Citation : 2023 Latest Caselaw 250 Ori
Judgement Date : 6 January, 2023
IN THE HIGH COURT OF ORISSA AT CUTTACK
WP(C) No.13536 of 2016
Rajashree Gajendra .... Petitioner
-versus-
State of Odisha and others .... Opposite Parties
Advocates appeared in this case :
For Petitioner : Mr. Sarat Kumar Gajendra, Sr. Advocate
Mr. L. Pradhan, Advocate
Mr. D. P. Das, Advocate
Mr. B. P. Das, Advocate
For Opposite Parties : Mr. Y.S.P. Babu, AGA
CORAM:
JUSTICE ARINDAM SINHA
JUSTICE SANJAY KUMAR MISHRA
JUDGMENT
06.01.2023
ARINDAM SINHA, J.
1. Mr. Gajendra, learned senior advocate appears on behalf of
petitioner and Mr. Babu, learned advocate, Additional Government
Advocate, for State. The writ petition was moved before us on 21st
WP(C) no.13536 of 2016 // 2 //
November, 2022, when Mr. Gagendra, submitted, his client had
applied for allotment of Acs.2.5 decimals of land under Odisha
Industrial Policy, 1996, for setting up a hotel. Initially a plot was
allotted but possession could not be given. Subsequently, another
plot at an alternate site was allotted, of area Ac.1.285 decimals and
given possession. Area of the plot being wholly insufficient for the
project contemplated and land applied, his client sought allotment of
the balance project land, as additional land. He adds, the project was
duly recommended. The additional land will also serve as access to
the national highway.
2. In spite of best efforts of his client to obtain allotment of the
balance land, on their having had been recommendation by officers
in the Government that such land was necessary, the application was
rejected by order dated 26th December, 2009 passed by The Hon'ble
Chief Minister. This was challenged by his client in W.P(C) no.1576
of 2010 resulting in judgment dated 6th April, 2011. He draws
attention to the judgment to show the reasons, on which impugned
therein order of The Hon'ble Chief Minister was set aside and
quashed.
// 3 //
3. Subsequent to said judgment there was another judgment
dated 24th February, 2012 in W.P.(C) no.19834 of 2011, whereby,
inter alia, view taken was that prayer of his client for allotment of
additional land for construction of road between the national
highway and already allotted plot, is not unjustified.
4. His client preferred special leave petition being Special
Leave to Appeal (C) no.7964 of 2014, disposed of on order dated 2nd
July, 2014. Text of the order is reproduced below.
"Delay condoned.
We have heard learned counsel for the petitioner. We are not inclined to interfere with the impugned order because the High Court has remanded the matter to the State Government for consideration of the claim of the petitioner. We are confident that the State Government will consider the representation of the petitioner taking into account the observations of the High Court.
The special leave petition is disposed of."
(emphasis supplied)
5. Notwithstanding, impugned order dated 10th March, 2016
was made, once again rejecting his client's application for additional
// 4 //
land. Submission was, the order does not bear reasons. There should
be direction compelling the authorities to allot the land, on quashing
impugned order.
6. 7th December, 2022 Mr. Gajendra had drawn attention to
order made earlier on 21st November, 2022. We reproduce paragraph
6 from said order.
"6. We have perused, inter alia, impugned order. Prima facie, it appears, recommendation no.1 is the reason for rejection. The recommendation is reproduced below.
"1. The team verified feasibility to provide 2nd road connectivity from the south side (NH-5) of the hotel site. But the team did not consider it proper as it would pose serious problem for maintenance and repair of heavy water pipe line passed to the nearby high level water tank.
Executive Engineer, GPEO have raised objection for using the site for road purpose in his letter No.19283 dtd. 1.11.2014."
Mr. Babu had submitted, his instructions were, additional land
cannot be allotted to petitioner for construction of road in view of
the reason reproduced above.
7. Mr. Gajendra then drew attention to certificate dated 12th
// 5 //
April, 2019 containing opinion of Chief Engineer (Roads and
Building) Retd., engaged by petitioner. The opinion is extracted
and reproduced below.
