Sunday, 17, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Basant Kumar vs The State Of Bihar
2025 Latest Caselaw 4054 Patna

Citation : 2025 Latest Caselaw 4054 Patna
Judgement Date : 9 October, 2025

Patna High Court

Basant Kumar vs The State Of Bihar on 9 October, 2025

Author: P. B. Bajanthri
Bench: Alok Kumar Sinha, P. B. Bajanthri
          IN THE HIGH COURT OF JUDICATURE AT PATNA
                   Civil Writ Jurisdiction Case No.11886 of 2025
     ======================================================
     Basant Kumar Son of Sri Ram Chandra Prasad Resident of Kailash Nagar,
     Gali No.-1, Old G.T. Road, P.S.- Sasaram, District- Rohtas.
                                                                 ... ... Petitioner/s
                                        Versus
1.    The State of Bihar through Additional Chief Secretary, Rural Works
      Department, Government of Bihar, Patna.
2.   The Engineer- In- Chief, Rural Works Department, Government of Bihar,
     Patna.
3.   The Chief Engineer-2, Rural Works Department (Gaya), Government of
     Bihar, Patna.
4.   The Superintending Engineer, Work Circle- Sasaram, Rural Works
     Department, Government of Bihar, Patna.
5.   The Nodal Officer, MMGSUY, Rural Works Department, Government of
     Bihar, Patna.
6.   The Executive Engineer, Rural Works Department, Works Division-
     Sasaram-1, District- Rohtas.

                                               ... ... Respondent/s
     ======================================================
     Appearance :
     For the Petitioner/s   :       Mr. Prabhat Ranjan, Adv.
                                    Mr. Ansh Prasad, Adv.
                                    Mr. Shubham Prakash, Adv.
     For the Respondent/s   :       Mr. P.K. Shahi, Advocate General
                                    Mr. Vikas Kumar, Adv.
     ======================================================
     CORAM: HONOURABLE THE CHIEF JUSTICE
             and
             HONOURABLE MR. JUSTICE ALOK KUMAR SINHA
     CAV JUDGMENT
     (Per: HONOURABLE MR. JUSTICE ALOK KUMAR SINHA)

      Date : 09-10-2025

                  Heard the parties.

                  2. The petitioner in the present writ application seeks the

     following main relief:

                                        "(i) Quashing of the decision of the
                            Technical Evaluation Committee as contained
                            in    Memo      No.     2469     dated     30.06.2025
 Patna High Court CWJC No.11886 of 2025 dt.09-10-2025
                                           2/34




                                (Annexure P/6) (uploaded on 01.07.2025) by
                                which mechanically differing with the report of
                                the jurisdictional Executive Engineer with
                                regard to the insufficient bid capacity of the
                                Respondent No. 6 and without assigning any
                                reason the technical bid of the Respondent No.
                                6 was declared to be responsive.
                                            (ii) Quashing of the decision of the
                                Technical Evaluation Committee as contained
                                in    Memo        No.    2477     dated    01.07.2025
                                (Annexure P/7) by which in the absence of any
                                objection and on the same day on which the
                                earlier proceeding was uploaded, without
                                there being any chance in circumstance, the
                                technical         evaluation       committee       has
                                reconvened its meeting and reiterated the
                                earlier decision with regard to the declaration
                                of responsiveness of the technical bid of
                                Respondent No. 6.
                                            (iii) Quashing of the decision of the
                                Technical Bid Evaluation Committee bearing
                                Memo No. 2611 dated 14.07.2025 (Annexure
                                P/9) by which after financial bid evaluation,
                                the    Respondents         have    re-evaluated    the
                                technical bid of the Lowest Bidder (L-1) and
                                subsequently,       declared his technical bid
                                responsive on account of insufficient bid
                                capacity,     and       entire    tender   has    been
                                recommended to be canceled with the further
                                recommendation for re-advertisement for the
 Patna High Court CWJC No.11886 of 2025 dt.09-10-2025
                                           3/34




                                reason that the rates have been opened and the
                                confidentiality of the tender stands vitiated.
                                            (iv) Directing the Respondents to
                                consider the Representation/ Request dated
                                16.05.2025

(Annexure P/10) wherein, the petitioner has requested for award of work in his favour as he was the 2nd Lowest Bidder and has consented to complete the work at the lowest evaluated price as quoted by L-1; and

(v) Restraining the Respondents from giving effect to the decision contained in Memo No. 2611 dated 14.07.2025 during the pendency of the present writ application and/or the without the leave of this Hon'ble Court.

(vi) Quashing of the Short Notice Inviting Tender No. RRRSMP-15/2025-26 dated 22.07.2025 signed by the Engineer In-

Chief and uploaded on 26.07.2025 by which giving effect to the Impugned Order of cancellation of the earlier tender, the work which is the subject matter of the present writ application has been re-advertised on the same terms and conditions; and"

3. Learned counsel for the petitioner, while assailing the

impugned decisions of the Respondents, has set out the broad facts

and grounds upon which the present writ application rests. It is

submitted that the petitioner is a contractor registered in Class-I Patna High Court CWJC No.11886 of 2025 dt.09-10-2025

under the Bihar Contractors Registration Rules, 2007 and has been

engaged in execution of various works on behalf of governmental

organizations.

4. The genesis of the controversy, as canvassed by the

petitioner, lies in the issuance of Notice Inviting Tender No.

RRRSMP-15/2024-25 dated 27.02.2025 for "Initial Rectification,

Minor Improvement, Surface Renewal, Construction of

Bridge/Drainage/Protection Work including Operation and

Management for the Rural Road Strengthening and Management

Program under the component of Mukhya Mantri Gramin Sadak

Unnayan Yojana (GEN) (MMGSUY)," with special reference to

Package No. RRRSMP/24-25 Sasaram-1/11 at Serial No. 1, the

total contract value being Rs. 3520.452 Lacs (Annexure: P/1).

5. It is submitted that altogether ten bidders, including

the petitioner, participated in the tender process. The Five-Member

Technical Bid Evaluation Committee, chaired by the Departmental

Engineer In-Chief, convened on 06.05.2025 for evaluation of

technical bids, and vide Memo No. 1643 dated 08.05.2025

(Annexure: P/1) declared seven bidders, including M/s Shanti

Construction, technically responsive, while three bidders were

declared non-responsive. An option was granted to file objections

within five working days. Exercising such option, the petitioner Patna High Court CWJC No.11886 of 2025 dt.09-10-2025

filed a detailed objection on 16.05.2025 (Annexure: P/3) against

the declaration of technical eligibility of three bidders, namely,

M/s Shanti Construction, M/s Govind Madhav, and V.S.

Construction, inter alia contending that M/s Shanti Construction

lacked the requisite bid capacity.

6. It is urged that despite this objection, the Technical

Bid Evaluation Committee, upon re-convening on 10.06.2025,

vide Memo No. 2220 dated 12.06.2025 (Annexure: P/4), reiterated

its earlier decision without properly dealing with the contentions

raised. Once again, the petitioner was constrained to file another

affidavit-ed objection on 13.06.2025 (Annexure: P/5) specifically

pointing out insufficiency of bid capacity of M/s Shanti

Construction and requesting re-calculation after taking into

account works already allotted in Aurangabad Division. On the

basis of this objection, a report was called from the jurisdictional

Executive Engineer, who categorically reported that M/s Shanti

Construction lacked the requisite bid capacity. Notwithstanding

this, vide Memo No. 2469 dated 30.06.2025 (Annexure: P/6) , the

Technical Bid Evaluation Committee reiterated its earlier stand,

declaring the bid of M/s Shanti Construction technically

responsive without assigning any reason for disregarding the

Engineer's report. The said decision was followed by yet another Patna High Court CWJC No.11886 of 2025 dt.09-10-2025

decision bearing Memo No. 2477 dated 01.07.2025 (Annexure:

P/7), passed in undue haste on the very day the earlier decision

was uploaded and without waiting for the objection period to

lapse.

7. Learned Counsel for the petitioner further submits

that on 05.07.2025, the financial bids were opened. M/s Shanti

Construction was declared as the lowest bidder (L-1) having

quoted 5.77% below the estimated rate, while the petitioner was

declared the second lowest bidder (L-2), having quoted 5.05%

below the estimated rate. The grievance of the petitioner, as urged

by learned counsel, is that surprisingly, after opening of financial

bids and declaration of the lowest bidder, the Committee, in the

absence of any objection, re-convened on 12.07.2025, this time

without one of its prominent members, and re-calculated the bid

capacity of M/s Shanti Construction. It was then found that the

said bidder did not, in fact, possess the requisite bid capacity, as

the petitioner had consistently maintained. Consequently, vide

Memo No. 2611 dated 14.07.2025 (Annexure: P/9), the Committee

decided to recommend cancellation of the tender and re-

advertisement of the work on the ground that confidentiality of

financial bids had already been compromised. Patna High Court CWJC No.11886 of 2025 dt.09-10-2025

8. Aggrieved thereby, the petitioner vide

communication dated 16.07.2025 (Annexure P/10) expressed

willingness to execute the work at the L-1 rate quoted by M/s

Shanti Construction. The Respondents, however, declined to

consider such willingness and instead proceeded with their

decision to cancel the tender.

Learned counsel for the petitioner contends that the

impugned decisions contained in Memo Nos. 2469 dated

30.06.2025, 2477 dated 01.07.2025, and 2611 dated 14.07.2025

are wholly arbitrary, contrary to the established principles of

tender law, dehors the Standard Bidding Document, and vitiated

by non-application of mind. It is submitted that:

(i) The decisions of 30.06.2025 and 01.07.2025 are non-

speaking and contrary to the materials on record, particularly the

report of the Executive Engineer, which clearly held that M/s

Shanti Construction lacked bid capacity.

(ii) The decision dated 01.07.2025 was premature, being

passed without lapse of the objection period, and further suffers

from procedural irregularity due to absence of a key committee

member.

(iii) The decision dated 14.07.2025 is vitiated by the

principle of coram non judice and is without jurisdiction, inasmuch Patna High Court CWJC No.11886 of 2025 dt.09-10-2025

as there is no provision in law for re-evaluating the technical bid

after the financial bid has been opened and the lowest bidder

declared.

(iv) The Respondents acted illegally in ignoring the

objections filed by the petitioner thrice, only to later accept the

same objections after financial bids had been opened, thereby

causing prejudice to the petitioner.

(v) Upon disqualification of the lowest bidder, the

Respondents ought to have invited the petitioner, being the second

lowest bidder, to express willingness to perform the work at the L-

1 rate. Instead, they arbitrarily recommended cancellation and re-

advertisement, which is against both settled practice and

departmental precedents (Memo No. 448 dated 05.05.2025 and

Memo No. 2206 dated 21.06.2025).

9. It is thus urged by the learned counsel for the

petitioner that the Respondents, by cancelling the tender process,

have sought to take advantage of their own wrong, to the detriment

of the petitioner. The decision also entails avoidable delay, re-

advertisement formalities, and cost escalation, all to the prejudice

of public interest. It is thus submitted that the relief sought by the

petitioner would not adversely affect the Respondents; rather, it

would serve the larger public interest by avoiding unnecessary Patna High Court CWJC No.11886 of 2025 dt.09-10-2025

procedural duplication and ensuring timely execution of the

project. The learned counsel for the petitioner, therefore, prays for

quashing of the impugned decisions and for issuance of

appropriate directions to the Respondents to allot the work to the

petitioner at the L-1 rate quoted by M/s Shanti Construction.

10. Learned counsel for the respondents has filed a

detailed counter affidavit traversing the allegations made in the

writ application. It has been submitted at the very outset that the

impugned decisions of the Technical Bid Evaluation Committee

are in conformity with the Standard Bidding Document, the

governing provisions of the Notice Inviting Tender (NIT), and the

settled norms for disposal of tenders.

11. It is the stand of the respondents that pursuant to the

Notice Inviting Tender bearing No. RRRSMP-15/2024-25 dated

27.02.2025 in relation to the works under the Mukhya Mantri

Gramin Sadak Unnayan Yojana (MMGSUY), a total of ten bidders

including the petitioner had submitted their bids. The Technical

Bid Evaluation Committee, in its meeting dated 06.05.2025,

evaluated the technical bids and declared nine bidders, including

the petitioner, to be technically responsive, which was

communicated through Memo No. 1643 dated 08.05.2025

(Annexure: R/A).

Patna High Court CWJC No.11886 of 2025 dt.09-10-2025

12. Learned counsel for the respondents submits that

objections were thereafter filed by certain bidders including the

petitioner, and the same were duly considered by calling for

reports from the jurisdictional Executive Engineer. On the basis of

such reports, the Technical Bid Evaluation Committee re-convened

its meetings on 10.06.2025 and 27.06.2025 and reiterated its

findings, declaring the petitioner qualified, as reflected in Memo

Nos. 2220 dated 12.06.2025 and 2469 dated 30.06.2025

respectively.

It has further been submitted that upon noticing a defect

in the calculation of bid capacity of M/s Shanti Construction, the

Committee again re-convened on 01.07.2025 and issued Memo

No. 2477, reaffirming its earlier conclusions. The respondents

assert that the Committee acted within its jurisdiction in correcting

technical assessments and ensuring conformity with bid capacity

requirements. The financial bid was thereafter opened on

05.07.2025, wherein M/s Shanti Construction was declared as the

Lowest Bidder (L-1), while the petitioner was ranked second (L-

2). However, upon further scrutiny of the bid capacity of M/s

Shanti Construction, and after recalculation, it emerged that the

said bidder lacked the requisite capacity as the works already

allotted to it had substantially reduced its permissible capacity. Patna High Court CWJC No.11886 of 2025 dt.09-10-2025

13. Learned counsel for the respondents submits that in

such circumstances, the Technical Bid Evaluation Committee, by

its meeting held on 12.07.2025, recommended cancellation of the

tender process and re-advertisement of the work, which decision

was communicated vide Memo No. 2611 dated 14.07.2025. The

said recommendation, it is urged, was made strictly in light of

Clause 33 of the NIT which reserves to the Engineer-in-Chief the

right to reject any or all bids and to cancel the bidding process at

any time prior to the award of contract without assigning any

reason. It is the stand of the respondents that once the financial

bids had been opened and the confidentiality of rates stood

compromised, there was no alternative available except to cancel

the tender and proceed for re-tendering. In such a situation,

awarding the work to the petitioner as L-2 could not have been

considered in the absence of any enabling provision in the

Standard Bidding Document or the NIT.

14. Learned counsel for the respondents has thus

emphasized that the grievance of the petitioner is misconceived

inasmuch as the petitioner's objections were duly considered on

multiple occasions, reports were called for and examined, and the

process was reviewed no less than five times before arriving at the

final decision. It is contended that the petitioner cannot seek Patna High Court CWJC No.11886 of 2025 dt.09-10-2025

enforcement of a claim for award of contract as L-2 in the absence

of a statutory or contractual provision to that effect. It is thus urged

that the writ application is devoid of merit, as the decision

impugned has been taken in public interest, to preserve the

integrity of the tender process, and strictly in terms of the powers

reserved under the NIT.

ISSUES IN QUESTION:

1. Whether the decision of the Technical Bid Evaluation

Committee declaring the technical bid of Shanti Constructions as

responsive, despite the contrary report of the jurisdictional

Executive Engineer regarding insufficient bid capacity, suffers

from arbitrariness or non-application of mind?

2. Whether the subsequent re-evaluation and reiteration

of the decision of the Technical Bid Evaluation Committee on

01.07.2025, without any material change in circumstances, is

legally sustainable?

3. Whether the final decision of the Technical Bid

Evaluation Committee dated 14.07.2025, cancelling the entire

tender process on the ground of insufficient bid capacity of the

Lowest Bidder (L-1) and breach of confidentiality of the tender,

was in accordance with Clause 33 of the Notice Inviting Tender

(NIT)?

Patna High Court CWJC No.11886 of 2025 dt.09-10-2025

4. Whether the petitioner, being the second lowest

bidder and having expressed willingness to execute the work at the

rate quoted by the Lowest Bidder (L-1), has any enforceable legal

right to claim award of the contract in his favour?

5. Whether this Court, in exercise of its writ jurisdiction

under Article 226 of the Constitution of India, has the power to

interfere in the decisions of the Technical Bid Evaluation

Committee and the tendering authority, particularly in matters

involving evaluation of bid capacity, responsiveness, and

cancellation of tender?

FINDINGS:

Issue No.1: Whether the decision of the Technical Bid

Evaluation Committee declaring the technical bid of Shanti

Constructions as responsive, despite the contrary report of the

jurisdictional Executive Engineer regarding insufficient bid

capacity, suffers from arbitrariness or non-application of mind?

Having considered the materials on record, it is evident

that the jurisdictional Executive Engineer, by his report dated

26.06.2025, clearly pointed out that the bid capacity of Shanti

Construction was deficient in comparison to the requirement

prescribed under the Notice Inviting Tender. Notwithstanding the

said report, the Technical Bid Evaluation Committee, in its Patna High Court CWJC No.11886 of 2025 dt.09-10-2025

meeting held on 30.06.2025, proceeded to declare the bid of Shanti

Construction as responsive, without recording any cogent reason

for differing with the findings of the Engineer. This Court finds it

difficult to hold such action as a proper exercise of discretion. The

absence of reasoning, particularly when an adverse report was

available on record, does reflect a degree of arbitrariness and non-

application of mind.

At the same time, the subsequent conduct of the

respondents cannot be overlooked. The Committee, upon further

scrutiny and calculation of bid capacity, ultimately found that

Shanti Construction did not meet the requisite bid capacity and,

accordingly, in its meeting dated 12.07.2025, recommended

cancellation of the entire tender, culminating in Memo No. 2611

dated 14.07.2025. Such cancellation was not only premised on the

insufficiency of bid capacity but also on the breach of

confidentiality of the financial bids already opened. In these

circumstances, the decision to re-tender the work stands as a

corrective measure.

It is settled law that the State or its instrumentalities are

entitled to cancel a tender process if the integrity of the process is

compromised, provided the action is not mala fide. In Michigan

Rubber (India) Ltd. v. State of Karnataka, (2012) 8 SCC 216, the Patna High Court CWJC No.11886 of 2025 dt.09-10-2025

Hon'ble Supreme Court held that in the matter of awarding

contracts, the authority has the right to decide whether to accept or

cancel bids, and interference is permissible only where the action

is patently arbitrary or intended to favour someone. Likewise, in

Afcons Infrastructure Ltd. v. Nagpur Metro Rail Corporation

Ltd., (2016) 16 SCC 818, the Court reiterated that a tendering

authority is the best judge of its requirements and judicial review

must remain limited. In Montecarlo Ltd. v. NTPC Ltd., (2016) 15

SCC 272, it was held "that in the competitive commercial field in

the matter of award of contract through tender, the conditions

regarding bidder's expertise and technical capability and capacity

are decided by the experts"

Applying the above principles in the facts of the present

case, though the declaration of Shanti Construction's bid as

responsive on 30.06.2025 was not justified, the respondents, by

cancelling the tender and opting for re-tender, have rectified the

process. This subsequent corrective action militates against any

allegation of malafides or arbitrariness in the ultimate decision.

Accordingly, while the action of the Technical Bid

Evaluation Committee dated 30.06.2025 in declaring Shanti

Construction responsive cannot be sustained as a reasoned

decision, the later step of cancelling the tender and proceeding for Patna High Court CWJC No.11886 of 2025 dt.09-10-2025

re-tender reflects fairness, transparency, and due compliance with

Clause 33 of the Notice Inviting Tender.

Issue No. 2. Whether the subsequent re-evaluation and

reiteration of the decision of the Technical Bid Evaluation

Committee on 01.07.2025, without any material change in

circumstances, is legally sustainable?

The record reflects that after the Technical Bid

Evaluation Committee declared Shanti Construction's technical

bid as responsive vide Memo No. 2469 dated 30.06.2025, the

Committee re-convened on 01.07.2025 and reiterated the earlier

decision through Memo No. 2477. It is pertinent to note that this

reiteration was undertaken on the same day the earlier decision

was uploaded and without any fresh objection, supplementary

report, or change in factual circumstances. The Executive

Engineer's report, which had pointed out that the bid capacity of

Shanti Construction was insufficient, was already available on

record, yet no further reasoned discussion was recorded in the

proceedings of 01.07.2025.

This Court observes that from a procedural standpoint,

the reiteration of the earlier decision without any new material

consideration cannot be said to constitute an exercise of

administrative discretion in its ideal form. The principles of Patna High Court CWJC No.11886 of 2025 dt.09-10-2025

reasoned decision-making require that where an authority departs

from or differs with the recommendations of a subordinate officer,

particularly in matters such as technical evaluation of bids, such

divergence should be expressly recorded with reasons. In this case,

the Technical Bid Evaluation Committee did not indicate why the

Executive Engineer's report was not being accepted, nor did it

elucidate why the earlier decision required reiteration.

Applying the principles of arbitrariness, mala fide

conduct, or non-application of mind, the reiteration of order dated

01.07.2025, standing alone, may be viewed as procedurally flawed

because it did not adequately address the concerns raised by the

Executive Engineer and did not provide a reasoned basis for

repeating the earlier decision. But this could have been a matter of

judicial review when the tender process would have been

concluded declaring L1 as the successful bidder despite these

lapses. However, the Court also notes that this procedural lapse

was immediately rectified by the respondents. Upon further

scrutiny, including detailed calculation of Shanti Construction's

bid capacity and consideration of the breach of confidentiality

arising from the opening of financial bids, the Committee, in its

meeting dated 12.07.2025, and subsequently via Memo No. 2611

dated 14.07.2025, recommended cancellation of the tender and re- Patna High Court CWJC No.11886 of 2025 dt.09-10-2025

advertisement. This subsequent corrective action demonstrates that

the respondents recognized the inadequacy of the earlier

procedural step and took appropriate measures to ensure fairness,

transparency, and integrity in the tendering process.

It is well established that the tendering authority has the

discretion to cancel a tender if it is found that the integrity of the

process is compromised, provided such discretion is exercised in

good faith. The principle that the authority inviting tenders is the

best judge of its requirements, and judicial interference is

warranted only in cases of malafide action or perversity has been

reiterated in a catena of judgments by the Hon'ble Apex Court.

In the present case, while the decision dated 01.07.2025

was not fully reasoned and arguably procedural impropriety

existed, the respondents have rectified the lapse by cancelling the

tender and initiating a fresh bidding process. This corrective step

effectively neutralizes any adverse effect arising from the

reiteration and upholds the overall fairness and legality of the

tender process. The Court is therefore satisfied that no prejudice

has been caused to the petitioner or to the other stakeholders, and

the respondents' final action ensures compliance with the

principles of natural justice, transparency, and reasoned decision-

making.

Patna High Court CWJC No.11886 of 2025 dt.09-10-2025

In conclusion, the reiteration of the decision on

01.07.2025, standing alone, is not fully sustainable as a reasoned

administrative action. However, in view of the corrective measures

taken by the respondents through cancellation and re-tendering of

the work, the lapse is rendered harmless, and the exercise of

discretion by the Technical Bid Evaluation Committee is validated

in the ultimate analysis.

Issue No. 3. Whether the final decision of the

Technical Bid Evaluation Committee dated 14.07.2025,

cancelling the entire tender process on the ground of insufficient

bid capacity of the Lowest Bidder (L-1) and breach of

confidentiality of the tender, was in accordance with Clause 33

of the Notice Inviting Tender (NIT)?

The record shows that after the financial bids were

opened on 05.07.2025, Shanti Construction was declared the

Lowest Bidder (L-1) with a quoted price 5.77% below the

estimated rate, while the petitioner was the 2nd lowest bidder.

Subsequent verification of the bid capacity of Shanti Construction

revealed that its total bid capacity, when adjusted for already

allotted works under Tender ID 139610 and Tender ID 139568,

was insufficient to undertake the tendered work of Rs. 3714.50482

lakhs. In addition, since the financial bids had already been Patna High Court CWJC No.11886 of 2025 dt.09-10-2025

opened, the confidentiality of the tender process stood

compromised, as all bidders were now aware of the L-1 rates.

In view of these facts, the Technical Bid Evaluation

Committee, in its meeting dated 12.07.2025, and by Memo No.

2611 dated 14.07.2025, recommended cancellation of the tender

and re-advertisement of the work. The Committee acted under

Clause 33 of the Notice Inviting Tender, which explicitly provides:

"The Engineer in Chief-cum-Additional Commissioner-cum-Special Secretary / Engineer in Chief reserves the right to accept or reject any bid and to cancel bidding process and reject all bids, at any time prior to the award of the contract without assigning any reason thereof."

Clause 33 clearly vests absolute discretion in the

tendering authority to cancel the tender even prior to award, and

such discretion can be exercised to maintain fairness, transparency,

and integrity in the process. The Committee's decision to cancel

the tender was based on two substantive grounds:

(i) insufficiency of bid capacity of the L-1 bidder, and

(ii) breach of confidentiality owing to prior opening of

financial bids.

Patna High Court CWJC No.11886 of 2025 dt.09-10-2025

Both grounds fall well within the ambit of Clause 33 and

are rational, objectively verifiable, and intended to safeguard the

tender process.

The law is well-settled that cancellation of a tender in

such circumstances is permissible and falls within the domain of

administrative discretion. In Afcons Infrastructure Ltd. v. Nagpur

Metro Rail Corporation Ltd (Supra), the Hon'ble Supreme Court

held that the tendering authority is the best judge of its

requirements and evaluation, and courts will interfere only in cases

of mala fide action, perversity, or manifest arbitrariness. Similarly,

in Michigan Rubber (India) Ltd. v. State of Karnataka (Supra), it

was held that the power to cancel a tender is an essential tool to

ensure probity in public procurement, and mere dissatisfaction of

bidders does not justify interference.

It is also noteworthy that the respondents conducted

multiple technical reviews, including calling for detailed reports

from the Executive Engineer, to ascertain the correctness of bid

capacities and technical eligibility. The decision to cancel the

tender, therefore, was not an arbitrary exercise but a considered

action following repeated technical assessments and a transparent

verification process.

Patna High Court CWJC No.11886 of 2025 dt.09-10-2025

In conclusion, the final decision dated 14.07.2025

cancelling the tender process on grounds of insufficient bid

capacity of the L-1 bidder and breach of confidentiality is legally

sustainable, exercised in accordance with Clause 33 of the NIT,

and reflects a lawful and prudent exercise of administrative

discretion to maintain fairness, transparency, and integrity in the

tender process.

Issue No. 4. Whether the petitioner, being the second

lowest bidder and having expressed willingness to execute the

work at the rate quoted by the Lowest Bidder (L-1), has any

enforceable legal right to claim award of the contract in his

favour?

The petitioner contends that, as the second lowest

bidder, he should have been awarded the work at the rate quoted

by the L-1 bidder, relying on the argument of logical sequencing

and fairness. It is, however, pertinent to note that the petitioner has

not specifically prayed for a declaration that he be treated as L-1 or

for an order awarding the contract to him in the present writ

application. The relief sought primarily challenges the decision of

the Technical Bid Evaluation Committee to cancel the tender and

does not include a direct claim for assignment of the contract. Patna High Court CWJC No.11886 of 2025 dt.09-10-2025

From a legal standpoint, no bidder, including the second

lowest bidder, acquires an enforceable right to be awarded a

contract merely because the lowest bidder is subsequently found to

be technically non-responsive. The law on public procurement is

clear that the tendering authority retains discretion to accept or

reject any bid, and the right to cancel a tender, unless restricted by

statute or contract, cannot be circumvented by invoking the

position of the next lowest bidder. The relevant provisions in the

Notice Inviting Tender (Clause 33) expressly empower the

authority to cancel the tender without assigning any reason. There

is no provision mandating that in case of disqualification of the L-

1 bidder, the second lowest bidder must automatically be offered

the contract. Judicial precedents reinforce this principle. In the

case of W.B. State Electricity Board v. Patel Engineering Co.

Ltd. And Others (2001) 2 SCC 451, it was categorically held that:

"33. We may, however, clarify that the

appellant is not obliged to award contract to

any of the bidders at their quoted price

bid......"

In the present case, the petitioner's willingness to

execute the work at the L-1 rate, expressed in his communication Patna High Court CWJC No.11886 of 2025 dt.09-10-2025

dated 16.07.2025, cannot override the explicit discretion of the

Technical Bid Evaluation Committee under Clause 33 of the NIT.

Also in a recent judgment by the Hon'ble Supreme

Court in the case of Prakash Asphaltings And Toll Highways

(India) Ltd. vs Mandeepa Enterprises & Ors Civil Appeal No.

11418 of 2025, the Hon'ble Apex Court has explicitly held:

"40. The above proposition has been followed by another three-Judge Bench of this Court in the recent case of Subodh Kumar Singh Rathore Vs. Chief Executive Officer , when it examined the concept of public interest in administrative decisions relating to award of contracts. This Court held that even assuming for a moment that there was technical fault in the tender, which if rectified had the possibility of generating more revenue, the same by no stretch could be said to be a cogent reason for concealing an already existing tender. This Court highlighted the importance of maintaining the sanctity of tenders in governmental procurement processes.

Public tenders are the cornerstone of governmental procurement processes, being competitive and ensuring fairness and transparency in the allocation of public resources. Public tenders are designed to provide a level playing field for all potential Patna High Court CWJC No.11886 of 2025 dt.09-10-2025

bidders, fostering an environment where competition thrives. The integrity of this process ensures that public projects and resources are delivered efficiently and effectively, benefiting the society at large. Therefore, sanctity of public tenders and contract is a fundamental principle that underpins the stability and predictability of legal and commercial relationships. Infact this Court put in a word of caution that considerations of public interest should not be narrowly confined to financial aspect only.

41. Applying the above legal principles to the facts of the present case, we are of the view that the Division Bench of the High Court clearly fell in error in directing respondent No. 2 to 4 to allow rectification of the financial bid of respondent No. 1 by treating the amount offered by it as the per day figure and on that basis to compute the total amount for the entire contractual period of 1095 days. Such an exercise is clearly impermissible having regard to the terms and conditions of the contract which are required to be understood on the anvil of this Court's judgments.

The authority granted to the tendering authority by clause 5B (v) of the Instruction to Bidders cannot be stretched to construe the price bid of respondent No. 1 as Patna High Court CWJC No.11886 of 2025 dt.09-10-2025

the per day offer, contrary to the bid declaration of respondent No. 1 itself, and thereafter, on that basis to work out a new bid amount for the entire contractual period making it the highest. In the present case, respondent No. 1 was not at all vigilant;

rather, it displayed a very casual approach. In such circumstances, clause 5B(v) cannot be invoked to resurrect the bid of respondent No. 1 to make it H1. Clause 5B(v) of the Instruction to Bidders has to read conjointly with clause 4(g) of the notice inviting electronic bid."

[Emphasis Supplied]

Relying on the aforesaid principles, it would be pertinent

to say that any alteration in the Financial Bid already submitted

would not be permissible in the eyes of law. Therefore, the

willingness of the petitioner to work at the rate quoted by L1,

expressed in his communication dated 16.07.2025 is impermissible

in law. Merely a benefit to the public exchequer cannot be a reason

to ignore the established law and rules subject to which bids are

invited.

The respondents have acted within their authority in

cancelling the tender after assessing the bid capacities and the

breach of confidentiality. The petitioner's argument based on Patna High Court CWJC No.11886 of 2025 dt.09-10-2025

"logical reasoning" does not translate into a legally enforceable

claim, especially since the writ does not seek a relief for direct

award of the contract in his favour. Courts have consistently held

that relief in writ jurisdiction must be strictly confined to the

reliefs claimed, and no additional entitlement can be read into the

application absent specific prayer.

Therefore, the petitioner has no enforceable legal right

to claim award of the contract merely on the basis of being the

second lowest bidder. The discretion to re-tender, or to cancel and

re-advertise, remains entirely with the respondents and is exercised

in accordance with law and the NIT provisions. The petitioner's

arguments, while logically appealing, do not give rise to any legal

entitlement enforceable in this Court.

Issue No. 5. Whether this Court, in exercise of its writ

jurisdiction under Article 226 of the Constitution of India, has

the power to interfere in the decisions of the Technical Bid

Evaluation Committee and the tendering authority, particularly

in matters involving evaluation of bid capacity, responsiveness,

and cancellation of tender?

It is well-settled that the writ jurisdiction under Article

226 of the Constitution of India is a powerful constitutional

remedy designed to protect fundamental rights and ensure legality, Patna High Court CWJC No.11886 of 2025 dt.09-10-2025

fairness, and non-arbitrariness in administrative action. However,

the exercise of such jurisdiction in matters relating to public

procurement, tender evaluation, and contractual awards is

circumscribed by well-established principles of administrative law

and judicial restraint.

It is trite law that award of contracts, acceptance or

rejection of tenders, and cancellation or re-tendering of public

works are essentially commercial and administrative functions of

the State and its instrumentalities. The scope of judicial review in

such matters is narrow and circumscribed.

In Michigan Rubber (India) Ltd. v. State of Karnataka

(2012) 8 SCC 216, the Hon'ble Supreme Court held that the

Government must have freedom of contract and is entitled to

prescribe conditions ensuring competition and safeguarding public

interest. The Apex court observed that:

17) In Jagdish Mandal vs. State of Orissa and Others, (2007) 14

SCC 517, the following conclusion is relevant:

"22. Judicial review of administrative

action is intended to prevent arbitrariness,

irrationality, unreasonableness, bias and malafides.

Its purpose is to check whether choice or decision is

made "lawfully" and not to check whether choice or Patna High Court CWJC No.11886 of 2025 dt.09-10-2025

decision is "sound". When the power of judicial

review is invoked in matters relating to tenders or

award of contracts, certain special features should

be borne in mind. A contract is a commercial

transaction. Evaluating tenders and awarding

contracts are essentially commercial functions.

Principles of equity and natural justice stay at a

distance. If the decision relating to award of contract

is bona fide and is in public interest, courts will not,

in exercise of power of judicial review, interfere even

if a procedural aberration or error in assessment or

prejudice to a tenderer, is made out. The power of

judicial review will not be permitted to be invoked to

protect private interest at the cost of public interest,

or to decide contractual disputes. The tenderer or

contractor with a grievance can always seek

damages in a civil court. Attempts by unsuccessful

tenderers with imaginary grievances, wounded pride

and business rivalry, to make mountains out of

molehills of some technical/procedural violation or

some prejudice to self, and persuade courts to

interfere by exercising power of judicial review, Patna High Court CWJC No.11886 of 2025 dt.09-10-2025

should be resisted. Such interferences, either interim

or final, may hold up public works for years, or delay

relief and succour to thousands and millions and may

increase the project cost manifold. Therefore, a court

before interfering in tender or contractual matters in

exercise of power of judicial review, should pose to

itself the following questions:

(i) Whether the process adopted or

decision made by the authority is malafide or

intended to favour someone;

OR Whether the process adopted or

decision made is so arbitrary and irrational that the

court can say: "the decision is such that no

responsible authority acting reasonably and in

accordance with relevant law could have reached";

(ii) Whether public interest is affected.

If the answers are in the negative, there

should be no interference under Article 226. Cases

involving blacklisting or imposition of penal

consequences on a tenderer/contractor or

distribution of State largesse (allotment of

sites/shops, grant of licences, dealerships and Patna High Court CWJC No.11886 of 2025 dt.09-10-2025

franchises) stand on a different footing as they may

require a higher degree of fairness in action."

In the case of Tata Cellular vs. Union of India (1994) 6

SCC 651 , the Supreme Court has held that:

"94. (1) The modern trend points to judicial restraint in administrative action.

(2) The court does not sit as a court of appeal but merely reviews the manner in which the decision was made.

(3) The court does not have the expertise to correct the administrative decision. If a review of the administrative decision is permitted it will be substituting its own decision, without the necessary expertise which itself may be fallible.

(4) The terms of the invitation to tender cannot be open to judicial scrutiny because the invitation to tender is in the realm of contract.

(5) The Government must have freedom of contract and that permits a fair play in the joints as a necessary concomitant for an administrative body functioning in an administrative sphere or quasi-

administrative sphere. Hence, the Court has laid down that the decision must not only be tested by the application of Wednesbury principle of reasonableness (including its other facts pointed out above) but must be free from arbitrariness not affected by bias or actuated by mala fides."

Patna High Court CWJC No.11886 of 2025 dt.09-10-2025

The respondents in the present case are statutory

authorities entrusted with the evaluation of technical bids,

financial bids, and overall tender administration under the

applicable rules and the Notice Inviting Tender (NIT). The law

recognizes that procurement processes are complex and often

involve technical assessments that are beyond the specialized

knowledge of the Court. Evaluation of bid capacity, calculation of

allotments, verification of eligibility, and determination of whether

confidentiality is compromised are inherently administrative and

technical functions. Courts are expected to ensure that the

authority has acted in good faith, followed due process, and

applied its mind, rather than substituting their own assessment of

technical matters.

In the present case, the respondents undertook multiple

rounds of technical scrutiny, reviewed reports of the Executive

Engineer, considered objections filed by the petitioner and other

bidders, and evaluated financial bids before ultimately cancelling

the tender pursuant to Clause 33 of the NIT. The actions of the

respondents indicate repeated application of mind and adherence

to principles of transparency, fairness, and procedural propriety.

There is no evidence of mala fide conduct, arbitrariness, or non-

application of mind that would justify judicial intervention. Patna High Court CWJC No.11886 of 2025 dt.09-10-2025

Applying the above principles, the Court recognizes that

while it has the constitutional power to review administrative

decisions, such power is exercised sparingly in the context of

tender evaluation, and only when there is demonstrable

arbitrariness, mala fides, or violation of statutory norms. In the

instant matter, the respondents acted in a reasoned, transparent,

and fair manner, and the procedural steps taken demonstrate

application of mind and administrative prudence. Accordingly,

judicial interference under Article 226 is neither warranted nor

justified merely because the petitioner disagrees with the

evaluation or believes he should have been awarded the contract.

Therefore, this Court is satisfied that there is no

justiciable ground to interfere in the decision-making process of

the respondents in this matter.

15. In view of the foregoing discussion on the major

issues in question, it is apparent that the respondents have acted

within the bounds of their statutory authority in re-evaluating the

financial bids, and ultimately exercised their discretion to cancel

and re-advertise the tender in accordance with Clause 33 of the

Notice Inviting Tender. While certain procedural aspects, such as

repeated re-evaluation of the technical bid, may appear irregular,

these were corrective measures aimed at ensuring fairness and Patna High Court CWJC No.11886 of 2025 dt.09-10-2025

transparency in the tender process. The petitioner, being the

second lowest bidder, does not possess any enforceable legal right

to claim award of the contract merely on the basis of his

willingness to match the L-1 rate. Moreover, in the absence of

mala fide action or manifest arbitrariness, this Court, in exercise of

its writ jurisdiction under Article 226 of the Constitution of India,

finds no justifiable ground to interfere with the considered

decisions of the Technical Bid Evaluation Committee and the

tendering authority.

16. Accordingly, the writ petition is devoid of merit and

is accordingly dismissed, while leaving the respondents free to

proceed with the re-tender process in accordance with law. All

pending I.As if any will be deemed to have been disposed of.

17. There shall be no order as to costs.




                                                        (P. B. Bajanthri, CJ)



                                                       (Alok Kumar Sinha, J)

Prakash Narayan
AFR/NAFR                AFR
CAV DATE                24.09.2025
Uploading Date          09.10.2025
Transmission Date       NA
 

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 

LatestLaws Partner Event : IJJ

 
 
Latestlaws Newsletter