Land Acquisition Officer vs Nityananda Patnaik on 26 September, 2023
            IN THE HIGH COURT OF ORISSA AT CUTTACK
                              L.A.A No.93 of 2003

Land acquisition Officer,            .....                                Appellants
Ganjam, Chhatrapur & Anr.
                                                                Mr.G.N. Rout, ASC
                                     Vs.
Nityananda Patnaik                   .....                               Respondent
                                                           Mr.S.K. Biswal, Advocate

                     CORAM: JUSTICE SANJAY KUMAR MISHRA

                                               ORDER

26.09.2023 Misc. Case No.114 of 2003 & LAA No. 93 of 2003 Order No. This matter is taken up through hybrid mode.

07.

2. Learned Counsel for the parties are present.

3. This Appeal has been preferred against the judgment dated 03.07.2001, passed by the learned Civil Judge (Senior Division), Aska in M.J.C. No.46/96.

4. As it seems from record, though the appeal was presented on 19.06.2003 by the State-Appellants, Misc. Case No.114 of 2003 for condonation of delay was filed on 04.07.2003 .

5. As per the office note, there is a delay of 577 days in filing the present Appeal. The reasons indicated in the Misc. Case for delay in preferring the Appeal are not convincing. That apart, the delay has not been properly explained. Further, though the Application for condonation of delay is pending since 2003, no step was taken by the State-Appellants to expedite the process of disposal of the said petition.

6. The apex Court in the case of Office of the Chief Post Master General & Ors. Vrs. Living Media India Ltd. & Anr. reported in

(2012) 3 SCC 563 observed as under:

"12) It is not in dispute that the person(s) concerned were well aware or conversant with the issues involved including the prescribed period of limitation for taking up the matter by way of filing a special leave petition in this Court. They cannot claim that they have a separate period of limitation when the Department was possessed with competent persons familiar with court proceedings. In the absence of plausible and acceptable explanation, we are posing a question why the delay is to be condoned mechanically merely because the Government or a wing of the Government is a party before us.

Though we are conscious of the fact that in a matter of condonation of delay when there was no gross negligence or deliberate inaction or lack of bonafide, a liberal concession has to be adopted to advance substantial justice, we are of the view that in the facts and circumstances, the Department cannot take advantage of various earlier decisions. The claim on account of impersonal machinery and inherited bureaucratic methodology of making several notes cannot be accepted in view of the modern technologies being used and available. The law of limitation undoubtedly binds everybody including the Government.

13) In our view, it is the right time to inform all the government bodies, their agencies and instrumentalities that unless they have reasonable and acceptable explanation for the delay and there was bonafide effort, there is no need to accept the usual explanation that the file was kept pending for several months/years due to considerable degree of procedural red tape in the process. The government departments are under a special obligation to ensure that they perform their duties with diligence and commitment. Condonation of delay is an exception and should not be used as an anticipated benefit for government departments. The law shelters everyone under the same light and should not be swirled for the benefit of a few. Considering the fact that there was no proper explanation offered by the

Department for the delay except mentioning of various dates, according to us, the Department has miserably failed to give any acceptable and cogent reasons sufficient to condone such a huge delay. Accordingly, the appeals are liable to be dismissed on the ground of delay."

7. Also, in view of the judgment/order of this Court in the case of State of Odisha Vrs. Surama Manjari Das (W.P.(C) No.15763 of 2021 dismissed on 16.07.2021), which has been passed relying on the decision of the Supreme Court in the case of The State of Madhya Pradesh Vrs. Bherulal, reported in 2020 SCC Online SC 849, this Appeal deserves to be dismissed on the ground of delay and laches.

8. Accordingly, Misc. Case as well as Appeal preferred under Section 54 of the Land Acquisition Act, 1894, stand dismissed on the ground of delay and laches.

(S.K.MISHRA) JUDGE Banita

Signature Not Verified Digitally Signed Signed by: BANITA PRIYADARSHINI PALEI Designation: JR. STENOGRAPHER Reason: AUTHENTICATION Location: HIGH COURT OF ORISSA, CUTTACK

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter