Monday, 18, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Suresh Chandra Mirchandan vs Chief General Manager
2022 Latest Caselaw 3001 Ori

Citation : 2022 Latest Caselaw 3001 Ori
Judgement Date : 7 July, 2022

Orissa High Court
Suresh Chandra Mirchandan vs Chief General Manager on 7 July, 2022
                 IN THE HIGH COURT OF ORISSA AT CUTTACK

                               ARBA No.12 of 2008
                              (Through hybrid mode)

            Suresh Chandra Mirchandan                ....            Appellant

                                                   Mr. S.K. Purohit, Advocate

                                        -versus-

            Chief General Manager, Mahanadi          ....         Respondents
            Coalfields Ltd. and another
                                                   Mr. S. Mohanty, Advocate

                         CORAM: JUSTICE ARINDAM SINHA
                                        ORDER

07.07.2022 Order No. I.A. no.24 of 2022

19. 1. This application is for recall of order dated 3rd March,

2022, dismissing the appeal. Mr. Purohit, learned advocate

appears on behalf of applicant/appellant and had moved the

application on 24th June, 2022. Order made that day is

reproduced below.

"Mr. Purohit, learned advocate appears on behalf of applicant and submits, his client is interested in the appeal but unfortunately had not given instructions, causing the appeal to be dismissed. He prays for recall of order dated 3rd March, 2022.

2. Applicant is directed to serve copy of the recall application along with this order on learned advocate, who had appeared on 3rd March, 2022,

// 2 //

when the appeal was dismissed. It is made clear that the appeal itself will be taken up on adjourned date. In event applicant is not ready with the appeal, the recalling application is likely to be dismissed.

3. List the recall application on 30th June, 2022, immediately after old matters."

2. Mr. Mohanty, learned advocate appears on behalf of

respondents. Parties are ready for hearing and disposal of the

appeal. In the circumstances, causes shown for lack of

instruction in pressing the appeal on 3rd March, 2022 are

accepted. The appeal is restored to file and the application is

disposed of.

3. Mr. Purohit submits, his client was contractor engaged

by Mahanadi Coalfields Ltd. (MCL) to do work. Though time

for doing the work was specified, several extensions were

granted by the employer. It is because of the employer that the

work could not be completed. 20% of the work remained

outstanding. In the circumstances, his client required resolution

of disputes by arbitration.

4. Chairman-cum-Managing Director (MCL) appointed

sole arbitrator. MCL was the employer. As such the Chairman-

cum-Managing Director (MCL) was ineligible to be arbitrator.

He could not then have appointed sole arbitrator,

// 3 //

notwithstanding the arbitration agreement clause. He submits,

arbitration is based on neutrality. The employer appointed its

person as arbitrator. Nothing further need be said on the

adjudication suffering from bias.

5. He relies on judgments of the Supreme Court.

(i) Judgment dated 26th November, 2019 in

Arbitration Application no.32 of 2019 (Perkins Eastman

Architects DPC v. HSCC (India) Ltd., paragraph 14

(Indiankanoon print). Relied upon passage is extracted and

reproduced below.

"14. In TRF Limited, the Agreement was entered into before the provisions of the Amending Act (Act No.3 of 2016) came into force. It was submitted by the appellant that by virtue of the provisions of the Amending Act and insertion of the Fifth and Seventh Schedules in the Act, the Managing Director of the respondent would be a person having direct interest in the dispute and as such could not act as an arbitrator. The extension of the submission was that a person who himself was disqualified and disentitled could also not nominate any other person to act Arbitration Application No.32 of 2019 Perkins Eastman Architects DPC & Anr. v. HSCC (India) Ltd."

(ii) Decision dated 10th February, 2017 in Arbitration

// 4 //

Petition (Civil) no.50 of 2016 M/s. Voestalpine Schienen

GMBH v. Delhi Metro Rail Corporation, paragraph-16 and 17

(IndiaLawLib print).

(iii) Decision dated 3rd July, 2017 in Civil Appeal

no.5306 of 2017 (TRF Ltd. v. Energo Engineering Projects

Ltd.), paragraphs 11, 56 and 57 (IndiaLawLib print). On query

from Court he submits, both Voestalpine (supra) and TRF

(supra) were referred to in Perkins (supra).

6. On further query from Court regarding whether the

declaration of law relied upon for the proposition that an

arbitrator, himself ineligible, cannot appoint another as based on

the year 2015 amendment, if can be made applicable to the

present case wherein the award was passed long before the

amendment, he reiterates his submission that because there is

inherent bias attributed to an ineligible person, the principles of

the declaration of law do apply.

7. Mr. Mohanty submits, the award is good and there

should not be interference in appeal on it having been upheld

by the lower Court. The judgments cited by Mr. Purohit do not

apply since the award is dated prior to the year 2015

amendments.

// 5 //

8. The position in law regarding bias in an adjudication

prior to the year 2015 amendment relied upon was to find it

appearing from the record. In this case Court has perused the

award. There is no apparent bias in the award. It is true that

Chairman-cum-Managing Director of MCL appointed the sole

arbitrator. The person then held office as General Manager,

Management Training Institute, MCL. The award is dated 1st

February, 2000.

9. In the award the arbitrator has tabulated respective cases

presented by the parties. It is clear that only 80% of the work

was done. The award says appellant had alleged that sites were

handed in piecemeal during June and July, 1993. Several

extensions of time were granted. The department had sent

express telegram to appellant requesting completion of balance

work within 20th March, 1996, to be treated as final notice.

10. The award also gives analysis of the evidence adduced

by the parties. The analysis says that appellant had not stated

when he submitted drawing to the department while the

department adduced documentary evidence to show that delay

was due to the late submission. Though appellant had said that

monsoon affected the work but the arbitrator found that the

whole work were to be completed in six months time but during

// 6 //

the first four months appellant did only 10% of the work. On

contention of appellant that there were two separate individual

work sites, the arbitrator found mention in the Notice Inviting

Tender (NIT) of the scope of work at the sites. In rejecting the

claims of work done but not paid for, refund of security deposit

and overheads, the arbitrator also rejected the consequential

claims of interest etc. There was finding on facts regarding the

amount of work done and that it had been paid for. There was

rejection of claim for refund of security deposit on the work

remaining incomplete.

11. The arbitrator allowed counter claims put up by the

employer. Two counter claims were allowed. Firstly, forfeiture

perpetual of security deposit and secondly, imposition of due to

belated completion of work. On perusal of reasons given in the

award for allowing the claims, Court finds that as aforesaid the

arbitrator awarded forfeiture of security deposit because the

work was not completed. However, the arbitrator held that MCL

had not closed the contract. In the circumstances, the award of

penalty appears to be perverse. This is because penalty imposed

at 10% of agreement value is on an agreement right to impose

penalty due to belated completion of work but the arbitrator

himself found that the work was incomplete and MCL had not

// 7 //

yet closed the contract. This counter claim award on penalty of

Rs.91,800/- is severable and is set aside.

12. Impugned judgment dated 28th July, 2007 is modified as

above.

(Arindam Sinha) Judge

Sks

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 

LatestLaws Partner Event : IJJ

 
 
Latestlaws Newsletter