Tuesday, 12, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Mahanadi Coalfields Ltd. And vs Sri Ram Construction
2022 Latest Caselaw 5172 Ori

Citation : 2022 Latest Caselaw 5172 Ori
Judgement Date : 27 September, 2022

Orissa High Court
Mahanadi Coalfields Ltd. And vs Sri Ram Construction on 27 September, 2022
                 IN THE HIGH COURT OF ORISSA AT CUTTACK

                              ARBA No.1 of 2006
                             (Through hybrid mode)

            Mahanadi Coalfields Ltd. and       ....           Appellants
            another
                                    Mr.Sanjit Mohanty, Senior Advocate
                                         Mr. Sudarsan Nanda, Advocate
                                              Mr. A. Mohanty, Advocate


                                       -versus-

            Sri Ram Construction                  ....              Respondent
                                                  Mr. D. Panda, Advocate
                                             Mr. Sudipto Panda, Advocate
                                               Mr. J.P. Behera, Advocate


                     CORAM: JUSTICE ARINDAM SINHA
                                      ORDER

27.09.2022 Order No.

17. 1. Mr. Mohanty, learned senior advocate appears on

behalf of appellants. He submits, impugned is judgment dated

24th September, 2005 of the Court below in rejecting his

client's challenge to award dated 31st March, 2004.

2. He submits, there was executed agreement dated 22nd

December, 1997 between respondent and his client, wherein his

client was employer and respondent was contractor. The

agreement was for construction of 336 'A' type quarters at

Lingraj Township of Talcher Area. The contract was valued at

// 2 //

Rs.7,13,43,281.28 in the agreement subject to any other sum

that may be arrived at under specifications clause. On notice of

respondent, arbitration clause in the notice inviting tender,

made part of the agreement, was scored out. Parties were

aware, therefore, the award of work under the agreement did

not contain arbitration agreement/clause.

3. On the contractor having procured materials, said to be

for purpose of constructing under the agreement, it applied for

advance to his client. His client agreed to advance Rs.70 lakhs

under independent agreement dated 9th February, 1998. The

agreement for extending advance contained arbitration clause.

4. He hands up a compilation of documents, statement of

facts and claims and the award. He furnishes copies to Court, to

be obtained by respondent since, respondent is represented by

Mr. Panda, online. Respondent is at liberty to obtain copies of

the documents handed up to Court today or by tomorrow.

5. Respondent alleged disputes had arisen. By letter dated

1st November, 1999 respondent gave notice for invocation of

arbitration agreement in agreement dated 9th February, 1998.

There was clear and unambiguous admission in said letter that

arbitration clause-14, in the tender made part of agreement

dated 22nd December, 1997, was deleted.

// 3 //

6. Mr. Mohanty submits, the law regarding appointment

of arbitrator under section 11 in Arbitration and Conciliation

Act, 1996 was, at that time, a request to be made to the Chief

Justice and the appointment an administrative act. Respondent

requested the Chief Justice and, without direction for issuance

of notice there was order dated 16th May, 2001 appointing

arbitrator.

7. On learning of appointment of arbitrator, appellants

applied for review. By order dated 30th August, 2001 the review

application was rejected. His client then by letter dated 31st

July, 2001 questioned jurisdiction of the arbitrator on ground

that claims were made in respect of agreement dated 22nd

December, 1997, which did not have arbitration clause.

8. He refers to the award to demonstrate from paragraph-8

therein, the point was taken. The arbitrator illegally found that

agreement dated 22nd December, 1997 (Ext.6 in the reference)

forms part of agreement dated 9th February, 1998 (Ext.18 in the

reference). The arbitrator went on to award Rs.3,93,72,100/-

and directed payment of interest at 17% per annum till date of

payment. Mr. Mohanty refers to the statement of claim, page-

17, in which is the schedule of the claims. He submits, each and

every claim was made under agreement dated 22nd December,

// 4 //

1997.

9. Mr. Panda prays for adjournment on not having earlier

received copies of the documents handed up.

10. List on 18th October, 2022.

(Arindam Sinha) Judge

Sks

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter