Citation : 2022 Latest Caselaw 2486 Ori
Judgement Date : 9 May, 2022
IN THE HIGH COURT OF ORISSA AT CUTTACK
ARBA No.58 of 2018
(Through hybrid mode)
Jayaram Panda .... Appellant
Mr. S.K. Sarangi, Advocate
-versus-
Project Director, M/s. National .... Respondents
Highway Authority of India and
others
Mr. A.K. Sharma, AGA
Mr. U.C. Mohanty, Advocate
CORAM: JUSTICE ARINDAM SINHA
ORDER
09.05.2022 Order No.
10. 1. Mr. Sarangi, learned advocate appears on behalf of
appellant and on 22nd March, 2022 had submitted, impugned
judgment dated 5th December, 2018 is liable to and should be
set aside in appeal. The Court below erred in not appreciating
that his client had mounted good challenge against award by
order dated 13th June, 2016 regarding quantum of compensation
to be paid to his client on acquisition by National Highways
Authority of India (NHAI). There were two technical
evaluations of industrial loss suffered and compensation to be
paid to his client. The earlier assessment returned finding of
compensation payable at Rs.55,69,904/-. There was a
// 2 //
subsequent assessment, which returned figure Rs.92,38,627/-.
He submits, there is no reasoning in the award as to why latter
assessment stood rejected.
2. Today, he draws attention to comments made by
General Manager DIC-Ganjam-Berhampur-cum- Chairman
Technical Committee dated 11th May, 2010. He submits, copy
of this document have been circulated to respondents, State and
NHAI.
3. He demonstrates from the comments that actual loss of
interest of Rs.31,49,513/- had not been considered basing on
Rs.24,61,359/- as fixed capital investment. Loss of interest was
calculated on Rs.17,90,759/- towards fixed capital investment,
determined by the previous committee. Furthermore, specific
damages were taken by the previous committee at
Rs.19,10,375/- but calculation given in the comments show the
figure to be Rs.38,10,538/-. The aggregate difference added to
the award amount make up the sum of Rs.92,38,627/-. He
submits, this recommendation by the comments was urged by
his client before the arbitrator but rejected out of hand.
4. Mr. Mohanty refers to impugned judgment dated 5th
December, 2018, paragraph-8. He submits, the learned judge
// 3 //
has given clarification as to why the comments are baseless. In
the circumstances, the award could not have been interfered
with and the Court below did not do so.
5. Mr. Sharma, learned advocate, Additional Government
Advocate appears on behalf of State and submits, the comments
are personal opinion/views of the General Manager, not
approved by the State Government. The recommendation of the
Technical Committee approved by the State Government is at
Rs.55,69,904/- as awarded by the arbitrator. He submits, there
should not be interference.
6. Perused impugned award. It appears from finding
therein that the assessment report at Rs.55,69,904/- was signed
by representative of NHAI with a dissent note. The findings
continue to he, inter alia, as appearing in the paragraph
reproduced below.
"The learned Advocate appearing for the PD, NHAI, in his counter, has stated that since the technical committee and DIC have assessed the compensation in this case and the Land Acquisition Officer-cum-CA concurs the same, he has no other agency to go into correctness of the assessment and he has no other course except to carry out the orders
// 4 //
of the authority as deems fit and proper and to place fund with the LAO-cum-CA for its payment.
Since the new Technical Committee has assessed the loss at Rs.55,69,904/- and recommended it to the Government in industries Department who have accepted the same and communicated for needful action vide his letter No.6577 dt.29.05.2010, the said assessment with regard to compensation is found justified. But the claim for payment of compensation of Rs.92,38,627/- has not been accepted by the Technical Committee. Taking advantage of the comments of GM, DIC dt.11.5.2010 on the objection of PD, NHAI, the OP No.1 has claimed the aforesaid amount. As the said amount has not been approved by the Technical Committee members formed by the Govt. Industries Department, the prayer for payment of compensation of Rs.92,38,627/- merits no consideration and accordingly it is rejected."
7. It is clear from impugned award that the Tribunal took
into consideration as decisive factor, change of stand of NHAI
in accepting recommendation of the Technical Committee made
at Rs.55,69,904/-. It may be that the Director, being Chairman
of the Committee, had commented on omissions made by the
Committee, in his personal capacity. However, appellant had
based its case for higher amount of compensation based on the
// 5 //
comments. The dispute before the Tribunal was not controversy
regarding acceptance of the Technical Committee
recommendation of reassessed amount at Rs.55,69,904/-
between the administration and NHAI. The controversy was
between appellant on the one hand and the authorities on the
other, regarding claim for higher compensation at
Rs.92,38,627/-. Perusal of the award does not give illumination
of a single reason directed towards the controversy.
8. It is true that by paragraph-8 in impugned judgment
several reasons have been given by the Court below but the
Court adjudicating a challenge against arbitral award is to be
guided by provisions in section 34, Arbitration and Conciliation
Act, 1996. The challenge is not akin to a first appeal being
continuation of the suit. Challenge against an award is on
grounds limited by section 34.
9. Sub-section (3) in section 31 mandates that the arbitral
award shall state the reasons, upon which it is based unless,
inter alia, it is to be made as per the clauses (a) and (b) in the
sub-section. Said clauses do not apply in the facts and
circumstances, as parties had not agreed to have the award
without reasons or that it was an award based on agreed terms.
// 6 //
Appellant had a contesting claim in the Tribunal, of seeking
higher compensation. As aforesaid, the Tribunal directed its
attention to settling the dispute between State and NHAI
regarding the reassessment made by the Technical Committee at
Rs.55,69,904/- and awarded the same.
10. The award being bereft of reason, goes against the
mandate of the Act and therefore is against public policy. It is
set aside.
11. On query from Court parties submit that a different
person is now holding office as Collector, Ganjam. Said office
is directed to deal with and dispose of the reference, as
expeditiously as possible.
12. The appeal is disposed of.
(Arindam Sinha) Judge
Sks
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!