Citation : 2022 Latest Caselaw 4708 Ori
Judgement Date : 14 September, 2022
IN THE HIGH COURT OF ORISSA AT CUTTACK
ARBA No.9 of 2020
(Through hybrid mode)
ACC Ltd. .... Appellant
Mr. Saswat Kumar Acharya, Advocate
-versus-
Subrat Ranjan Dash .... Respondent
Mr. Avijit Pal, Advocate
CORAM: JUSTICE ARINDAM SINHA
ORDER
14.09.2022 Order No.
11. 1. Mr. Acharya, learned advocate appears on behalf of
appellant. He submits, there were two agreements entered into
between his client as principal and respondent as the clearing
and forwarding (C&F) agent. The first agreement was executed
on 1st April, 2005. Clause-26 in it is reproduced below.
"Clause 26: It is agreed between the parties to this contract that in the event of any dispute of any nature arising out of this contract, the same shall be referred to the Company which will appoint two of its Officers to conduct an enquiry and the decision arrived at by them for resolving such dispute shall be final and binding between the parties. In the
// 2 //
event of any matter being referred to a Court of Law only those Courts in whose jurisdiction Kolkota Regional Office is situated will have the exclusive jurisdiction to entertain the same."
2. On 25th July, 2007 another agreement was executed
between the parties. Said agreement was given retrospective
commencement from 1st July, 2007. Clause-22 in it provided
for arbitration. Under the clause, reference of disputes could
only be of disputes arising out of, or in relation to said
agreement or any interpretation or implementation of any
clause including any dispute with respect to the existence or
validity thereof or the breach thereof. He submits, of the claims
awarded, except claim no.9, the awards were in respect of
disputes arising out of the earlier agreement. It could not have
been arbitrated upon by the Tribunal. His client made
application under section 16 in Arbitration and Conciliation
Act, 1996. Paragraph 4 from the application is reproduced
below.
"4. That upon perusal of the claim items it can be seen that certain claim items emanate from the earlier contract and relate to the period under that contract for which the same are not only barred by limitation but do not arise out of any provisions of
// 3 //
Arbitration Clause which is only provided in the agreement under Annexure-2 and the dispute has been referred to the Hon'ble Arbitrator in accordance with Clause-22 of the Second Agreement only. It has also been made clear in the second Agreement under Annexure-2 in Clause-25 that the second Agreement supersedes all prior understandings and the agreements on the subject matter and as such there cannot be any arbitration on the claims which relate to the period under first agreement."
3. With reference to reasoning in impugned judgment
dated 15th November, 2019 he submits, though the Court below
struck down award on claim nos. 1 and 6 as relating to period
prior to the 2005 agreement, on ground that no reason was
assigned in the award, said Court erred, as apparent on face of
the judgment, in thereby taking into consideration claims arisen
under the 2005 agreement. He reiterates, said agreement had no
arbitration clause. He refers to a passage in the judgment,
reproduced below.
"Learned Arbitrator has analyzed the true purport of the agreements, while considering the petition U/s. 16 of the Act, 1996, so also in Issue No.2 as regard to the claim of the petitioner that the same was barred by law of limitation and arrived at a conclusion that all
// 4 //
the claims are arbitriable. There appear justified reasons assigned by the learned sole Arbitrator in view of the fact that a bare reading of the aforesaid clauses, in two different agreements would go to show that there was no substantial change in the agreement and one agreement is substituted by other. The supersession/substitution itself takes in its fold the earlier agreement, which merges with the subsequent agreement in terms of Sec.62 of the Indian Contract Act and therefore, Clause-22 of the Agreement 2007, which refers to Arbitration Clause, takes it in its domain all the disputes arose between 2005 till the agreement is finally concluded by the parties."
He submits, there is error of law apparent in above reasoning
inasmuch as there can be no merger on novation, provided by
section 62 in Contract Act, 1872. Furthermore, where terms of
the two agreements are inconsistent, there cannot also be
substitution. He submits, clause-26 in the first agreement
provided for approach to Court and clause-22 in the subsequent
agreement, to arbitration. The two clauses are inconsistent. The
second agreement, therefore, cannot be said to have substituted
the first. He relies on judgment of the Supreme Court in Lata
Construction v. Rameshchandra Ramniklal Shah reported
in (2000) 1 SCC 586, paragraph-12 (Manupatra print)
// 5 //
reproduced below.
"12. One of the essential requirements of `Novation'; as contemplated by Section 62, is that there should be complete substitution of a new contract in place of the old. It is in that situation that the original contract need not be performed. Substitution of a new contract in place of the old contract which would have the effect of rescinding or completely altering the terms of the original contract, has to be by agreement between the parties. A substituted contract should rescind or alter or extinguish the previous contract. But if the terms of the two contracts are inconsistent and they cannot stand together, the subsequent contract cannot be said to be in substitution of the earlier contract."
He submits, apart from claim no.9, award on claims in respect
of the earlier agreement be set aside in appeal.
4. Mr. Pal, learned advocate appears on behalf of
respondent. He submits, there was reference to arbitration upon
request made to the Chief Justice. By order dated 27th August,
2015 there was appointment of the arbitrator. It would appear
from said order that the Bench noticed the two agreements. On
finding no appointment had been made as per the second
agreement, power under section 11(6) was exercised to appoint
the arbitrator.
// 6 //
5. He relies on, relevant to the case, judgment of the Supreme Court in SBP and Co. v. Patel Engineering Ltd. reported in (2005) 8 SCC 618, paragraph-20. A passage therefrom is extracted and reproduced below.
"20. Section 16 is said to be the recognition of the principle of Kompetenz-Kompetenz. The fact that the arbitral tribunal has the competence to rule on its own jurisdiction and to define the contours of its jurisdiction, only means that when such issues arise before it, the Tribunal can and possibly, ought to decide them. This can happen when the parties have gone to the arbitral tribunal without recourse to Section 8 or 11 of the Act. But where the jurisdictional issues are decided under these Sections, before a reference is made, Section 16 cannot be held to empower the arbitral tribunal to ignore the decision given by the judicial authority or the Chief Justice before the reference to it was made. The competence to decide does not enable the arbitral tribunal to get over the finality conferred on an order passed prior to its entering upon the reference by the very statute that creates it. That is the position arising out of Section 11(7) of the Act read with Section 16 thereof. The finality given to the order of the Chief Justice on the matters within his competence under Section 11 of the Act, are
// 7 //
incapable of being reopened before the arbitral tribunal xx xx xx."
He submits, following the judgment appellant's application
under section 16 was misconceived. His client all along duly
acted as the C&F agent. Of claims made some were rejected.
His client has accepted the award and seeks execution thereof.
There should not be interference in appeal.
6. The patent illegality apparent on face of the award
urged in appeal by appellant is that apart from claim no.9, the
claims awarded were in respect of disputes arisen under the
first agreement, which was outside four corners of the second
agreement bearing the arbitration clause. Hence, the arbitrator
travelled beyond his jurisdiction in awarding on those claims.
Ground by entry (iv) in clause (a) under sub-section (2) of
section 34 (prior to amendment) stands satisfied for
interference in appeal to set aside award on those claims. This
is the only ground urged.
7. Court is unable to accept appellant's contention that the
second agreement, at least so far as dispute resolution clauses
are concerned, could not have been a substitution of the first.
This is because there was alteration of the term, of approach to
// 8 //
Court in the first agreement to be reference to arbitration in the
second agreement. This was novation. However, there could
not have been merger of terms of the first agreement on
execution of the subsequent agreement, under section 62 in
Contract Act, 1872. This appears to be an erroneous
appreciation of the law of novation, where terms of the original
agreement need not be performed. It is arguable whether 'need
not be performed' is a bar to perform but that can be decided in
an appropriate case. Still, for adjudication on the appeal, it is
necessary to look at both the agreements.
8. Agreements dated 1st April, 2005 and 25th July, 2007
are agency agreements where appellant is principal and
respondent, its C&F agent. Arbitration clause is part of the
second agreement. Also in the second agreement there is a term
by clause-4, extracted and reproduced below.
"4. Term The term of this Agreement shall commence with retrospective effect from 1st July, 2007 and shall continue until 30.06.2010, unless terminated earlier as per Clause 12 hereinafter. This Agreement may be renewed at the sole discretion of ACC and on such terms and conditions as may be agreed to by ACC. The earlier agreement signed with C&FA on
// 9 //
1st April, 2005 which was valid up to 31.03.2008 is hereby cancelled."
(emphasis supplied)
By the second agreement, earlier agreement dated 1st April,
2005, valid up to 31st March, 2008, was cancelled. As a
consequence, when there was notice for commencement of the
reference, there was only the agreement dated 25th July, 2007.
Clause-22 in the agreement is of wide amplitude in
encompassing disputes that may arise in connection with the
agreement. The earlier agreement stood cancelled by this
agreement and as such it is but natural that disputes arising out
of the cancelled agreement stood connected to this agreement.
9. The request for appointment of arbitrator under section
11(6) was made by respondent. It was confined to the clearing
and forwarding agency agreement dated 25th July, 2007. The
law as it stood on 27th August, 2015 (date of appointment of
arbitrator) required judicial exercise in making the
appointment. It was made. The appointment thus made eclipsed
operation of section 16 in enabling the Tribunal to decide on its
own competence as declared in Patel Engineering (supra).
10. Perused the award with reference to claims awarded. As
aforesaid claim nos. 1 and 6 were set aside by the Court below
// 10 //
on finding no reasons assigned in the award against them. On
rest of the claims awarded, there does not appear to be any
apparent patent illegality.
11. Impugned order is confirmed. The appeal is disposed
of.
(Arindam Sinha) Judge
Sks
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!