Wednesday, 13, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Sadanand Singh Construction Pvt. Ltd vs The State Of Bihar And Ors
2025 Latest Caselaw 280 Patna

Citation : 2025 Latest Caselaw 280 Patna
Judgement Date : 14 May, 2025

Patna High Court

Sadanand Singh Construction Pvt. Ltd vs The State Of Bihar And Ors on 14 May, 2025

         IN THE HIGH COURT OF JUDICATURE AT PATNA
                   Civil Writ Jurisdiction Case No.9630 of 2017
     ======================================================
     Sadanand Singh Construction Pvt. Ltd. Son of Medni Singh, Resident of
     Village- Dharhara, P.S.- Dharhara Munger.

                                                      ... ... Petitioner/s
                                  Versus
1.   The State Of Bihar through the Secretary Rural Works Department,
     Government of Bihar, Patna
2.   The Chief Engineer- 1, Rural Works Department, Bihar, Patna.
3.   The Chief Engineer- 2, Rural Works Department, Bihar, Patna.
4.   The Superintendent Engineer, Rural Works Department, Work Anchal,
     Munger.
5.   The Executive Engineer, Rural Works Department, Work Division , Munger.

                                                             ... ... Respondent/s

     ======================================================
     Appearance :
     For the Petitioner/s   :     Mr. Uday Prasad Singh, Advocate
     For the Respondent/s   :     Mr. Kumar Alok-SC 7

     CORAM: HONOURABLE JUSTICE SMT. G. ANUPAMA CHAKRAVARTHY

                                ORAL JUDGMENT

                                Date : 14-05-2025


                  1. The petitioner, in the present Writ

      petition, challenges the so-called Award dated

      13.11.2014

passed by the Chairman, Bihar Public

Works Contracts Disputes Arbitration Tribunal in

relation to the executed work titled "Sirasi Mahsar

Kaila Road to Bhadusi Road under P.M.G.S.Y.,

Package No. BR-31.02," vide Agreement No. 1,

PMGSY 2009-10, dated 09.10.2009, on the ground Patna High Court CWJC No.9630 of 2017 dt.14-05-2025

that the said Award lacks any decisive or

conclusive order regarding the executed work and

is, therefore, non est and not legally tenable.

The petitioner further prays for the

issuance of an appropriate writ, preferably in the

nature of mandamus, or any other suitable writ(s),

order(s), or direction(s), commanding the

respondent authorities to release the petitioner's

admitted dues of Rs.1,16,445/- for the completed

work under the aforementioned agreement.

2. The brief facts of the case, according to

the petitioner, are that the petitioner participated

in a tender floated by the respondent authorities

for the work titled "Sirasi Mahsar Kaila Road to

Bhadusi Road under P.M.G.S.Y., Package No. BR-

31.02" (Agreement No. 1, PMGSY 2009-10, dated

09.10.2009), and being the lowest bidder, the

contract was awarded to him. Upon award of the

contract, the petitioner mobilized all necessary

resources and executed the work in the presence

of the site engineer appointed by the respondent.

The execution was verified, and measurements Patna High Court CWJC No.9630 of 2017 dt.14-05-2025

were duly recorded in the Measurement Book

(M.B.) and authenticated by the Assistant

Engineer, as per the terms and conditions of the

agreement.

3. It is submitted on behalf of the

petitioner that running bills for the executed

work, were place before the respondent

authorities for processing them. However, a

portion of the payment, specifically Rs.1,16,445,

was withheld without justification. It is further

submitted that despite repeated requests and

personal visits by the petitioner, the due amount

was not released. The respondent merely sent a

checklist to the higher authorities for fund

allotment, but no conclusive action was taken. The

petitioner had to raise loans on interest, from the

market to execute the work, and due to the non-

payment of dues, he and his family are under

severe financial distress.

4. The Learned counsel for the petitioner

submitted that the petitioner's claim was referred

to the Bihar Public Works Contracts Disputes Patna High Court CWJC No.9630 of 2017 dt.14-05-2025

Arbitration Tribunal (Reference No. 09/12), which

passed an Award dated 13.11.2014. However, the

Award failed to conclusively address the

petitioner's claim of Rs.1,16,445/- even though

the work had been approved by the Site Engineer

and Assistant Engineer. Following the Award, the

petitioner submitted a representation to the

authorities. Although partial payment was

released, the disputed amount of Rs.1,16,445 was

excluded on the ground that no order had been

passed in its favor. Subsequently, the respondents

issued a letter (No. BRFDA(HQ) PMGSY-55/2013-

498 dated 06.02.2017) for the release of funds,

but no payment has been made to date.

5. It is submitted by the Learned counsel

for the petitioner that the non-payment of his

admitted dues is arbitrary, illegal, and

discriminatory, especially as other similarly

situated contractors have been paid. This

constitutes a violation of Article 14 of the

Constitution, due to hostile discrimination and

selective treatment. It is further submitted that Patna High Court CWJC No.9630 of 2017 dt.14-05-2025

the executed work has never been denied by the

respondents.

6. The Learned counsel for the petitioner

submitted that in the interest of justice, equity,

and fair play, the petitioner prays to issue

appropriate directions to the respondents to

release the outstanding dues of Rs.1,16,445/-.

8. A detailed counter affidavit was filed on

behalf of the Respondent Nos. 1 to 5. It is averred

in the counter that the writ petition has been filed

to challenge the Award dated 13.11.2014 passed

by the Chairman, Bihar Public Works Contracts

Disputes Arbitration Tribunal, and seeks a

direction to release the petitioner's alleged dues

of Rs.1,16,445/- with interest, however, the relief

sought is not maintainable.

9. It is further averred in the counter

affidavit that the petitioner did not complete the

assigned work, despite repeated reminders from

the authorities. Consequently, a Checklist dated

03.03.2015 was prepared for administrative

approval of the revised estimate for the same Patna High Court CWJC No.9630 of 2017 dt.14-05-2025

project - "Sirsai-Mahsar-Kalia Road to Bhadusi

Road under PMGSY." The original administrative

approval was granted on 30.03.2008, but due to

the petitioner's disinterest and non-completion of

the work, a revised estimate was submitted. The

petitioner was therefore recommended to be

debarred, as mentioned in the Checklist. The

original estimate was Rs. 62,91,400/-, while the

revised estimate was Rs.92,16,220/-, showing an

increase of Rs. 29,24,820/-, which comes to an

increase of 46.49% without any addition of new

work, solely due to the delay and non-completion

caused by the petitioner.

10. The Learned counsel for the

respondents submitted that the petitioner had

earlier approached the Bihar Public Works

Contracts Disputes Arbitration Tribunal in

Reference Case No. 09/2012, raising similar

claims, including the Rs.1,16,445/- in question.

11. It is further submitted on behalf of the

respondents that the Tribunal was pleased to

pass the following award:

Patna High Court CWJC No.9630 of 2017 dt.14-05-2025

"1. The petitioner shall be entitled to the refund of the Initial Security Deposit Including Earnest Money in the shape of NSE for an amount of Rs. 1,89,500/- (Rs One Lac eighty nine thousand five hundred only).

2. The petitioner shall also be entitled to the payment of recovery amount of deduction towards Security Deposit of Rs. 1,13,555/-(One Lac thirteen thousand three hundred fifty five only) and payment of recovery amount of deduction of for performance Security of Rs. 56,778/- (Rs. Fifty Six Thousand seven hundred seventy eighty) only from running bills.

3. The petitioner shall be entitled to simple interest @ 10 % p.a over the awarded amount award from the date of award.

4. The party shall bear their own cost. Memo of payment may be prepared accordingly."

12. The Learned counsel for the

respondents submitted that the Tribunal gave a

reasoned and final finding, clearly disentitling the

petitioner from any additional amount for Patna High Court CWJC No.9630 of 2017 dt.14-05-2025

executed work. Therefore, his claim of

Rs.1,16,445/- is not maintainable and the

allegations of hostile discrimination are baseless,

as the petitioner's case has already been

adjudicated on merits, and he has been treated in

accordance with the law.

13. It submitted on behalf of the

respondents that in view of the above, the writ

petition is devoid of merit and is fit to be

dismissed.

14. Heard the Learned counsel for the

petitioner as well as the Learned counsel for the

respondents.

15. Based on the facts and circumstances

stated above, this Court is of the considered view

that there is no merit in the case of the petitioner.

This Court does not find any error in the order

dated 13.11.2014 passed by the Chairman, Bihar

Public Works Contracts Disputes Arbitration

Tribunal, Patna. Therefore, the order of the Bihar

Public Works Contracts Disputes Arbitration

Tribunal, Patna is, hereby, confirmed.

Patna High Court CWJC No.9630 of 2017 dt.14-05-2025

16. Accordingly, the writ petition is

dismissed as devoid of merits.

17. Interlocutory Application(s), if any,

shall stands disposed of.

(G. Anupama Chakravarthy, J) Spd/-

AFR/NAFR                NAFR
CAV DATE                NA
Uploading Date          15.05.2025
Transmission Date
 

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter