Wednesday, 13, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Sibu Kanungo vs State Of Odisha And Others
2023 Latest Caselaw 8148 Ori

Citation : 2023 Latest Caselaw 8148 Ori
Judgement Date : 28 July, 2023

Orissa High Court
Sibu Kanungo vs State Of Odisha And Others on 28 July, 2023
                       ORISSA HIGH COURT: CUTTACK
AFR
                           W.P(C) NO. 1754 OF 2023

          In the matter of an application under Articles 226 and 227
          of the Constitution of India.
                                   ---------------
          Sibu Kanungo                           .....       Petitioner

                                    -versus-

          State of Odisha and others           .....     Opp. Parties


               For petitioner     : Mr. Milan Kanungo,
                                    Sr. Advocate along with
                                    M/s. S.R. Mohanty and
                                    D. Acharya, Advocates.

               For opp. parties   : Mr. P.P. Mohanty,
                                    Addl. Government Advocate

          P R E S E N T:

               THE HONOURABLE DR. JUSTICE B.R.SARANGI
                              AND

THE HONOURABLE MR JUSTICE MURAHARI SRI RAMAN

Date of Hearing: 25.07.2023:: Date of Judgment: 28.07.2023

DR. B.R. SARANGI, J. The petitioner, who is a contractor, has filed

this writ petition challenging the order dated 12.01.2023

under Annexure-7, by which the Executive Engineer,

Nayagrah (R&B) Division, Nayagarh, in pursuance of the

approval of rescission of contract vide letter no.2198 dated

15.11.2022 of the Chief Construction Engineer, Khurdha

(P&B) Circle, Khurdha, has rescinded the contract

agreement no.223P1/2018-19 for the work "Improvement

to Sadar Police Station to Khetribarpur Khandugaon RD

road from 0/0 km to 2/430 km for the year 2017-18" as

per Clause-2(i) of P1 agreement with levy of penalty @ 20%

of the value of leftover work to be realized from the

petitioner-contractor.

2. The factual matrix of the case, in brief, is that

the Chief Construction Engineer, Khurdha (R&B) Circle,

Khurdha-opposite party no-3 invited tender for the work

"Improvement to Sadar Police Station to Khetribarpur

Khandugaon RD Road of Ward No-6 from 0/0 to 2/430 km

vide Bid Identification No.SE/Khurdha (R&B) Circle-

02/2018-19". Pursuant to such tender call notice, the

petitioner participated in the bid and came out successful.

Consequently, on 17.09.2018, an agreement was executed

between the petitioner and opposite party no. 4, vide P1

Agreement No- 223-P1/2018-19.

2.1 After execution of the agreement, the petitioner

moved his men and machineries to start and complete the

work as per the agreement, but, however, due to

encroachments and forcible occupation of land by various

persons, it was difficult on his part to conclude the work.

Even though the petitioner made several requests, vide

letters dated 03.12.2018, 12.02.2019 and 24.03.2019, but

no action was taken by the opposite parties. Ultimately,

opposite party no.4 informed the petitioner that they cannot

evict the encroachments as General Election 2019 was

around the corner and displacement of people would create

hue and cry for the ruling government. Even though an

obligation was cast on the opposite parties to give the land

free of encroachment to undertake the work, they did not

discharge their duties and responsibilities by providing

encroachment free land to undertake the work. The

opposite parties, on 25.01.2021, inspected the entire site

and decided to double the width of the road, i.e., instead of

single lane it was decided to make the road double lane and

accordingly a revised estimate was prepared and finalised

on 24.11.2021. After finalisation of the revised estimate,

opposite party no.4, vide letter no. 6629 dated 24.11.2021,

submitted the revised estimate with deviation statement for

the approval of the higher authority, i.e., opposite party

no.3 and after duly scrutinizing the proposal, opposite

party no.3, vide letter no. 417 dated 04.03.2022, approved

the deviation and accordingly, returned the documents to

opposite party no.4 for starting the double laning of the

road. For revising the work and to give a go ahead to the

petitioner, since the opposite parties took considerable

time, the petitioner mobilised few of his resources to

complete the work under other agreements in order to

achieve his bid capacity. However, when the approval was

accorded by opposite party no. 3, the petitioner immediately

resumed the work basing on which, the running account

was released in favour of the petitioner in the month of

April, 2022 for the work done in the month of March, 2022.

2.2 The petitioner humbly continued the work till the

onset of monsoon, but due to unprecedented rains, it was

very difficult to execute the work as per the revised

estimate, as it was only earthwork and was carried out on

the foothill of the mountain which was hampered by heavy

water flow. After the rain subsided, when the petitioner

moved his men and machineries for resumption of work at

the site, he was verbally stopped by the Assistant Engineer

from doing any work at the site. As a result of thereof, the

petitioner made a grievance before opposite party no. 4 on

20.11.2022. While his grievance was pending, the

petitioner received a letter dated 12.01.2023, whereby

opposite party no. 4 has rescinded the agreement for the

work "Improvement to Sadar Police Station to Khetribarpur

Khandugaon RD road of ward no.6 from 0/0 km to 2/430

km vide Bid Identification No.SE/Khurdha (R&B) Cirlce-

02/2018-19" with a levy of penalty of 20% of the value of

the leftover work. Hence, this writ petition.

3. Mr. Milan Kanungo, learned Senior Advocate

appearing along with Mr. S.R. Mohanty, learned counsel for

the petitioner vehemently contended that the impugned

letter dated 12.01.2023 vide Annexure-7, which has been

issued in rescinding the contract, is arbitrary,

unreasonable and contrary to the provisions of law and

violates the principles of natural justice as the petitioner

has never been served with a notice to show cause and he

has not been given opportunity of hearing before the order

impugned was passed. He further contended that as per the

agreement, which was executed on 17.09.2018, the work

could not be executed, as the authorities proposed to revise

the work. As such, the revised estimate was prepared and

finalised on 04.03.2022 and, thereafter, the petitioner was

allowed to start the work, as the scope of work was

completely changed. He further contended that in one hand

the opposite parties delayed the finalization and approval of

revised work/estimate by three years and on the other

hand in an arbitrary and most unfair manner rescinded the

work granted in favour of the petitioner by attributing the

delay to him in execution of the same. He, therefore,

contended that the actions of the opposite parties are per se

unfair, illegal, arbitrary, discriminatory, abridges the

legitimate expectation and also infringes the statutory and

fundamental rights of the petitioner as guaranteed under

Articles 14, 19 and 21 of the Constitution of India and,

therefore, seeks for interference of this Court.

4. Mr. P.P. Mohanty, learned Addl. Government

Advocate appearing for the State-opposite parties, though

admitted the factual matrix as stated above, contended that

the petitioner failed to complete the work as per his

commitment. Accordingly, the contract rescission proposal

was initiated as per Clause-2(i) of the agreement and got

approved by the competent authority. Therefore, after

rescission of contract, on 20.03.2023, a fresh tender was

issued by the Chief Construction Engineer, Khurda (R&B)

Circle-opposite party no.3. Since the petitioner challenged

the rescission of contract by filing the present writ petition,

on 10.04.2023, the said fresh tender was cancelled by

opposite party no.3. It is further contended that as the

petitioner failed to start the work, for which Contract

Management Meeting was held on 07.12.2018. In the said

meeting, the petitioner had committed to start the work by

13.12.2018, but he did not comply with the same. As a

consequence thereof, a show cause notice was issued vide

letter dated 02.02.2019. In spite of that, the petitioner did

not start the work as per his commitment. Therefore, he

was issued with show cause notices, vide letters no. 4916

dated 18.12.2019, no. 3113 dated 28.04.2020, no. 4185

dated 21.07.2020, no. 3617 dated 04.05.2021 and no. 4101

dated 07.07.2021. In spite of repeated show cause notices,

the petitioner did not take any step to expedite the work to

complete in all respect. He further contended that

inspection was caused by the Chief Engineer (DPI & Roads)

Odisha, Bhubneswar on 25.01.2021. The petitioner was

instructed to improve the road with provision of double lane

instead of single lane with scope of work within agreement

amount. The Contract Management Meeting was held on

08.10.2021 in presence of the petitioner, being the agency,

and other Engineer-in-Charge, where the petitioner

committed to start the work by 16.10.2021 and to submit

the revised work programme by 11.10.2021 prior to start of

the work. Consequently, the revised estimate and deviation

was approved by the Chief Construction Engineer, R&B

Circle, vide letter No.417 dated 04.03.2022. Since the

petitioner did not execute the original quantity of work

provided in the original estimate, the action was taken

against him. It is further contended that the petitioner has

been paid the running account bill time to time, as per

execution of quantity provided in the original agreement

and also the bill was paid to the petitioner for the work

executed during March 2022. The petitioner did not execute

the agreement quantity and was far behind the quantity

provided in the estimate or revised quantity. He has

executed the work for a total amount of Rs. 68,37,781.42

excluding GST (approximately 21% of agreement amount)

up to March 2022. Thereafter, no work has been executed

by the petitioner till rescission of contract. Therefore, the

action taken by the authorities is well justified.

Consequentially, dismissal of the writ petition is sought for.

5. This Court heard Mr. Milan Kanungo, learned

Senior Advocate appearing along with Mr. S.R. Mohanty,

learned counsel for the petitioner and Mr. P.P. Mohanty,

learned Addl. Government Advocate appearing for the

State-opposite parties in hybrid mode and perused the

records. Pleadings have been exchanged between the

parties and with the consent of learned counsel for the

parties, the writ petition is being disposed of finally at the

stage of admission.

6. Before delving into the contentions raised by

learned counsel for the parties, for a just and proper

adjudication of the case, Clause-2(i) of the Conditions of

Contract is quoted herein below:-

"(i) To rescind the contract (of which rescission notice in writing to the contractor under the hands of the Executive Engineer shall be conclusive evidence), 20% of the value of left-over work will be realised from the contractors penalty. (Works Deptt No. 10639, Pt. 27.05.2005)

In the event of above course being adopted by the Executive Engineer the contractor shall have no claim to compensation for any loss sustained by him by reason of his having purchased or procured any materials, or entered into any engagements, or made any advances on account of or with a view to, the execution of the work or the performance of the contract. And in case the contract shall be rescinded under the provisions aforesaid, the contractor shall not be entitled to recover or be paid any sum of any work thereto for actually performed under this contract, unless and until the Executive Engineer shall have certified in writing the performance of such work and the value payable in respect thereof and he shall only be entitled to be paid the value so certified."

On perusal of the aforementioned clause, it is made clear

that to rescind the contract (of which rescission notice in

writing to the contractor under the hands of the Executive

Engineer shall be conclusive evidence) 20% of the value of

left-over work will be realised from the contractor as

penalty. Therefore, for rescinding the contract, an

obligation was cast on the Executive Engineer to give a

rescission notice in writing. Thereby, a condition has been

stipulated for giving prior notice to the contractor.

7. On careful examination of the documents

available on record, there is no dispute that pursuant to the

tender notice invited by the opposite parties, the petitioner

participated and on being selected was allotted with the

work. But, subsequently, the work in question was revised

and instead of single laning road it was decided for double

laning and, as such, the road was encroached by the

unauthorised occupants, which the opposite parties were

under obligation to provide free of encroachments. When

this fact was brought to the notice of the opposite parties,

instead of taking a call on the issue, responsibility was

shifted on the petitioner to evict such unauthorised

occupants and undertake the work including revised work.

Needless to say that the revised work was permitted to be

done by the petitioner only vide letter dated 04.03.2022 by

approving the deviation. Hence, the petitioner was to start

the work, but due to heavy rain, it was not possible on his

part to go with the work immediately. Unfortunately, an

inquiry was conducted behind his back and on the basis of

such inquiry, the order dated 12.01.2023 was passed by

rescinding the contract. Much emphasis was laid by

learned Addl. Government Advocate that petitioner was

issued with four show cause notices of different dates as

pleaded in paragraph-9 of the counter affidavit. But fact

remains, those notices had been issued much prior to

revision of work and, therefore, the same have no bearing to

the present context, since the petitioner was allowed to do

the revised work only in March, 2022 vide letter dated

04.03.2022. It has also been admitted that the petitioner

has executed the work for a total amount of

Rs.68,37,781.42 excluding GST (approximately 21% of

agreement amount) up to March, 2022. Beyond March

2022, no work has been executed by the petitioner till the

order of rescission of contract was issued in January, 2023.

Though reliance was placed on Contract Management

Meeting held on 08.10.2021, where the petitioner

committed to start the work by 16.10.2021, but after that

the petitioner had executed the work amounting to

Rs.26,65,146.00 excluding GST of the agreement amount

during March, 2022. Therefore, when the petitioner is

progressing with the work, on the plea of failure to achieve

the target, a bald statement has been made to the effect to

show that notices were issued to the petitioner giving

opportunity to state his difficulty. But factually no such

show cause notice was served on the petitioner and the

contract rescission proposal was initiated as per Clause-2

(i) of the Conditions of the Contract, which got approved by

the Chief Construction Engineer, by imposing levy of

penalty of 20% on the petitioner. So far as contention

raised and as pleaded in paragraph-9 of the counter

affidavit, that several show cause notices were issued, those

show cause notices had been issued prior to 04.03.2022,

when on a revised estimate the petitioner was to execute

the work from single laning to double laning road. When

the work was in progress, the step for rescission of contract

was taken without complying with the principle of natural

justice.

8. The petitioner has specifically pleaded in

paragraphs-12 and 15 of the writ petition to the following

effect:-

"12. That it is most respectfully submitted that the impugned letter under Annexure-7 has been issued in clear violation of the principles of natural justice as the Petitioner has never been served with a show cause notice and the Petitioner has not been heard before passing of the impugned order. This ground alone makes the order liable to be quashed and set aside by this Hon'ble Court.

15. That the actions of the Opp. Parties are in clear violation of the principles of natural justice and oozes malafide. This shows the arbitrary nature with which the Petitioner has been dealt with and acted upon. Hence. the impugned order as under Anncxure-7 is liable to be quashed and set aside."

9. In the reply to the same, the State-opposite

parties, in their counter affidavit, have stated in

paragraphs-14 and 16 to the following effect:-

"14. That the averments made in paragraph No.12 of writ petition are disputed and denied. It is humbly submitted that in spite of several letters issued to the petitioner, he never heed to keep the progress of the work. After conduct of several contract management meeting and several Show Cause Notices issued to the petitioner, finally the contract was rescinded under clause 2 (i) of the agreement with imposition of penalty @ 20% of value of left over work. Thereby the rescission of the contract under clause 2 (i) of the agreement does not violate the principle of natural justice.

All other allegations/ averments made in this paragraph are hereby disputed and denied.

16. That the averments made in paragraphs No. 15, 16, 17 and 18 of the writ application shall be dealt with at the time of hearing."

10. From the above pleadings available on record, it

is made clear that in reply to the contention raised by the

petitioner, that there was non-compliance of the principles

of natural justice, it has only been stated by the State-

opposite parties that the action was taken under Clause-2(i)

of the agreement, which cannot be construed to be

compliance of the principles of natural justice. In absence

of an effective reply to the pleading made on behalf of the

petitioner, it is deemed that the same has been admitted by

the opposite parties. It is trite that a fact admitted need not

be proved. An admission of fact in the written

statement/counter need not be proved, reason being an

admission is concession or voluntary acknowledgement

made by a party or someone identified with him in legal

interest of the existence of certain fact which are in issue or

relevant to an issue in the case. The predominant

characteristic of this type of evidence consists in its binding

characters.

11. Admissions are broadly classified into two

categories; (a) Judicial admissions; and (b) Extra-judicial

admissions. Judicial admissions are formal admissions

made by a party during the proceedings of the case. Extra-

judicial admissions are informal admissions not appearing

on the record of the case. The former are fully binding on

the party that makes them. They constitute a waiver of

proof.

12. Section 58 of the Evidence Act confines to

judicial admission such as admission by pleadings. It

normally relates to agreed statements of facts made

between both parties to save time and expenses at a trial.

13. The basic principle under Order 6 Rule 5 of CPC

is that every allegation of fact in the plaint must be taken

as admitted unless denied or stated to be not admitted in

the pleading of the defendant. Hence, where there is no

pleading of the defendant, there can be no denial or non-

admission on his part and he is bound by all the allegations

in the plaint.

14. Section 3 (vi) of the Debts Recovery Tribunal

Regulations of Practice, 1997 also clarifies that pleading

shall include original applications, reply statements,

rejoinders and additional statements supplementing the

original applications and reply statement as may be

permitted by the tribunal.

15. In Vidyawati Gupta v. Bhakti Hari Nayak,

(2006) 2 SCC 777, the apex Court held that the word

'pleadings' under Order VI Rule 1 and Order VII of the Code

means 'plaint' or written statement.

16. In K. Laxmanan v. Thekkayil Padmini, (2009)

1 SCC 354, the apex Court held that 'pleadings' consist

only of a plaint and a written statement. A replication if

filed by plaintiff and allowed by the Court would be a part

of 'pleadings'.

'Pleadings' include particulars and a 'pleading'

must state only facts and not law.

17. In M. Venkataramana Hebbar (Dead) by LRS v.

M. Rajagopal Hebbar & others, (2007) 6 SCC 401, the

apex Court held the averments made in the plaint not been

denied in the written statement, the said averment is

deemed to be admitted. Therefore, in terms of Section 58 of

the Evidence Act, facts admitted need not be proved.

