Monday, 18, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

M/S Time Technoplast Ltd vs Rajasthan Urban Infrastructure ...
2022 Latest Caselaw 158 Raj/2

Citation : 2022 Latest Caselaw 158 Raj/2
Judgement Date : 7 January, 2022

Rajasthan High Court
M/S Time Technoplast Ltd vs Rajasthan Urban Infrastructure ... on 7 January, 2022
Bench: Sameer Jain
       HIGH COURT OF JUDICATURE FOR RAJASTHAN
                   BENCH AT JAIPUR

              S.B. Civil Writ Petition No. 21083/2019

M/s Time Technoplast Ltd., A Public Limited Company, Having
Registered Office At 102, First Floor, Center Point, Somnath-
Daman Road, Somnath, Dabhej, Nani Daman, Daman (Ut)-
396210 Through Its Authorized Signatory Mr. Ashok Kumar
Verma, Deputy General Manager, Marketing, Jaipur.
                                                                  ----Petitioner
                                   Versus
Rajasthan Urban Infrastructure Development Project (R.u.i.d.p.),
Avs Building, Jawahar Circle, Jln Marg, Jaipur Through Its Project
Director.
                                                                ----Respondent

For Petitioner(s) : Mr. H.V. Nandwana through VC For Respondent(s) : Mr. Lokendra Singh Shekhawat through VC

HON'BLE MR. JUSTICE SAMEER JAIN

Order

07/01/2022

1. By way of present writ petition, the petitioner has challenged

order dated 13.11.2018 passed by respondent RUIDP, whereby in

ex-parte manner, the petitioner company has been debarred/

banned/ disqualified from supplying high density Polythylene

(HDPE) pipes manufactured by the petitioner company. No time

limit has been fixed by the respondent and the ban is for unlimited

period as a blanket ban, resulting in permanently debarring the

company from supplying HDPE pipes manufactured by it.

2. It is submitted that the petitioner company is a Public Ltd

company and approved by Bureau of Indian Standard (BIS). It is further

submitted that the products manufactured by the petitioner company

(2 of 4) [CW-21083/2019]

are being used by over 200 companies of India and some of the Asian

Companies ever since 1992.

3. The submission of petitioner company is that one contract was

entered with Larsen and Turbo, wherein, HDPE pipes were required for

length of about 3.21 Km. They were approved suppliers to Larsen and

Turbo. They have made requisite inspection. Third party inspection was

also carried in addition to L&T. Pipes were supplied in the year 2016 and

they remained in open, therefore, there were some cracks and they

were not met with the required specification.

4. Per contra, counsel for the RUIDP submits that the proceedings

were carried out with due process of law, expert team has conducted

audit, samples of pipes were sent to the third party expert laboratory

who has given a report which is on record that low grade material was

used and the results of the laboratory specifies that the supply was not

of specified benchmark. The petitioner project was pertaining to sewage

and water supply for the District of Pali any supply not meeting out the

required specification can be fatal for health and against public interest.

5. The counsel for the petitioner, in support of his claim that the

order is violative of principles of natural justice and not legal, just

and proper has relied upon the judgments of Hon'ble Apex Court

namely (2021) 2 SCC 551: UMC Technologies Private

Limited Vs. Food Corporation of India & Anr. and (2014) 14

SCC 731: Kulja Inustries Limited Vs. Chief General

Manager, Western Telecom Project Bharat Sanchar Nigam

Limited & Ors. wherein, it was held that notice is pre-requisite

for blacklisting and principle of natural justice should be followed.

6. On perusal of records of the writ petition, submissions

advanced by both the respective counsels and judgments cited at

bar it is no doubt true that the impugned order dated 13.11.2018

(3 of 4) [CW-21083/2019]

was passed in violation of principles of natural justice, a blanket

ban of permanent nature was imposed against the petitioner

company without affording them any notice and opportunity of

hearing.

7. On this account alone, the impugned order dated 13.11.2018

is liable to be set-aside. But on the contrary we cannot ignore the

fact that the respondents are into works of public interest and

infrastructure development, any low grade supply, if it is alleged,

can be fatal for the common public wherein there will be loss not

only of revenue but may affect the health of the citizens at large.

It is also noted that vide order dated 10.12.2019 by way of

interim order, the Hon'ble Court had modified the operation of the

order dated 13.11.2018 restricting the ban to the extent of RUIDP.

8. This Court makes the said order dated 10.12.2019 as

absolute and set aside the remaining portion of impugned order

dated 13.11.2018, for the time being till the disposal of the

following proposal which was accepted by both the counsels

appearing for the respective parties.

9. That by 15th of February, 2022 a show cause notice will be

served by the respondent- RUIDP upon the petitioner company

about the defects and irregularities committed by them along with

punishment/penalty to be initiated. The respondents will also

specify the name of five independent arbitrators, out of their panel

who are independent and impartial and are not ex-employees of

the department but experts in the field of legal/technical side and

can adjudicate upon the matter in disputes.

10. That within 30 days from 15th February, 2022 i.e. on receipt

of show cause notice, a response/ defence will be submitted by

the petitioner company along with the selection of one of the

(4 of 4) [CW-21083/2019]

arbitrator out of the given list for adjudication of the case. The

learned arbitrator so chosen by the petitioner company and

respondents will decide his fee as per Schedule IV of the

Arbitration (Amendment) Act, 1996 and adjudicate the case/

matter within a time period of sixty days on receipt of the reply,

on its own merits without being prejudiced by any observation of

the Court.

11. With these directions, the present writ petition is disposed of

and the order dated 13.11.2018 is modified in terms of interim

order dated 10.12.2019 till the adjudication of the case by the

learned arbitrator.

12. In light of the above above terms, the writ petition is

disposed of with the consent of the parties.

13. All pending applications also stand disposed of.

(SAMEER JAIN),J

RAJAT KUMAR/Faheem 44

Powered by TCPDF (www.tcpdf.org)

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 

LatestLaws Partner Event : IJJ

 
 
Latestlaws Newsletter