"During my visit, I saw construction of a massive structure of the Hotel building in progress. For reaching the spot of the Hotel site I had to go on the Industrial Estate road on the back side of the allotted land site and take a turn to reach the Water supply Pump house gate over a vacant space which is being used as ingress and outgress for the purpose of building construction. There is no direct access of the Hotel building to the service road of N.H. No.5. If a 40 ft. or 50 ft wide road would be constructed from the Hotel building site of Smt. Rajashree Gajendra on the adjoining Southern side Govt. vacant land crossing the water supply pipe line with minimum 1 ft height over it there shall be absolutely no difficulty for maintenance of that stretch of pipe line nor any damage would be caused."
(emphasis supplied)
8. On that date (7th December, 2022) there was direction upon
State to file additional affidavit dealing with the certificate. State filed
additional affidavit dated 20th December, 2022 affirmed by Deputy
Director of Estates General Administration and Public Grievance
Department. The affidavit carries disclosure being undated field
// 6 //
inspection report. Today, Mr. Babu relies on it as State's contention to
oppose prayers in the writ petition. We have perused the disclosure in
said affidavit. The disclosure carries findings and recommendations
made by four persons, who had signed the report. We extract and
reproduce the recommendations.
"1. The team verified feasibility to provide 2nd connectivity from the south side (NH-5) of the hotel site. But the team did not consider it proper as it would pose serious problem for maintenance and repair of heavy water pipe line passed to the nearby high level water tank. Executive Engineer, GPEO have raised objection for using the site for road purpose in his letter No.19283 Dated 1.11.2014.
2. Further, the committee felt that the lessee has kept the land idle for a long time. Moreover, several hotels at Bhubaneswar having less than one Acre of land have been established in the limits of BMC. So the committee did not consider it fit and proper to recommend for allotment of additional land due to scarcity of government land for public purpose within the limits of BMC."
9. Petitioner has prayed for quashing impugned order dated
10th March, 2016 and for direction upon the authority to make
allotment of balance required extent of land of Ac. 1.215 decimals,
out of which area of Ac. 0.950 decimals is available adjoining to the
// 7 //
northern side and an area of Ac.0.265 decimals is available adjoining
to the southern side of petitioner's allotment.
10. Hearing of the writ petition on earlier two occasions resulted
in our aforesaid direction upon State to file additional affidavit, which
has been filed. As aforesaid, contention of State for opposing the
prayer are the recommendations made in the undated field inspection
report, the two recommendations reproduced above. We have perused
the recommendations. The authors of the report in so recommending,
themselves appear as not convinced on recommendation no.1, to have
giving recommendation no.2 for additional support to recommendation
no.1. The second recommendation says, further the committee felt that
the lessee has kept the land idle for a long time, which is why the
committee did not consider it fit or proper to recommend allotment of
additional land due to scarcity of Government land for public purpose
within the limits of Bhubaneswar Municipal Corporation (BMC).
11. The affidavit was called for from State because petitioner had
relied on certificate dated 12th April, 2019, relevant content of which
also stands extracted above. There has no scope for State to contend
in the alternative. In event they wanted Court to uphold their reasons
// 8 //
for rejecting petitioner's claim for additional allotment, the reasons
had to be good ones. The first reason appears to be based on objection
regarding maintenance of underground water pipe. That reason would
not allow the land on the southern side of petitioner's allotment to be
used as access to her plot or for that matter to be used as access for
any purpose since, access would, according to the report, pose serious
problems for maintenance and repair of heavy water pipe line passed
to the nearby high level water tank. Thus, the second reason citing
scarcity of availability of Government land for public purpose
militates against the first.
12. There has been no attempt to dispute contents of the
certificate by an expert, deponent of said affidavit not being one and
having had relied on the undated field inspection report. The report
does not deal with the opinion. Secondly, inclusion of the second
recommendation as alternative case weakened the contention
regarding damage to water pipe being reason for rejection of the
claim for allotment of additional land on southern side of petitioner's
allotment, for purpose of access to it.
// 9 //
13. Impugned order dated 10th March, 2016 is set aside and
quashed. Opposite party no.1 is directed to forthwith allot the
additional land on southern side of petitioner's allotment, since State
had only considered granting it on that side. The additional allotment
is to be made and must be informed to petitioner, within four weeks
of communication.
14. The writ petition is allowed and disposed of.
( Arindam Sinha ) Judge
( S. K. Mishra ) Judge
P.K. Sahoo
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!