Citation : 2021 Latest Caselaw 4156 Patna
Judgement Date : 18 August, 2021
IN THE HIGH COURT OF JUDICATURE AT PATNA
REQUEST CASE No.53 of 2020
======================================================
Hindustan Construction Company Ltd. a Company incorporated under the Companies Act, 1956, having its registered office at Hincon House, L.B.S. Marg, Vikhroli (West), Mumbai- 400 083, through its authorized representative Mr. Nilesh Vasant Mekel, son of Vasant Dasharath Mekel, aged about 44 years, Gender- Male, resident of Flat No. G- 2, Building No. C7, Mohan Puram CHS, Kansai Section, Jatale Hospital, Ambernath East, Thane- 421501, Maharashtra.
... ... Petitioner/s
Versus
1. Bihar Rajya Pul Nirman Nigam Limited a Company incorporated under the Indian Companies Act, 1956, having its registered office at 7, Sardar Patel Marg, Patna, Bihar- 800015, through the Managing Director.
2. The Managing Director, Bihar Rajya Pul Nirman Nigam Limited.
3. The Deputy Chief Engineer, South Bihar, Bihar Rajya Pul Nirman Nigam Limited.
4. The Engineer-in- Charge, Works Division- Gaya, Bihar Rajya Pul Nirman Nigam Limited.
... ... Respondent/s ====================================================== Appearance :
For the Petitioner/s : Mr. Nikhil Kumar Agrawal, Advocate Ms. Aditi Hansaria, Advocate For the Respondent/s : Dr. Anand Kumar, Advocate ====================================================== CORAM: HONOURABLE THE CHIEF JUSTICE ORAL JUDGMENT
(The proceedings of the Court are being conducted by Hon'ble the Chief Justice/Hon'ble Judges through Video Conferencing from their residential offices/residences. Also the Advocates and the Staffs joined the proceedings through Video Conferencing from their residences/offices.)
Date : 18-08-2021
This application has been moved seeking appointment
of an Arbitrator invoking the powers of this Court under Section
11(6) of the Arbitration and Conciliation Act, 1996.
There is no dispute about-(a) the legality, validity and
binding effect of the agreement dated 04.03.2014 entered into Patna High Court REQ. CASE No.53 of 2020 dt.18-08-2021
between the parties to the lis; (b) the existence of arbitration clause
contained therein; (c) the existence of dispute(s) arisen therefrom
and (d) the petitioner having put the party to notice of its intent
seeking arbitration under the agreement.
Learned counsel for the petitioner submits that
disputes and differences have arisen under the contract between the
parties dated 4th March, 2014 and as per Clause 25 of the Clauses of
Contract, the petitioner initially filed its claims before the Engineer
in-Charge on 17.05.2019 and thereafter, before the Deputy Chief
Engineer on 15.10.2019. The petitioner also filed an Appeal before
the Managing Director on 12.11.2019. However, no decision has
been taken in the aforesaid claims/appeal filed by the petitioner.
Accordingly, in terms of Clause 25 of Clauses of Contract, an
Arbitrator is required to be appointed as the Managing Director of
the Respondent has failed to decide the Appeal of the petitioner
within time stipulated therein. As such, there is no legal impediment
for this Court in entertaining the present petition and allowing the
same.
The sole ground for resistance of the petition, as
argued in the Court, is non-quantification of the claim. From the
communication dated 10th January, 2020, whereby the petitioner, in
exercise of its right, had named the Arbitrator, the claim stands
quantified. At one place, the figure mentioned is Rs.8883.65 lakhs.
Hence, the contention is misconceived.
Patna High Court REQ. CASE No.53 of 2020 dt.18-08-2021
Hence, this Court is inclined to allow the petition by
appointing an arbitrator.
As such, Hon'ble Mr. Justice Shivaji Pandey, Retired
Judge of the Patna High Court, Patna is appointed as learned
Arbitrator to adjudicate all disputes arising out of agreement dated
04.03.2014 entered into between the parties to the lis.
All pleas and issues raised, on merits, are left open to
be considered and decided by the learned Arbitrator.
Learned Arbitrator shall be entitled to fees as per
the Fourth Schedule of the Arbitration Act.
Since the dispute arises out of an agreement of the
year 2014, the hearing be expedited.
Parties undertake to fully cooperate and not take any
unnecessary adjournment.
The proceedings, during the time of current Pandemic-
Covid-19 shall be conducted through digital mode, unless the
parties otherwise mutually agree to meet in person i.e. physical
mode.
It is expected of the learned Arbitrator to adjudicate
the disputes expeditiously.
Joint Registrar (List) is directed to communicate the
order to the learned Arbitrator.
Learned counsel for the parties also undertake to
communicate the order to the learned Arbitrator. In fact, they Patna High Court REQ. CASE No.53 of 2020 dt.18-08-2021
volunteered to appear before him, through digital mode on 13 th of
September, 2021 and apprise him of the passing of the order.
Parties shall file their statement of claims before the
learned Arbitrator on such date of hearing which he may fix, as per
mutual convenience.
The Request Petition stands disposed of in the above
terms.
Interlocutory Application(s), if any, shall stand
disposed of.
(Sanjay Karol, CJ)
K.C.Jha/-
AFR/NAFR CAV DATE Uploading Date 23.08.2021 Transmission Date
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!