Citation : 2022 Latest Caselaw 7368 Ori
Judgement Date : 14 December, 2022
IN THE HIGH COURT OF ORISSA, CUTTACK
WP(C) No.8856 of 2010
(Through hybrid mode)
M/s Orissa Industrial Infrastructure ....... Petitioner
Development Corporation, IDCO Tower,
Bhubaneswar.
-Versus-
The Presiding Officer, Industrial Tribunal ....... Opposite Parties
and another
Advocates appeared in the case:
For petitioner - Mr. S.P. Mishra,
Senior Advocate
For opposite parties - Mr. B. Satpathy,
Advocate
D. Mohanty,
CORAM:
JUSTICE ARINDAM SINHA
JUSTICE SANJAY KUMAR MISHRA
JUDGMENT
14.12.2022
ARINDAM SINHA, J.
1. The writ petition is of the management. It was moved before
this Bench on 9th November, 2022, when Mr. Mishra, learned senior
advocate appearing on their behalf had submitted, there had been
orders made by coordinate Benches, requiring affidavits being filed.
The requirement was because though there was direction for
regularization of 43 workmen, no particulars could be provided by the
union, at whose instance the reference was caused. His client has also
filed affidavit. We reproduce below paragraphs 3 and 4 from our said
order dated 9th November, 2022.
"3. We find, impugned is award dated 30th March, 2010. We have perused order of reference being whether 80 causal workers are entitled for regularization along with payment for equal pay on equal work. The tribunal found on facts, inter alia, 43 persons out of 80 workmen were seeking regularization. Particulars of the persons have been given in page-11 of the award. It goes on to record a further finding of fact that the management had regularized good number of Nominal Muster Roll (NMR) employees with approval of the Board of Directors. Those regularized stood in same footing as the 43. Hence, opinion of the tribunal that claim for regularization made by them merits consideration owing to them having rendered unblemished service under the corporation for more than 18 years. This too is a finding of fact.
4. The management will be heard on adjourned date regarding perversity on any one or more of above recorded findings of fact."
(emphasis supplied)
2. Today Mr. Mishra submits, perusal of impugned award dated
30th March, 2010 will reveal there was no evidence before the labour
Court to say that 43 workmen had been appointed/engaged by his
client. During pendency of the writ petition, several of the 43 have
WP(C) no.8856 of 2010 crossed the age of superannuation. One of them raised separate
industrial dispute, regarding which the reference is still pending. He
adds by reference to since set aside judgment dated 21st April, 2017 of
the learned Single Judge, earlier disposing of the writ petition that
three workers of the 43, against serial nos.34, 35 and 43, had no
document to support they ever having worked for his client.
3. Mr. Mishra refers to failure report dated 23rd September, 2008
of conciliation made under section 12(4) in Industrial Disputes Act,
1947. He submits, there was clear admission by the workmen that they
had been engaged through the contractors. This was the position on
compliance of specific direction made by the Managing Director on
circular dated 6th May, 1986. Text of the circular is reproduced below.
"Please recall that from time to time we have taken decisions not to engage N.M.Rs. without specific sanction from Managing Director and also disengage them on completion of the project for which N.M.Rs. were engaged. I hope, all are taking steps to review the position work-wise under your division and disengaging the N.M.Rs. when not required to reduce the burden of our Corporation, i.e. cannot survive unless all responsible office bearers are conscious that they have a moral duty to see that the Corporation finances are not overburdened due to our negligence. If we do not follow certain discipline, this organization will not be able to take the burden and as a consequence even the existing 1000 or so employees will face serious difficulty in retaining their jobs.
WP(C) no.8856 of 2010 I would, therefore, once again request you that no new hands should be taken as N.M.Rs. without specific approval from the Managing Director to ensure control on the number of staff. Copies of circular No.11994 dated 20.05.83, 3850 dated 23.02.1985 and No.2539 dated 3.2.1986 issued in this respect are enclosed for your ready reference. A list of person kept on DLR since 1.1.86 may please be intimated for my information."
4. He then refers to impugned award and submits, the workmen
could not tender a single document to show they had been appointed
/engaged by his client. His client had several ongoing projects at that
time and therefore, had obtained workers through contractors,
specifically for the projects. The work was not perennial in nature.
There had been no engagement. There is no question of whether such
engagement was made through contractors against posts, for
application of the exception declared by the Supreme Court in
Secretary, State of Karnataka v. Umadevi, reported in (2006) 4
SCC 1. He also relies on another judgment of said Court in Official
Liquidator v. Dayanand, reported in (2008) 10 SCC 1, paragraphs
59, 101, 115 and 116. Mr. Mishra submits, none of the 43 workmen
are at present working for his client in any of his client's projects.
Affidavit saying so has been filed. He submits, there be interference on
the award as containing findings based on no evidence.
WP(C) no.8856 of 2010
5. Mr. Satpathy, learned advocate appearing for the Union
(opposite party no.2) relies on impugned award. He submits, it was a
trial on evidence resulting in finding on facts. Opportunity was given
to the management and they adduced evidence. This being the writ
Court, as different from an appellate Court, on such an award there
should be no interference.
6. The writ petition was presented on 11th May, 2010 impugning
award dated 30th March, 2010. It was heard on several occasions and
as aforesaid, dealt with by the learned Single Judge on judgment dated
21st April, 2017. Said judgment was set aside in writ appeal by order
dated 4th April, 2019, on ground no.9 taken therein saying that the
judgment was passed after period of six years since date of argument
and therefore, vitiated due to inordinate delay. The Division Bench,
following judgments of the Supreme Court in Bhagwandas
Fatechand Daswani v. HPA International, reported in (2000) 2 SCC
13 and Kanhaiyalal v. Anupkumar, reported in (2003) 1 SCC 430,
set aside the judgment. There was a Special Leave Petition filed but
dismissed by the Supreme Court on order dated 19th August, 2019.
Hence, the writ petition is before us on remand.
WP(C) no.8856 of 2010
7. Perused impugned award. We find that particulars of the 43
workmen were given therein, as aforesaid. They have claimed to have
been employed in various divisions in years 1985 and 1992, to work as
casual workers in different posts such as Work Sarkar, Clerk, Fire
Guard, Electrical Helper, Supervisor, Pump Operator, Peon,
Watchman etc. On query from Court, it could not be shown from
impugned award that the workmen had made out a case in the labour
Court, of having been employed through contractors. On the contrary
there is record in impugned award that case of the workmen was, from
inception their employment was with the corporation and they had
rendered services to it. Only with a view to frustrate their claim, the
management has taken plea of their engagement through contractors.
8. On the side of the workmen two witnesses were examined.
They exhibited several documents, which were appreciated by the
labour Court to indicate their engagement by the management. The
Court below, however, recorded that the two witnesses were asked in
cross-examination and had admitted that managing director of the
corporation is the appointing authority in respect of Class-III and
Class-IV employees. It is clear from impugned award, the workmen
WP(C) no.8856 of 2010 could not produce any document of appointment issued by the
appointing authority.
9. The management also adduced evidence. They produced
documents of a contractor. The labour Court found that though the
management witness had produced contractor's document but
surprisingly, he himself did not know the contractor. Further finding of
the labour Court is that such documents were of year 1996 onwards
and not prior thereto, the workers claim of engagement in years 1985
and 1992, as aforesaid. We notice, the contractor himself/themselves
did not take the box as party witnesses of the management.
10. We extract and reproduce below the passage from failure
report dated 23rd September, 2008, relied upon on behalf of the
management.
"Though the payment was made through the contractors but they are working in the same place under direct control and supervision of the management since last five to six years. Further none of the contractor have work orders continuously for five to six years under the management as principal employer. So the management is paying wages to the workers through different contractors and supervision and control of their work is being done by the management.
Neither the principal employer has obtained registration for engagement of contractor to do the work of these workers through contractors nor the contractor have obtained licence for execution of
WP(C) no.8856 of 2010 work and engagement of these labourer from the appropriate Authority as per the provisions of Contract Labour (R&A) Act. Further none of the contractor have issued wage slips or service certificate to these workers in support of their engagement. Hence these daily rated workers can not be treated as contract labour in accordance with the Contract Labour (R &A) Act. It is only an after thought concept of the management to treat these workers as contract labour without any documentary in accordance with law."
(emphasis supplied)
The Conciliation Officer filed the report. Said officer was not a
witness in the labour Court. Above passage in the report being
appreciation of said officer regarding case of the parties or specifically
the workmen, same could not be relied upon as evidence in the labour
Court, unless the officer had been examined therein. Nevertheless, the
report can be said to be in favour of the workman. The appreciation of
the situation by the officer found confirmation by the findings on facts
in impugned award.
11. We made query to Mr. Satpathy regarding any document
relied upon by the labour Court in respect of the workmen against
serial nos.34, 35 and 43, respectively being Parsuram Pattanaik,
Dayananda Dehury and Prasnta Kumar Senapati. Nothing could be
shown.
WP(C) no.8856 of 2010
12. Impugned award contains findings of facts. Exhibit 1 relied
upon by the workmen is office order dated 8th May, 2008. We extract
subject passage from said order and reproduce it below.
"Pursuant to the decision taken by the Board of Directors in its 72nd meeting held on 28.1.2008 & 2.2.2008 vide Agenda No.19, the following NMR/DLR/NMR on Contract basis employees are hereby regularized in the posts and scale of pay as mentioned against their names each subject to the following terms conditions."
We are clear in our mind the tribunal relied on the documents
produced by the workmen. They had engagement from the
management, was inference drawn on trial upon having evidence laid
before the Court. In such a situation we have before us the contentions
of the management, on reliance upon above referred circular, of
embargo in engagement of workmen. Yet, the management by the
office order had regularized on 8th May, 2008, contract basis
employees in the posts and scales of pay as mentioned therein. This
regularization made indicates, the circular dated 6th May, 1986 was not
adhered to or complied with. Mr. Mishra submits, those workmen,
regularized by said office order, had been engaged prior to year 1986.
The position that emerges is, even contractual workers had been
regularized by the management and here, evidence before the labour
WP(C) no.8856 of 2010 Court was that some of the workmen had been engaged in year 1985,
prior to year 1986. The management produced documents of a
contractor to show engagement from year 1996 but the contractor did
not take the box to prove those documents.
13. Dayanand (supra) is of no aid to petitioner, having placed
reliance on paragraphs 59, 101, 115 and 116 of the judgment. The
Supreme Court in paragraph 59 said that creation and abolition of
posts, formation and structuring/re-structuring of cadres, prescribing
the source and mode of recruitment and qualification and criteria on
selection, etc. are matters, which fall within the exclusive domain of
the employer. There is no controversy regarding that in the case before
us. Here, petitioner has petitioned for judicial review over impugned
award directing regularization. Paragraphs 101,115 and 116 are on
legitimate expectation. Our appreciation of impugned award is that
regularization was directed thereby on findings of fact, of engagement
of the workmen by the corporation in various divisions and posts. In
those circumstances, case of the management that the workers had
been engaged through contractors was not accepted, to direct
regularization. Said direction was not made on finding that the workers
had a legitimate expectation to be regularized and, therefore, there
WP(C) no.8856 of 2010 should be direction accordingly. The workers had not claimed such on
basis of any assurance held out by the management. It was nobody's
case that the management had given assurance of absorbing the
workmen.
14. In view of above discussion we do not find reason to interfere
with impugned award. We are reminded of the declaration of law
made by the Supreme Court regarding interference with award on
industrial disputes made by the Supreme Court in Syed Yakoob v.
Radhakrishnan, reported in AIR 1964 SC 477.
15. The writ petition is dismissed.
(Arindam Sinha) Judge
(S. K. Mishra) Judge
P.C.Dash
WP(C) no.8856 of 2010
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!