Wednesday, 13, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Shobha Devi vs The State Of Bihar And Ors
2025 Latest Caselaw 4087 Patna

Citation : 2025 Latest Caselaw 4087 Patna
Judgement Date : 13 October, 2025

Patna High Court

Shobha Devi vs The State Of Bihar And Ors on 13 October, 2025

          IN THE HIGH COURT OF JUDICATURE AT PATNA
                   Civil Writ Jurisdiction Case No.8704 of 2018
     ======================================================
     Shobha Devi Wife of Sunil Kumar Gupta at Police Camp, Beda, P.O. Beda,
     P.S. Sasaram Muffasil, District Rohtas.

                                                              ... ... Petitioner/s
                                      Versus
1.   The State of Bihar through the Principal Secretary, Department of Energy,
     Government of Bihar, Old Secretariat, Patna
2.   The South Bihar Power Distribution Company Limited, Vidyut Bhawan,
     Bailey Road, Patna through its Managing Director.
3.   The Electrical Executive Engineer, Supply, Sasaram, District Rohtas.
4.   The Assistant Electrical Engineer, Electric Supply Sub-Division, Sasaram
     Rural, District Rohtas.
5.   The District Certificate Officer, Rohtas, Sasaram.

                                               ... ... Respondent/s
     ======================================================
     Appearance :
     For the Petitioner/s     :     M/s Suraj Samdarshi
                                    Avinash Shekhar
                                    Simran Kumari
                                    Abhilasha Jha, Advocates
     For the Respondent/s     :     Mr.Abbas Haider -SC 6
     ======================================================
         CORAM: HONOURABLE JUSTICE SMT. G. ANUPAMA CHAKRAVARTHY

                                  ORAL JUDGMENT
                                  Date : 13-10-2025

                    1.      The   petitioner      has      filed   the      Writ

      application for the following reliefs:

                      "(i) For issuance of a Writ of Mandamus
                      directing the respondent authorities and
                      in particular the respondent no. 4, to
                      complete the assessment proceeding as
                      per provisions of Section 126 of the
                      Electricity Act, 2003, which has not
                      attained finality till date.
                      (ii) For issuance of a Writ of Certiorari for
 Patna High Court CWJC No.8704 of 2018 dt.13-10-2025
                                           2/7




                        quashing of the certificate proceeding
                        giving rise to Certificate Case No. 33 of
                        2016-17, which has been instituted on
                        the     requisition           which     has    not    been
                        properly filled up by the respondent no.
                        4.
                        (iii) For a declaration that initiation of
                        certificate         proceeding           without      final
                        adjudication under Section 126 and 127
                        of the Electricity Act, 2003 tantamounts
                        to    gross       abuse        of     the     power   and
                        discretion conferred upon the Assessing
                        Authority.
                        (iv) For a direction to the respondent no.
                        5 not to take any further step in the
                        certificate proceeding bearing Certificate
                        Case No. 33 of 2016-17 instituted on the
                        basis of the requisition filed by the
                        respondent no. 4, who is the Assessing
                        Officer       also,      without        compliance      of
                        Section 126 of the Electricity Act.
                        (v) For a declaration that unauthorized
                        use of electricity would be only to the
                        extent of the parameters reflected by the
                        meter and not the connected load found
                        in course of physical inspection, wherein
                        meter is found to be correct; and for any
                        other      relief     or      reliefs   to    which    the
                        petitioner is found entitled."
 Patna High Court CWJC No.8704 of 2018 dt.13-10-2025
                                           3/7




                     2. The brief facts as culled out of the

         petition are that the petitioner for establishing rice

         mill took an electricity connection bearing Service

         Connection No. AIR-3059, energized on 06.07.2012

         with an initial sanctioned load of 51 H.P., which was

         enhanced to 81 H.P. under LTIS-II category. On

         11.11.2014

, an inspection was conducted during

which the connected load was found to be 136 H.P.,

though the meter recorded a maximum demand of

116.19 H.P. All seals of the meter were found

normal pursuant to the said inspection a demand

of Rs. 8,56,852/- was raised under Section 126 of

the Electricity Act. The said provisional assessment

dated 24.12.2014.

3. It is submitted that the petitioner filed

representation dated 07.01.2015 based on these

grounds in response to Letter No. 424, but no final

order was passed under Section 126 of the

Electricity Act. Despite this, the electricity supply

was disconnected on 31.03.2015, and a certificate

proceeding was initiated under the Bihar & Orissa Patna High Court CWJC No.8704 of 2018 dt.13-10-2025

Public Demand Recovery Act, 1914, (hereinafter

called as the PDR Act) for recovery of Rs.

7,71,843/-.

4. The Learned counsel for the petitioner

submitted that in the absence of a final

assessment under Section 126 of the Electricity

Act, initiation of recovery under the PDR Act is

illegal. It is further submitted that without a final

order, the petitioner is deprived of the statutory

right to appeal under Section 127 of the Electricity

Act.

5. It is contended that the requisition for

recovery filed by respondent no. 4 is defective and

incomplete, vitiating the proceedings initiated

thereupon and the entire recovery proceeding are

contrary to the statutory scheme, thereby violating

Articles 14 and 19(1)(g) of the Constitution of

India.

6. A counter affidavit was filed on behalf of

the respondents wherein the respondents admitted

the inspection findings and the issuance of the

provisional assessment.

Patna High Court CWJC No.8704 of 2018 dt.13-10-2025

7. The Learned counsel for the respondents

submitted that the petitioner did not file

objections within the stipulated time.

8. It is argued that the certificate

proceeding was validly initiated based on the

provisional assessment and the requisition was

filed properly.

9. The respondents asserted that the

petitioner should have availed the remedy under

Section 10 of the PDR Act before approaching the

Writ court. They denied any violation of

constitutional rights and submitted that the

certificate officer was the competent authority to

adjudicate the objections.

10. Heard the Learned counsel for the

petitioner as well as the Learned counsel for the

respondents.

11. Upon hearing the parties and perusing

the records, it is evident that the final order under

Section 126 of the Electricity Act was not passed

despite the petitioner having filed objections to the

provisional assessment due to this procedural Patna High Court CWJC No.8704 of 2018 dt.13-10-2025

lapse the petitioner could not avail the statutory

right of appeal under Section 127 of the Electricity

Act.

12. Further, the initiation of certificate

proceedings under the Bihar & Orissa Public

Demand Recovery Act, 1914, without finalization of

the assessment process, is found to be premature

and legally unsustainable.

13. The Court also notes from the record

that the petitioner has filed an objection under

Section 9 of the PDR Act, but the Certificate Officer

has not yet passed any order under Section 10.

14. Under the facts and circumstances

stated above, the Court finds it appropriate to

remit the matter to the Certificate Officer to decide

the objections filed by the petitioner in accordance

with law.

15. In view of the foregoing discussions,

the matter is remitted to the concerned Certificate

Officer to decide the objection filed by the

petitioner under Section 10 of the Bihar & Orissa Patna High Court CWJC No.8704 of 2018 dt.13-10-2025

Public Demand Recovery Act, 1914.

16. It is needless to mention that before

passing any order, the authority concerned shall

give an opportunity of hearing to the petitioner.

Any order passed shall be communicated to the

petitioner. The entire exercise shall be completed

as expeditiously as possible preferably within a

period of three months from the date of filing of

the objections by the petitioner.

17. Accordingly the matter is disposed of

with the aforesaid observation.

18. Interlocutory Application(s), if any,

shall stand disposed of.

(G. Anupama Chakravarthy, J) Spd/-

AFR/NAFR                NAFR
CAV DATE                NA
Uploading Date          15.10.2025
Transmission Date
 

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter