Citation : 2022 Latest Caselaw 3377 Ori
Judgement Date : 21 July, 2022
IN THE HIGH COURT OF ORISSA AT CUTTACK
ARBA No.4 of 2016
(Through hybrid mode)
State of Odisha and others .... Appellants
Mr. P.P.Mohanty, AGA
-versus-
M/S. B. Engineers & Builders Ltd., .... Respondent
BBSR
Mr. Debendra Kumar Dwibedi, Advocate.
CORAM: JUSTICE ARINDAM SINHA
ORDER
21.07.2022 Order No.
20. 1. The appeal was moved before this Bench on 4th January, 2022.
On behalf of appellant(State) it was submitted that State had entered
into the contract with respondent. As per the contract and pursuant to
request made by respondent, there was settlement of final bill and
closure. It is only thereafter that the contractor raised dispute and
invoked the contract clause regarding appointment of adjudicator.
Being aggrieved by the ruling of the adjudicator, the contractor then
invoked the arbitration clause. The arbitrator awarded on extra items,
outside scope of the contract. This was not appreciated by the learned
District Judge in dealing with the petition made under section 34,
Arbitration and Conciliation Act, 1996. The award ought to have been
// 2 //
set aside and should be set aside in appeal.
2. It was further submitted, impugned judgment dated 10th
September, 2015 should be interfered with in appeal. First ground of
challenge against the award (since appeal is continuation of the
challenge) is regarding claim no.1. There was rate fixed for extra
works, not provided by the contract. The rates were fixed by the
Supervisory Committee. The Committee cannot be said to have been a
contracting party, to have modified terms of the contract. Regarding
claim no.2 it was submitted, there should not have been interest
granted for retention of security money. No such provision was there
in the contract
3. Today Mr. Mohanty, learned advocate, Addl. Government
Advocate appearing on behalf of appellant refers to paragraph 14 in
award dated 10th December, 2010. It is in dealing with claim no.1 on
removal of bulged concrete and rectification of guides under water. He
submits, this was work outside scope of the contract. Same would
appear from recital of the claim in the award itself. The arbitrator
accepted finding of the adjudicator made before the reference that
removal of bulged in concrete occurring in the dam phase underwater,
has to be treated as extra item. He submits, this claim was rejected at
the threshold. He relies on communication dated 11th February, 1999
from Engineer-in-Chief to the Government, disclosed by his client's
// 3 //
additional affidavit dated 14th March, 2022, to submit, the Supervisory
Committee was constituted to assist and solve problems of the
Executive Engineer, to take spot decision on site conditions for
ensuring strict quality control and expedite execution of the works. It
did not have authority to recommend rates for work, not contemplated
under the contract, to thereby purport to act on behalf of the employer,
to cause novation of it.
4. He submits further, all bills were paid and the security deposit
refunded as well but on delay of eight months. The contract did not
provide for payment of interest on refund of security money.
5. Mr. Dwibedi, learned advocate appears on behalf of
respondent-contractor. He had submitted, supplementary agreements
were entered into, which enlarged scope of the contract to include the
six claims that were dealt with by the award. All claims were not
awarded in favour of his client. There is no defect in the award as can
be said to be one, which falls within the grounds in section 34. The
appeal should be dismissed.
6. Controversy in the appeal is confined to aforesaid claim no.1
made by the contractor and award of interest on delayed refund of
security money. Contention of appellant has been that both the claims
awarded, were beyond four corners of the contract. The arbitrator,
therefore, travelled beyond the contract and misconducted himself.
// 4 //
The contention of misconduct is based on two grounds. Firstly, the
contract did not provide for extra work or rates, and secondly, it also
did not provide for interest on refund of security money.
7. It appears from relied upon communication dated 11th
February, 1999 that two committees were constituted by the employer,
without reference to the contractor. The constitution of these
committees was in aid of working out the contract. Constitution of the
two committees, being Supervisory Committee and High Level
Technical Committee, as stated in said communication, is extracted
therefrom and reproduced below.
"A committee with the following members is constituted to function as supervisory committee to assist and solve the problems of the Executive Engineer, S&M Division, Hirakud to take spot decision on the site conditions for ensuring strict quality control and expeditious execution of the works.
1. S.E, Hirakud Dam Circle Chairman
2. S.E,Mechanical, Hirakud Member
3. E.E.,H.D.R.D.Division, Burla Member Secretary
4. E.E. Stores & Mech. Divn., Hirakud Member
5. E.E. Main Dam Division, Burla Member
All spot decisions on higher technical and financial matters are to be referred to the technical committee by the member secretary.
A high level technical committee is constituted under the Chairmanship of E.I.C., Water Resource with the following members to take decisions on the technical and financial matters upon recommendation (on its receipt) from the supervisory committee.
1. Sri R.C. Tripathy, Engineer-in Chief, Water Resources
// 5 //
2. Sri B. B. Mishra, Engineer-in-Chief, Planning & Design
3. Sri R.K. Kanungo C.E. & Basin Manager, Upper Mahanadi Basin, Burla
4. Sri Sanatan Deo, Chief Engineer, Mechanical"
(Emphasis supplied)
8. Agreed procedure on dispute resolution, provided in the
contract, required reference initially to an adjudicator. The dispute was
so referred and the adjudicator ruled on it. The contractor being
aggrieved on the adjudication made, sought reference to arbitration,
which was concluded by the award. The adjudicator had found that
claim no.1 was indisputably on extra work and it had to be paid. The
finding was extracted and quoted in the award and is also reproduced
below.
"As such the removal of Bulged in concrete occurring in the Dam face, Under Water, has to be treated as Extra Item and paid for....."
It appears the contractor was aggrieved by the ruling because the
adjudicator had reduced the area recorded in measurement book at 251
sqm. to 226 sqm. and the rate agreed at Rs.65,230/- per sqm. to
Rs.6688/- per sqm.. What is significant is and as pointed out by Mr.
Dwibedi, State did not challenge the ruling made by the adjudicator on
both findings. What follows is that there was extra work got done and
some rate provided therefor.
9. At instance of appellant the lower Court record was produced
// 6 //
but relied upon exhibit-11 was not found therein. Mr. Mohanty then
produced copy of the exhibit with copy to Mr. Diwbedi.
10. Exhibit-11 relied upon in the reference has been perused by
Court. Extract in paragraph 18 of the award was truly made therefrom.
The exhibit is a document recording compliance to 8th meeting of the
Supervisory Committee held on 22nd January, 2002. The document
was tendered by the contractor and Court ascertained from Mr.
Mohanty that there is no dispute regarding existence of it. The extract
in the award from the document is reproduced herein as from the
exhibit.
"In additional to rectification of misalignment the work involves cutting of bulge concrete and under water welding of missing link of guides. Under water welding of missing link has already been done in the left guide of emergency gate slot no.49. Hence the committee decided to include under water cutting of bulge concrete and welding of missing link as two extra items and continue with the work. The negotiated rates of Rs.14,500/- per meter of underwater welding and Rs.65,230/- per Sqm of removal of bulged concrete as agreed by 6th supervisory committee and 4th High level technical committee was recommended by the committee. The agency also agreed to it."
(Emphasis supplied)
11. The employer was represented in the working of the contract
by its several engineers and authorized personnel. No contention has
// 7 //
been made regarding constitution of the committees as were
unauthorized. The Supervisory Committee had authority to take spot
decision on higher technical and financial matters but, they were to be
referred to the High Level Technical Committee. The High Level
Technical Committee was empowered to take decision on the
technical and financial matters upon recommendation (on its receipt)
from the Supervisory Committee. The arbitrator found and there is
clear statement in the document being exhibit-11 that the Supervisory
Committee made the recommendation by its 6th meeting and in the 4th
High Level Technical Committee meeting, same was agreed to.
12. So far as the interest on delayed payment of retention money is
concerned, on query from Court Mr. Mohanty could not demonstrate
existence of any clause in the contract authorizing delayed repayment.
In the circumstances, award for interest on delayed refund of retention
money appears to be a possible view.
13. Impugned judgment is confirmed. The appeal is found to be
without merit and the same is dismissed.
(Arindam Sinha) Judge Prasant
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!