Indian Contract Act. The
arbitration application therefore deserves to be and is accordingly,
allowed and Mr. Justice S.K. Keshote (Retired), 10 Eden Garden,
Flat No.302, Bajaj Nagar Enclave, Near Gandhi Nagar Railway
Station, Jaipur, is appointed as an arbitrator to decide the dispute.
(6 of 6) [ARBAP-58/2020]
13. The appointment of the sole arbitrator is subject to the
declarations being made under Section 12 of the Arbitration and
Conciliation Act, 1996 with respect to the independence and
impartiality, and the ability to devote sufficient time to complete
the arbitration within prescribed period.
14. Accordingly, arbitration application stands allowed. The
arbitrator shall be entitled to lay down fees as provided under
Manual of Procedure for Alternative Disputes Resolution, 2009 as
amended from time to time.
15. Registry is directed to intimate Mr. Justice S.K. Keshote
(Retired) and obtain his formal consent.
16. The observations made herein-above are only for the
purpose of deciding the present application and the same will not
disentitle the parties to raise all valid objections before the learned
Arbitrator and the Arbitrator will be free to dispose the said
objection without being influenced by the observations made by
this Court.
(PANKAJ BHANDARI),J
SUNIL SOLANKI /PS
Powered by TCPDF (www.tcpdf.org)
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!