Citation : 2023 Latest Caselaw 9932 Ori
Judgement Date : 24 August, 2023
IN THE HIGH COURT OF ORISSA, CUTTACK
CRLA No.594 of 2010
An appeal under section 374 Cr.P.C. from the judgment and
order dated 19.11.2010 passed by the Special Judge (Vigilance),
Balasore in T.R. Case No.261 of 2007.
----------------------------
Bana Bihari Das ......... Appellant
-Versus-
State of Odisha (Vigilance) ......... Respondent
For Appellant: - Ms. Tejasmita Mohapatra
Advocate
For Respondent: - Mr. M.S. Rizvi
Addl. Standing Counsel
(Vigilance)
----------------------
P R E S E N T:
THE HONOURABLE MR. JUSTICE S.K. SAHOO
------------------------------------------------------------------------
Date of Hearing and Judgment: 24.08.2023
------------------------------------------------------------------------
S.K. SAHOO, J. The appellant Bana Bihari Das faced trial in the Court
of learned Special Judge (Vigilance), Balasore in T.R. Case
No.261 of 2007 for offences punishable under section 13(2) read
with section 13(1)(c) of the Prevention of Corruption Act, 1988
(hereinafter „1988 Act‟) on the accusation that being a public // 2 //
servant functioning as Junior Engineer, Jaleswar Irrigation Sub-
Division attached to Section-I from 18.10.1987 to 22.07.1992
received M.S. rods of different sizes weighing Q.4.03 kgs. from
the contractor K.C. Ray and on inventory, on 17.02.1995 a
shortage of M.S. rods came to Q.3.73 kgs. worth of Rs.5,000/-
(rupees five thousand) which have been dishonestly or
fraudulently misappropriated and otherwise converted to his own
use entrusted upon him or under his control as a public servant.
The appellant was further charged under section 409 of the
Indian Penal Code (hereinafter „the I.P.C.‟) on the accusation
that he being a public servant and entrusted with M.S. rods of
different sizes weighing Q.4.03 kgs. during the aforesaid period
committed criminal breach of trust in respect of the said
property worth of Rs.5,000/- (rupees five thousand) i.e. iron
rods of different sizes.
The learned trial Court vide impugned judgment and
order dated 19.11.2010 has been pleased to hold the appellant
guilty of both the charges and sentenced him to undergo R.I. for
two years on each count for the offences under section 13(2)
read with section 13(1)(c) of the 1988 Act and section 409 of
the I.P.C. and he was further directed to pay a fine of Rs.5,000/-
(rupees five thousand), in default, to undergo further S.I. for a
// 3 //
term of four months and both the substantive sentences of
imprisonment were directed to run concurrently.
The Prosecution Case:
The prosecution case, as per the F.I.R. lodged by
Kartik Chandra Biswal (P.W.9) before the Superintendent of
Police, Vigilance, Balasore, is that he received information about
misappropriation of Q.4.03 kgs. of iron rods worth of Rs.5,000/-
(rupees five thousand) by the appellant and accordingly,
conducted an enquiry which revealed that the appellant while
posted as Junior Engineer, Jaleswar Irrigation Section-I received
the steel and iron rods from one B.C. Dey, contractor on
02.12.1989 and those rods were (i) 10 mm dia steel Q.0.58
kgs., (ii) 8 mm dia M.S. rod Q.0.25 kgs., (iii) 16 mm dia M.S.
rod Q.0.94 kgs. and (iv) 22 mm dia M.S. rod Q.2.26 kgs. and
the total comes to Q.4.03 kgs. It is further case of the
prosecution, as per the F.I.R. that the aforesaid quantity of rods
were received by the appellant on 02.12.1989 and till
23.07.1992, he had not issued the same for any construction
work from the date of receipt. On 23.07.1992, the appellant
handed over the complete charge of Jaleswar Irrigation Section-I
to Shri Anil Kumar Panda (P.W.2), J.E. and however, the steel
and M.S. iron rod were not handed over to P.W.2 and therefore,
// 4 //
the appellant being a public servant committed criminal
misconduct and dishonestly misappropriated Q.4.03 kgs. of M.S.
iron rods worth of about Rs.5,000/- (rupees five thousand)
abusing his official position.
P.W.10 Apurba Kumar Ash, who was the O.I.C. of
Vigilance Police Station, Balasore, as per the direction of the
Superintendent of Police, Vigilance, Balasore registered the case
and handed over the charge of investigation to Shri Kartik
Chandra Biswal (P.W.9) for investigation.
P.W.9 after taking over the charge of investigation,
examined the witnesses, seized certain documents, prepared the
seizure list (Ext.17) and visited the spot on 30.09.1994 and
handed over the charge of investigation to Shri Apurba Kumar
Ash (P.W.10).
After taking over the charge of investigation again,
P.W.10 submitted requisition to the Executive Engineer,
Irrigation Division, Balasore and the S.D.O., Irrigation Sub-
Division, Jaleswar about the charge papers between the
appellant and P.W.2 and on 02.01.1995, he seized certain
documents, namely, copy of charge papers in between the two
and letter no.16 of Executive Engineer, Irrigation Division,
Balasore and prepared the seizure list vide Ext.16. The charge
// 5 //
papers bear the signatures in original of both the appellant as
well as P.W.2 and it was found that on 23.07.1992, the appellant
handed over the charge to P.W.2 and from the letter of the
Executive Engineer, Irrigation Division, Balasore, the valuation of
different iron rods were furnished and the same is marked as
Ext.11. Ext.10 is the register in which the appellant had
mentioned the amount of rods which he had received from the
department and page nos.32 and 33 in the said register marked
as Ext.10/1 which revealed that the appellant handed over the
charge of excess rods to himself on 23.07.1992. The
Investigating Officer examined the witnesses, conducted
inventory of the office room of P.W.2. During inventory, iron
rods of different sizes were found inside the store room and
accordingly, the inventory report was prepared mentioning the
quantity, value and sizes of the iron rods and the said inventory
report is marked as Ext.5. The iron rods found inside the store
room were seized and a seizure list was prepared marked as
Ext.6 and the Investigating Officer left the rods in the zima of
Kashinath Mishra (P.W.1), Assistant Engineer of Jaleswar
Irrigation Sub-Division on due execution of a zimanama by him.
The original letter of the S.D.O., Irrigation Sub-Division,
Jaleswar and the original explanation of the appellant pursuant
// 6 //
to such letter were also seized as per the seizure list marked as
Ext.8 and some other letters were also seized from the Office of
the S.D.O., Irrigation Sub-Division, Jaleswar on 22.04.1995 and
the I.O. prepared the seizure list marked as Ext.18. He also
seized four letters from the Office of the Executive Engineer,
Balasore Irrigation Division and prepared the seizure list marked
as Ext.21. Brundaban Chandra Dey, the contractor who executed
the construction work of Guasanala Irrigation Creek at village
Kharidchhak was also examined. The I.O., as per the direction of
the Superintendent of Police, Vigilance, met the Chief Engineer,
Irrigation to obtain sanction for prosecution against the appellant
and he discussed the facts of the case, produced all the relevant
papers and documents of the case for his perusal and on
19.01.1996, he received the sanction order through the
Superintendent of Police, Vigilance, Balasore, which is marked as
Ext.22. The appellant was arrested and he was released on bail.
On completion of investigation, P.W.10 submitted charge sheet
against the appellant for commission of offences under section
13(2) read with section 13(1)(c)(d) of the 1988 Act and section
409 of the I.P.C. on the accusation that the appellant while
posted as the J.E. had misappropriated a sum of Rs.4,525/-
// 7 //
(rupees four thousand five hundred twenty five) towards the
cost of the iron rods.
The appellant while not disputing that he received
the surplus M.S. rods of Q.4.03 kgs. of different sizes from
contractor Brundaban Chandra Dey, in his accused statement to
question no.3 stated that he had handed over the charge of the
iron rods to P.W.2. It is his specific stand in the defence plea
that he has not misappropriated any rods and he has been
falsely implicated in the case.
Witnesses & Exhibits:
In order to prove its case, the prosecution examined
ten witnesses.
P.W.1 Kashinath Mishra was the S.D.O., Irrigation at
Jaleswar and he is a witness to the seizure and after seizure of
M.S. rods from the office of P.W.2, the seized rods were given in
his zima vide zimanama Ext.7.
P.W.2 Anil Kumar Panda was the Junior Engineer,
Jaleswar Section-I. He stated that he took charge of his post
from the appellant on 23.07.1992 and at the time of handing
over charge, the appellant did not hand over charge of some
articles which have been categorically mentioned in the charge
report.
// 8 //
P.W.3 Naba Kumar Pani was the Junior Clerk in the
Office of the Executive Engineer, Irrigation Division, Balasore
and he is a witness to the seizure of charge papers of handing
over and taking over charge between the appellant and P.W.2 so
also one letter issued by Executive Engineer.
P.W.4 Naba Kumar Mohanty was the Wage Earner
Khalasi in Irrigation Sub-Division Office, Jaleswar and he is a
witness to the seizure of charge paper of the appellant and site
account exercise book and some other documents as per seizure
list Ext.17.
P.W.5 Harekrushna Mohanty was the B.D.O. at
Jaleswar and he stated that on the basis of requisition in
connection with an inventory by the Vigilance Department, he
had gone to the Irrigation Office, Jaleswar and in his presence,
inventory was conducted in the office of P.W.2.
P.W.6 Muralidhar Dhal was the Executive Engineer of
the Irrigation Division, Balasore, who stated to have sent one
letter to the Vigilance Police, Balasore and forwarded the letter
of P.W.2 under his letter.
P.W.7 Subash Chandra Dixit was the cashier in
Jaleswar Irrigation Sub-Division and he is a witness to the
// 9 //
seizure of iron rods and some letters as per the seizure lists
Exts.6 and 8 respectively.
P.W.8 Kirtan Chandra Patra was the Junior Engineer
in Jaleswar Irrigation Sub-Division and he is a witness to the
seizure of some letters and documents as per the seizure lists
Exts.18 and 19 respectively.
P.W.9 Kartika Chandra Biswal was the Inspector,
Vigilance Unit, Jaleswar and he is the informant in the case and
also the initial investigating officer of the case and upon his
transfer, he made over the charge of investigation to Inspector
Apurba Kumar Ash (P.W.10) on 05.12.1994.
P.W.10 Apurba Kumar Ash was the Officer in-charge
of Vigilance police station, Balasore, who took over investigation
of the case from P.W.9 as per direction of the Superintendent of
Police, Vigilance, Balasore and on completion of investigation, he
submitted charge sheet against the appellant.
The prosecution exhibited twenty two documents.
Ext.1 is the letter dated 15.03.1993 of P.W.2 to the S.D.O.
regarding deficit of M.S. rods of different diameter, Ext.2 is the
letter dated 27.11.1992 of P.W.2 to S.D.O., Ext.3 is the letter
no.625 dated 30.11.1992, Ext.4 is the letter dated 04.12.1992
to the S.D.O. reply, Ext.5 is the inventory list, Exts.6, 8, 16, 17,
// 10 //
18 and 21 are the seizure lists, Ext.7 is the zimanama, Ext.9 is
the charge report, Ext.10 is the site account register, Ext.10/1 is
the entry in page-13 of Ext.10, Ext.10/2 is the pages 6 and 7 of
Ext.10, Ext.11 is the letter of Executive Engineer to the Vigilance
Department, Ext.12 is the letter of S.D.O. to B.B. Das, Ext.13 is
the report of peon, Ext.14 is the letter dated 27.01.1992, Ext.15
is the letter no.22 dated 15.03.1993, Exts.19 & 19/1 are the
documents seized under Ext.18, Ext.20 is the written F.I.R. and
Ext.22 is the sanction order.
Two witnesses have been examined on behalf of the
defence.
D.W.1 Swapneswar Jena, who was working as
N.M.R. in Section-I of Jaleswar Irrigation Sub-Division, stated
that on 23.07.1992, the appellant was relieved by his successor
(P.W.2) and charge was handed over by the appellant and taken
over by P.W.2 and charge papers were scribed by P.W.2 and the
appellant was showing the articles.
The appellant has examined himself as D.W.2.
The defence exhibited five documents. Ext.X is the
charge report, Ext.Y is the signature of the appellant at page-12,
Ext.A is the answer of P.W.6 to the query of Vigilance police,
// 11 //
Ext.B is the signature of P.W.2 on the letter, Ext.C is the charge
report which was earlier marked „X‟.
Findings of the Trial Court:
The learned trial Court, after assessing the oral as
well as documentary evidence on record, has been pleased to
hold that on 23.07.1992, the appellant handed over the charge
to his successor (P.W.2). It was further held that the prosecution
has established that the appellant had with him the surplus iron
rods on the day as he handed over the charge to his successor
(P.W.2) but he also took the plea that he handed over the said
iron rods to his successor. It was further held that Ext.C has to
be discarded as it does not reveal that the surplus iron rods were
handed over by the appellant to P.W.2. It was further held that
the appellant did not hand over the iron rods in question to
P.W.2 on 23.07.1992 at the time of handing over the charge. It
was further held that the materials available on record and the
false defence of the appellant cumulatively establish that he
criminally misappropriated Q.4.03 kgs. of iron rods received by
him after conclusion of the work in question. The learned trial
Court further held that non-examination of the sanctioning
authority is not fatal to the prosecution and there was a valid
sanction for prosecution of the appellant and in the ultimate
// 12 //
analysis, it was held that the prosecution has succeeded in
establishing the guilt of the appellant for both the charges.
Contentions of the Parties:
Ms. Tejasmita Mohapatra, learned counsel appearing
for the appellant challenging the impugned judgment contended
that though it is the prosecution case that the appellant received
the iron rods in question from one Brundaban Chandra Dey, but
in the charge, it has been mentioned that he received the same
from one K.C. Ray. Neither K.C. Ray nor Brundaban Chandra
Dey has been examined during trial to substantiate that they
handed over Q.4.03 kgs. of M.S. rods of different sizes to the
appellant. Learned counsel further argued that in the accused
statement, question no.3 has been put by the learned trial Court
that from the evidence of P.W.2, it transpired that the appellant
had received surplus/unutilized Q.4.03 kgs. of M.S. rods of
different sizes from contractor Brundaban Chandra Dey to which
the appellant answered in affirmative but nowhere P.W.2 had
stated about the said aspect in his evidence. Therefore, the
learned trial Court should not have put such question in the
accused statement. It was further argued that in question no.14,
it was put to the appellant that from the evidence of P.W.10, the
I.O., it revealed that during the investigation, he had examined
// 13 //
contractor Brundaban Chandra Dey and the said contractor had
stated before him that he had returned the excess iron rods after
completion of the construction work to the appellant. Since
Brundaban Chandra Dey, contractor has not been examined, the
learned trial Court was not justified in putting the statement of
Brundaban Chandra Dey recorded under section 161 of the
Cr.P.C. in the accused statement to the appellant. It is
contended that since the learned trial Court has committed
illegality in putting questions like questions no.3 and question
no.14, the answers given by the appellant cannot be utilized
against him and should be taken out of consideration. Learned
counsel further submitted that in absence of examination of the
relevant witnesses like Brundaban Chandra Dey and K.C. Ray
from whom the appellant stated to have received M.S. rods of
different sizes, the entrustment part cannot be established and
even if in the accused statement, it was elicited that the
appellant is having possession of the M.S. rods of different sizes
of Q.4.03 kgs. but Ext.C, which is the original charge handing
over the documents, would reveal that same has been handed
over to P.W.2 and the learned trial Court without relying on the
original document has relied upon a carbon copy of the same in
which tampering has been made by P.W.2 mentioning not to
// 14 //
have received the iron rods. Learned counsel further submitted
that once the original document vide Ext.C is taken into account
and it shows that the M.S. iron rods were handed over to P.W.2,
the question of misappropriation by the appellant does not
arises, in fact, it would be the responsibility of P.W.2 to explain
as to what he did with the iron rods. Learned counsel further
argued that there is every possibility that after receiving the iron
rods from the appellant, P.W.2 has misappropriated the same
and manipulated some documents and in order to save his own
skin, foisted a case against the appellant and therefore, it is a fit
case where benefit of doubt should be extended in favour of the
appellant.
Mr. M.S. Rizvi, learned Additional Standing Counsel
appearing for the Vigilance Department, on the other hand,
contended that when in the accused statement, the appellant
has specifically admitted to have received the surplus/unutilized
M.S. rods of Q.4.03 kgs. from the contractor Brundaban Chandra
Dey, non-examination of the contractor cannot be a factor to
disbelieve the prosecution case. Learned counsel further argued
that the documentary evidence like Ext.10 reveals that as on the
date, the appellant handed over the charge, for the month of
July 1992, there was having the stock of Q.4.03 kgs. of rods and
// 15 //
in that month, there was no transaction and therefore, he should
have handed over the entire iron rods to his successor who is
none else than P.W.2, but P.W.2 has mentioned in Ext.10 that
while handing over the charge, the appellant had not handed
over the iron rods and therefore, the learned trial Court was
justified in relying on Ext.9 in which it is specifically mentioned
that P.W.2 has not taken over the charge of the iron rods
mentioned in page-12 of Ext.9. Learned counsel further
submitted that the learned trial Court has rightly taken into
account the evidence on record so also the documents proved on
behalf of the prosecution to arrive at the conclusion that the
appellant was entrusted with Q.4.03 kgs. of rods and he has
misappropriated the same and therefore, the charges have been
duly proved and thus, the appeal being devoid of merits should
be dismissed.
Analysis of the Evidence:
Adverting to the contentions raised by the learned
counsel for the respective parties, in order to prove a case under
section 409 of the I.P.C., it must be established that (i) the
accused was a public servant (ii) he was entrusted with any
property and (iii) that he has committed breach of trust in
respect of such property. Once entrustment is proved, it is for
// 16 //
the accused to prove how the property entrusted was dealt with.
„Criminal breach of trust‟ has been defined under section 405 of
the I.P.C. which is as follows:-
"Whoever, being in any manner entrusted with property, or with any dominion over property, dishonestly misappropriates or converts to his own use that property, or dishonestly uses or disposes of that property in violation of any direction of law prescribing the mode in which such trust is to be discharged, or of any legal contract, express or implied, which he has made touching the discharge of such trust, or willfully suffers any other person so to do, commits criminal breach of trust."
Thus, in order to prove criminal breach of trust,
there must be an entrustment, there must be misappropriation
or conversion to one‟s own use or use in violation of any legal
direction or of any legal contract and the misappropriation or
conversion or disposal must be with dishonest intention. Where
the entrustment is missing, the same would not constitute a
criminal breach of trust.
Section 13(1)(c) of the 1988 Act also states that if a
public servant dishonestly or fraudulently misappropriates or
// 17 //
otherwise converts for his own use any property entrusted to
him or under his control as a public servant or allows any other
person to do so, then he can be said to have committed the
offence of criminal misconduct, which is punishable under
section 13(2) of the 1988 Act.
In the case in hand, the prosecution case as per the
F.I.R. is that Q.4.03 kgs. of steel and iron rods were received by
the appellant from contractor Brundaban Chandra Dey on
02.12.1989, however in the charge, it is mentioned that the M.S.
rods of different sizes weighing Q.4.03 kgs. were received by the
appellant from contractor K.C. Ray. It cannot be lost sight of the
fact that the F.I.R. was lodged after receipt of information and
conducting enquiry. Therefore, there is inconsistency as to from
which contractor the appellant received the steel and iron rods in
question. Neither any of those contractors have been examined
during trial to substantiate the same nor was any documentary
evidence proved on behalf of the prosecution to show that on
02.12.1989, steel and iron rods were received either from
Brundaban Chandra Dey or from K.C. Ray. The learned trial
Court has put the following question to the appellant:-
"Q.3. It transpires from the evidence of P.W.2- J.E. (Anil Kumar Panda) that you had received
// 18 //
surplus/unutilized 4.03 quintals of M.S. Rods of different sizes from contractor Brundaban Ch. Dey. What have you got to say?"
The appellant answered the above question in
affirmative.
After going minutely through the evidence of P.W.2,
the learned Additional Standing Counsel for the Vigilance
Department Mr. Rizvi fairly submitted that nowhere P.W.2 has
stated that the appellant received surplus/unutilized Q.4.03 kgs.
of M.S. rods of different sizes from contractor Brundaban
Chandra Dey. I have also gone minutely through the evidence of
P.W.2 and found that there is nothing in his statement in that
respect.
Similarly, question no.14, which was put to the
appellant in the accused statement, reads as follows:-
"Q.14. It transpires further from the evidence of P.W.10- I.O. that during his investigation, he had examined contractor Brundaban Ch. Dey and that the contractor had stated before him that he had returned the excess iron rods after completion of the aforementioned construction work to you. What have you got to say?"
The answer to this question is in affirmative but it
seems that this question is based on the statement of contractor
// 19 //
Brundaban Chandra Dey recorded under section 161 of the
Cr.P.C. before the Investigating Officer and as already stated the
said contractor has not been examined during trial.
Law is well settled that statement recorded under
section 161 Cr.P.C. is not a substantive piece of evidence and it
can only be used for the limited purpose of contradiction and
corroboration to the evidence of a witness, when he is examined
in Court. Again section 313 of the Cr.P.C. requires that the
attention of the accused must specifically be brought to the
inculpatory pieces of evidence so as to give an opportunity to
him to offer an explanation if he chooses to do. Circumstances
which were not put to the accused in his statement under
section 313 of the Cr.P.C. cannot be used against him and have
to be excluded from consideration. The examination of the
accused under section 313 of the Cr.P.C. is not a mere formality,
the questions put and the answers given thereunder have great
use. It is a direct dialogue between the Court and the accused.
The material evidence against the accused should be brought to
his notice in order to enable him to give explanation. When there
is no evidence or there is no circumstance appearing in the
evidence against the accused on a particular aspect and there is
// 20 //
nothing for him to explain, no question is required to be put to
him on that aspect.
In the case in hand, when the evidence of P.W.2 is
silent that the appellant had received surplus/unutilized Q.4.03
kgs. of M.S. rods of different sizes from contractor Brundaban
Chandra Dey, the learned trial Court should not have put such
question to the appellant in the accused statement as there was
no evidence in that respect. By putting such question, the
learned trial Court has committed illegality by going beyond the
scope of section 313 of Cr.P.C. and therefore, answers given, if
any, has no relevance and cannot be utilized against the
appellant.
Coming to the question no.14 as pointed out by the
learned counsel for the appellant, it reveals that the question
was formulated on the basis of 161 Cr.P.C. statement of
contractor Brundaban Chandra Dey recorded by P.W.10 and in
that statement, the contractor allegedly stated that he had
returned excess iron rods after completion of the construction
work to the appellant. Brundaban Chandra Dey has been cited as
charge sheet witness no.14 but for the reason best known to the
prosecution, he has not been examined during trial. A statement
made by a witness to a police officer during course of
// 21 //
investigation recorded under section 161 of the Code is not and
cannot be treated as substantive evidence. It may be used for
the purpose of contradicting the evidence of the prosecution
witness and by confronting it in the manner provided under
section 145 of the Evidence Act. Therefore, when despite being a
charge sheet witness, the prosecution has not examined
Brundaban Chandra Dey, whatever allegedly he has stated
before the Investigating Officer (P.W.10), on that basis a
question should not have been put to the appellant under section
313 Cr.P.C. Hence, the learned trial Court has committed
illegality in putting such question and therefore, the answer
given, if any, to such question is taken out of consideration.
There is no dispute that the site account register has
been marked as Ext.10 and for the month of July 1992, it was
mentioned that there was availability of stock of Q.4.03 kgs. of
steel and M.S. iron rods of different sizes and during that month,
the transaction was „Nil‟, but the appellant specifically pleaded
that while handing over the charge to P.W.2, he handed over
such rods, which would be evident from Ext.C, the original of the
charge hand over document in which P.W.2 has put his signature
and received different articles including the steel and M.S. iron
rods in questions. From the side of the prosecution, Ext.9 was
// 22 //
proved, which is the carbon copy of the charge report and P.W.2
has stated that at the time of handing and taking over charge,
four carbon copies were prepared of the charge report, the
original remained with the person, who gave the charges,
another copy remained with the person who took the charge and
other two copies remained with the concerned authority. In the
carbon copy of charge report which has been proved to be Ext.9
by the prosecution, in page no.12 thereof, P.W.2 admitted to
have mentioned in original ink in Remark Column against the
steel and M.S. rods to be „Nil‟, which were not there in the
original charge report. D.W.1 Swapneswar Jena has stated that
on 23.07.1992, the appellant was relieved by his successor
P.W.2 and the charge was handed over to P.W.2 and he was
present at that point of time and the charge papers were scribed
by P.W.2 and the appellant was showing articles charge of which
he was handing over to P.W.2 and he along with the staff were
bringing the documents as per the version of the appellant and
after scribing the charge papers, the appellant and P.W.2 put
their signatures in the respective columns on each page and
accordingly, he proved the document marked as Ext.C. When in
the original charge report marked as Ext.C on behalf of the
defence, it is reflected that P.W.2 has received the steel and
// 23 //
M.S. rods in question from the appellant on 23.07.1992 and in
Ext.9, the carbon copy, there has been tampering and it was
mentioned not handed over, the learned trial Court was not
justified in acting upon a carbon copy of the charge report where
there is tampering and not relying on the original charge report,
which is proved by the defence as Ext.C. If on 23.07.1992, the
steel and iron rods were available in the stock and the same was
handed over by the appellant to P.W.2 and the charge report
was prepared, it cannot be said that the appellant
misappropriated the same. Once P.W.2 had taken over the
charges, it is he who was to explain as to how the same was not
found in the stock. The possibility of P.W.2 himself
misappropriating the rods in question and by manipulating the
charge report Ext.9 (carbon copy) in his own hand and foisting
the case against the appellant cannot be ruled out.
Conclusion:
In view of the foregoing discussions, when there is
no clear evidence regarding entrustment of steel and M.S. rods
in question in favour of the appellant and the material witnesses
have been withheld by the prosecution and when it appears that
tampering has been made with the charge report (Ext.9) and on
the basis of original charge report (Ext.C), it appears that the
// 24 //
rods were handed over to P.W.2, in my humble view, the
ingredients of the offences either under section 409 of the I.P.C.
or section 13(1)(c) of the 1988 Act, which is punishable under
section 13(2) of the said Act are not made out against the
appellant.
In the result, the criminal appeal is allowed. The
impugned judgment and order of conviction of the appellant
under section 13(2) read with section 13(1)(c) of the 1988 Act
and section 409 of the I.P.C. is not sustainable in the eye of law
and the sentence passed thereunder is hereby set aside and the
appellant is acquitted of all the charges.
The appellant, who is on bail by order of the Court, is
hereby discharged from liability of the bail bonds and the surety
bonds shall also stand cancelled.
The trial Court records with a copy of this judgment
be sent down to the concerned Court forthwith for information
and necessary action.
Before parting with the case, I would like to put on
record my appreciation to Ms. Tejasmita Mohapatra, learned
counsel for the appellant for rendering her valuable help and
assistance towards arriving at the decision above mentioned.
This Court also appreciates the valuable help and assistance
// 25 //
provided by Mr. M.S. Rizvi, learned Additional Standing Counsel
for the Vigilance Department.
.................................
S.K.Sahoo,J.
Orissa High Court, Cuttack The 24th August 2023/RKMishra
Signature Not Verified Digitally Signed Signed by: RABINDRA KUMAR MISHRA Reason: Authentication Location: HIGH COURT OF ORISSA, CUTTACK Date: 15-Sep-2023 18:54:19
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!