Therefore, the Court was entitled to draw the inference that

the same has been admitted.

18. In Jaspal Kaur Cheema and another v.

Industrial Trade Links and others, (2017) 8 SCC 592,

the apex Court held that the defendant in the written

statement must categorically deny or dispute the averments

made in the plaint, as evasive denial would amount to an

admission of the allegation made in the plaint.

19. Applying the said analogy to the present case, it

is made clear that when a specific plea has been taken by

the petitioner in the writ petition at paragraphs-12 and 15,

as quoted above, the manner in which the opposite parties

have replied in their counter affidavit at paragraphs 14 and

16 is absolutely evasive one, which cannot be accepted.

Therefore, an inference can be drawn that the principle of

natural justice has not been complied with while issuing

the letter under Annexure-7 dated 12.01.2023 in rescinding

the contract.

20. The essential of compliance of natural justice is

nothing but a duty to act fairly. Natural justice is an

antithesis of arbitrariness. It, therefore, follows that audi

alteram partem, which is facet of natural justice is a

requirement of Art.14.

The word 'nature' literally means the innate

tendency or quality of things or objects and the word 'just'

means upright, fair or proper. The expression 'natural

justice' would, therefore, mean the innate quality of being

fair.

Natural justice, another name of which is

common sense of justice, is the name of those principles

which constitute the minimum requirement of justice and

without adherence to which justice would be a travesty.

Natural justice accordingly stands for that fundamental

quality of fairness which being adopted, justice must not

only be done but also appears to be done.

The soul of natural justice is "fair play in action".

21. In HK (An Infant) in re, 1967 1 All ER 226 (DC),

Lord Parker, CJ, preferred to describe natural justice as 'a

duty to act fairly'.

22. In Fairmount Investments Ltd. v. Secy. of

State for Environment, 1976 2 All ER 865 (HL), Lord

Russel of Killowen somewhat picturesquely described

natural justice as 'a fair crack of the whip'.

23. In R. v. Secy. Of State for Home Affairs, ex p.

Hosenball, Geoffrey Lane, LJ, 1977 3 All ER 452 (DC & CA),

preferred the homely phrase 'common fairness' in defining

natural justice.

24. In Ridge v. Baldwin, (1963) 2 SLL RT 66 at 102,

Lord Morris of Borth-y-Gest observed that "it is well

established that the essential requirements of natural

justice at least include that before someone is condemned

he is to have an opportunity of defending himself, and in

order that he may do so that he is to be made aware of the

charges or allegations or suggestions which he has to meet

... My Lords, here is something which is basic to our

system: the importance of upholding it far transcends the

significance of any particular case".

25. In Byrne v. Kinematograph Renters Society

Ltd, (1958) All ER 579, while considering the requirements

of natural justice, Justice Narman, J said. "........First, I

think that the person accused should know the nature of

the accusation made; secondly, that he should be given an

opportunity to state his case; and thereby, of course, that

the tribunal should act in good faith. I do not think that

there really is anything more".

26. In Russel v. Duke of Norfolk, (1949) 1 All ER

109, Tucker, LJ, observed that one essential is that the

person concerned should have a reasonable opportunity of

presenting his case. The view of Tucker, LJ, in Russell's

case (supra) has been approved by the Supreme Court of

India in Rattan Lal Sharma v Managing Committee,

(1993) 4 SCC 10 : AIR 1993 SC 2115.

27. In General Medical Council v. Spackman,

(1943) AC 627, Lord Wright pointed out that it should give

a full and fair opportunity to every party being heard.

28. In A.K. Kraipak and others v. Union of India,

AIR 1970 SC 150: (1969) 2 SCC 262, is a landmark in the

growth of this doctrine. Speaking for the Constitution

Bench, Hegde, J. observed thus:

"If the purpose of the rules of natural justice is to prevent miscarriage of justice one fails to see why those rules should be made inapplicable to administrative enquiries. Often times it is not easy to draw the line that demarcates administrative enquiries from quasi-judicial enquiries. Enquiries

which were considered administrative at one time are now being considered as quasi-judicial in character. Arriving at a just decision is the aim of both quasi-judicial enquiries as well as administrative enquiries. An unjust decision in an administrative enquiry may have far reaching effect than a decision in a quasi-judicial enquiry".

In Maneka Gandhi v. Union of India, AIR 1978

SC 597 : (1978) 1 SCC 248, law has done further blooming

of this concept. This decision has established beyond doubt

that even in an administrative proceeding involving civil

consequences doctrine of natural justice must be held to be

applicable.

29. In Swadeshi Cotton Mills v. Union of India,

AIR 1981 SC 818, the meaning of 'natural justice' came for

consideration before the apex Court and the apex Court

observed as follows:-

"The phrase is not capable of a static and precise definition. It cannot be imprisoned in the straight- jacket of a cast-iron formula. Historically, "natural justice" has been used in a way "which implies the existence of moral principles of self evident and urarguable truth". "Natural justice" by Paul Jackson, 2nd Ed., page-1. In course of time, judges nurtured in the traditions of British jurispruduence, often invoked it in conjuction with a reference to "equity and good conscience". Legal experts of earlier generations did not draw any distinction between "natural justice" and "natural law".

"Natural justice" was considered as "that part of natural law which relates to the administration of justice."

30. In Basudeo Tiwary v Sido Kanhu University

and others (1998) 8 SCC 194, the apex Court held that

natural justice is an antithesis of arbitrariness. It, therefore,

follows that audi alteram partem, which is facet of natural

justice is a requirement of Art.14.

31. In Nagarjuna Construction Company Limited

v. Government of Andhra Pradesh, (2008) 16 SCC 276,

the apex Court held as follows:

"The rule of law demands that the power to determine questions affecting rights of citizens would impose the limitation that the power should be exercised in conformity with the principles of natural justice. Thus, whenever a man's rights are affected by decisions taken under statutory powers, the court would presume the existence of a duty to observe the rules of natural justice. It is important to note in this context the normal rule that whenever it is necessary to ensure against the failure of justice, the principles of natural justice must be read into a provision. Such a course is not permissible where the rule excludes expressly or by necessary intendment, the application of the principles of natural justice, but in that event, the validity of that rule may fall for consideration."

32. The apex Court in Uma Nath Panday and

others v State of U.P. and others, AIR 2009 SC 2375,

held that natural justice is the essence of fair adjudication,

deeply rooted in tradition and conscience, to be ranked as

fundamental. The purpose of following the principles of

natural justice is the prevention of miscarriage of justice.

33. In Mohinder Singh Gill v. The Chief Election

Commissioner, AIR1978 SC 851 : (1978) 1 SCC 405, the

apex Court held that natural justice is treated as a

pervasive facet of secular law where a spiritual touch

enlivens legislation, administration and adjudication, to

make fairness a creed of life. It has many colours and

shades, many forms and shapes and, save where valid law

excludes, it applies when people are affected by acts of

Authority. It is the bone of healthy government, recognised

from earliest times and not a mystic testament of judge-

made law. Indeed, from the legendary days of Adam-and of

Kautilya's Arthasastra-the rule of law has had this stamp of

natural justice which makes it social justice.

34. In Bhagwan v. Ramchand, AIR 1965 SC 1767:

(1965) 3 SCR 218, the apex Court held that the rule of law

demands that the power to determine questions affecting

rights of citizens would impose the limitation that the power

should be exercised in conformity with the principles of

natural justice.

35. In Sukdev Singh v Bhagatram, AIR 1975 SC

1331: (1975)1 SCC 421, the apex Court held that whenever

a man's rights are affected by decisions taken under

statutory powers, the court would presume the existence of

a duty to observe the rules of natural justice.

36. In view of the facts and law, as discussed above,

it is made clear that while issuing letter no. 243 dated

12.01.2023 in rescinding the contract, there was gross

violation of the principles of natural justice, which has been

admitted in the pleadings made in the counter affidavit filed

by the opposite parties. Therefore, in view of the clear

admission made by the opposite parties in their counter

affidavit, this Court has no hesitation to hold that the

impugned order issued under Annexure-7 dated

12.01.2023 cannot be sustained in the eye of law and the

same is liable to be quashed and is hereby quashed.

37. In the result, therefore, the writ petition stands

allowed. But, however, under the circumstances of the

case, there shall be no order as to costs.





                                                                       (DR. B.R. SARANGI)
                                                                             JUDGE

           M.S. RAMAN, J.                        I agree.


                                                                          (M.S. RAMAN)
                                                                              JUDGE



                            Orissa High Court, Cuttack
                            The 28th July, 2023, Arun




Signature Not Verified
Digitally Signed
Signed by: ARUN KUMAR MISHRA

Designation: ADR-cum-Addl. Principal Secretary Reason: Authentication Location: Orissa High Court Date: 28-Jul-2023 16:19:38

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter