Citation : 2022 Latest Caselaw 7151 Ori
Judgement Date : 7 December, 2022
ORISSA HIGH COURT: CUTTACK
W.P.(C) No.24000 of 2019
In the matter of an application under Articles 226 and 227 of
the Constitution of India
----
Satyashri Mohapatra ..... Petitioner
-Versus-
State of Odisha and others ..... Opp. Parties
For Petitioner : Mr. R.N. Parija, Adv.
For Opp. Parties : Mr. S.K. Samal, A.G.A.
P R E S E N T:
THE HONOURABLE MR. JUSTICE SANJAY KUMAR MISHRA
Date of Hearing : 15.09.2022 and Judgment: 07.12.2022
S.K. Mishra, J. The Petitioner has filed the Writ Petition, being
aggrieved by Order dated 26.11.2019, as at Annexure-1, vide
which his representation to grant and release all the service and
financial benefits at par with his counter parts, in terms of the
Notification dated 14.05.2019, as at Annexure-8, was rejected
by the Opposite Party No.1.
2. Accordingly, a prayer has been made to set aside the said
Order dated 26.11.2019, and to direct the Opposite Parties to
grant and release all the service as well as financial benefits to the Petitioner, as was being granted in favour of the
counterparts of the Petitioner, in terms of the Notification dated
14.05.2019.
3. This case has checked history. The case of the Petitioner is
that way back on 28.10.1994, he was allowed to work as
NMR/DLR Engineer under the Water Resources Department
with due approval of the Department after following due
procedure of law. After his appointment as such, he was
discharging his duties at par with Assistant Engineers to the
utmost satisfaction of the Authorities. There was no adverse
remark communicated to him during his entire service career
and he used to draw a consolidated payment of Rs.2,000/-,
which was at par with scale of pay of the Assistant Engineers
during the year, 1994, which was also increased subsequently
at par with the revision of pay of Assistant Engineers.
The Government of Odisha, Water Resources Department,
vide letter dated 27.02.2004, appointed 10 nos. of NMR/DLR
Graduate Engineers, including the Petitioner, against the
sanctioned post of Assistant Engineer by following due
procedure of law.
While the Petitioner and similarly placed 9 others were
continuing as such, some of the Junior Engineers, working
under the Department of Water Resources, approached the
Tribunal challenging the appointment of the Petitioner and 9
others, which was registered as O.A. No.504/2004. Finally, the
Tribunal disposed of the said O.A. by setting aside the Order
dated 27.02.2004 with an observation/direction that it would
not be a bar as to the continuance of the affected persons as
DLR Engineers for discharging some technical duties without
the designation or responsibility of Sub-Divisional Officers.
4. Challenging the said judgment passed by the Tribunal, the
Petitioner, along with similarly placed 9 others, preferred Writ
Petition No.1748/2007 before this Court. While issuing notice,
as an interim, it was ordered that continuance of the Writ
Petitioners in the posts held by them will be abided by the result
of the Writ Petition and the said Writ Petition is still pending for
consideration before this Court.
5. It is further case of the Petitioner that during pendency of
W.P.(C) No.1748/2007, the Opposite Parties decided that those
persons, who are continuing as NMR/DLR Graduate Engineers
like the persons, who were engaged prior to 12.04.1993, would
be brought over to work-charged establishment as Assistant
Engineer (work-charged) with pay band of Rs.9300-34800 and
Grade pay of Rs.4600/- and in terms of the said decision, vide
letter dated 28.05.2009, a request was made to the Opposite
Party No.1 to ensure that the Engineers, who are working as
NMR/DLR, to be brought over to work-charged establishment.
Pursuant to such request, the Finance Department gave
concurrence to such proposal. After such concurrence, one
Sarat Chandra Gouda, who was working as NMR Graduate
Engineer, was brought over to work-charged establishment.
However, the case of the Petitioners in W.P.(C) No.1748/2007
was not taken into consideration.
6. Being aggrieved by such discriminatory act of the Opposite
Parties, the Petitioner, along with other Writ Petitioners, in
W.P.(C) No.1748/2007, filed Misc. Case No.9411/2012, which
was disposed of vide Order dated 17.07.2012, with the following
observations:
Misc. Case No.9411 of 2012 " Heard learned counsel for the parties. Pendency of the writ application will not be a bar for consideration of the case of the petitioners for the post of Work Charged Assistant Engineers.
The Misc. Case is accordingly disposed of."
7. After the said Order was passed by this Court in Misc.
Case No.9411/2012, out of 10 writ Petitioners, 9 NMR/DLR
Engineers were brought over to the work-charged
establishment, vide Notification dated 08.02.2013 and the
Petitioner was singled out and he was allowed to continue as
contractual Assistant Engineer. Challenging such
discriminatory act of the Authority, the Petitioner was
constrained to approach the Tribunal in O.A. No.2415 (C)/2015,
with a prayer to direct the Opposite Parties to regularize his
service as Assistant Engineer (Mech.)/Assistant Executive
Engineer (Mech.) with an alternative prayer to extend the relief,
as was being granted to similarly placed 9 contractual
Engineers. The Tribunal, vide judgment dated 03.03.2017, was
pleased to allow the said O.A. Pursuant to the judgment passed
in O.A. No.2415(C)/2015, vide Notification dated 09.10.2017,
the Petitioner was brought over to work-charged establishment
w.e.f. 08.02.2013 i.e. the date on which the similarly placed 9
counterparts employees were brought over to work-charged
establishment.
8. It is further case of the Petitioner that, vide Resolution
dated 21.03.2013 of the Department of Water Resources, there
was a restructuring of cadre of Orissa Engineering Services and
Diploma Engineering Service, where there is a mention that the
entry level post of the cadre of Orissa Engineering Services shall
be at the level of Assistant Executive Engineer in Junior Class-I
Branch in the cadre of pay in PB-3, Rs.15600-39100/- with GP
Rs.5400/-.
9. After such Resolution was passed by the Department of
Water Resources, and during pendency of O.A.
No.2415(C)/2015, the Petitioner and similarly placed 9
employees preferred O.A. No.1036(C)/2016 and O.A.
No.1089(C)/2016 before the Tribunal praying therein to allow
them to be posted in the work-charged establishment as
Assistant Executive Engineer with above mentioned scale of pay
w.e.f. 21.03.2013. The said O.As. were disposed of vide a
common judgment dated 16.05.2018 directing the Opposite
Parties to treat the Applicants as work-charged Assistant
Executive Engineer against the post, which was upgraded and
to give them all the service and financial benefits from the date
the said posts were upgraded.
10. In pursuance of the said judgment of the Tribunal, the
Opposite Parties, vide Notification dated 14.05.2019, granted all
such service and financial benefits to the other 9 similarly
situated persons w.e.f. 21.03.2013, on which date the post of
"Assistant Engineer" was upgraded as "Assistant Executive
Engineer".
11. So far as the Petitioner is concerned, as per the
Notification dated 09.10.2017, he was brought over to work-
charged establishment w.e.f. 08.02.2013 as work-charged
Assistant Engineer, from which date the other similarly situated
9 employees were brought over to work-charged establishment.
Though there was no embargo on the part of the Opposite
Parties to allow the same benefit to the Petitioner, as was being
given to other 9 employees as per Notification dated 14.05.2019,
on being debarred from said benefit, the Petitioner gave a
representation on 15.05.2019 to the Authority concerned
ventilating his grievances. Since the Authority sat tight over the
matter and did not take any decision on the said representation,
he was constrained to file O.A. No.1160(C)/2019 before the
Tribunal, which was disposed of on 05.07.2019, directing the
Opposite Parties to consider and dispose of the representation of
the Petitioner within a stipulated time. On being so directed, the
Authority concerned rejected the representation of the
Petitioner, vide Order dated 26.11.2019, as at Annexure-1,
which is impugned in the present Writ Petition.
12. Though a detailed Counter Affidavit has been filed by the
State-Opposite Parties, the sum and substance of the said
Counter Affidavit is that the Petitioner was engaged as NMR
Graduate Engineer (Mech.) after 12.04.1993 i.e. the date with
effect from which instruction was issued vide letter dated
05.06.1993 of the Department of Water Resources (previously
named as Irrigation Department) imposing ban on recruitment
of work-charged/NMR/DLR employees. Thereafter, the
Petitioner along with others were appointed on contract basis
against regular sanctioned posts of Assistant Engineer, vide
Office Order dated 27.02.2004 of the Department of Water
Resources and continued as such on renewal basis every year.
Subsequently, in obedience to the Order dated 03.03.2017 of
the Tribunal in O.A. No.2415(C)/2015, the Petitioner was
brought over to work-charged establishment w.e.f. 08.02.2013
as work-charged Assistant Engineer in the scale of pay in PB-2,
Rs.9300-34800/, GP Rs.4600/- with usual D.A. and other
allowances admissible from time to time and posted as
Estimator in the O/o the Executive Engineer, Stores & Mech.
Division, Bhubaneswar, against the existing vacancy of
Assistant Executive Engineer (Mech.), vide Notification dated
09.10.2017 of the Department of Water Resources. On the other
hand, his counterparts were upgraded as work-charged
Assistant Executive Engineer in terms of the common Order
dated 16.05.2018 passed by the Tribunal, which was specific to
them only. The Petitioner is neither a similarly placed person
nor party to O.A. No.1036(C)/2016 for getting similar benefits,
as was being extended to the Applicants in O.A. No.1036(C)/
2016. Besides, a stand has been taken in the Counter Affidavit
that if the name of the Petitioner had been included in the said
common Order dated 16.05.2018, then his post could have been
upgraded as work-charged Assistant Executive Engineer along
with his counterparts.
13. It is further case of the State-Opposite Parties that the
Petitioner was brought over to work-charged establishment as
work-charged Assistant Engineer (Mech.) in compliance of the
Order of the Tribunal dated 03.03.2017 and he was posted as
Estimator in the O/o the Executive Engineer, Mech. Division,
Bhubaneswar, which was lying vacant at that time in the rank
of AEE (Mech.) consequent upon upgradation from the post of
AE (Mech.) under restructuring of OES Cadre. The posting of
the Petitioner against the post of AEE (Mech.) was just a mere
adjustment/arrangement for compliance of the Tribunal's Order
dated 03.03.2017, passed in O.A. No.2415(C)/2015.
14. In response to the said Counter Affidavit filed by the State-
Opposite Parties, the Petitioner has filed a Rejoinder Affidavit
stating therein that his case, so also case of his 9 counterparts
are on the same footing and the judgment passed in O.A.
No.1036(C)/2016 and O.A. No.1089(C)/2016 cannot be treated
as a judgment in personam, else it will amount to
discriminatory in nature. It has further been stated in the
Rejoinder Affidavit that the appointment of the Petitioner as
NMR Graduate Engineer (Mech.) after 12.04.1993 is not correct
as the Government, vide Notification dated 05.06.1993, gave an
exception that where it is considered necessary, such
recruitment shall be made with prior approval of the
Government and the appointment of the Petitioner has been
done with approval of the Government and the Tribunal, while
passing the judgment vide Annexure-5, has taken into
consideration such aspect in detail dealing with the Govt.
Notification dated 05.06.1993 and the appointment Order of the
Petitioner being done after due approval of the State Govt.,
Tribunal having taken note of said Notification dated
05.06.1993, the stand of State-Opp. Parties that the Petitioner's
appointment was after 12.04.1993 is unsustainable as the said
issue has already been adjudicated by the Tribunal and it
cannot be reopened subsequently, being already adjudicated by
the Tribunal in O.A. No.2415(C)/2015, vide judgment dated
03.03.2017.
It has further been contended in the Rejoinder Affidavit
that while complying such judgment under Annexure-5 to the
Writ Petition, the Petitioner was brought over to work-charged
establishment under Annexure-6, w.e.f. 08.02.2013 i.e. the date
on which similarly placed 9 other counterparts were brought
over to work-charged establishment. Therefore, the Petitioner
and his other 9 counterparts cannot be segregated to different
category and there is no justifiable reason to deny the benefit
what has been granted to his counterparts and now the
Opposite Parties cannot take a contrary stand denying claim of
the Petitioner as pursuant to Annexure-6, the State
Government, vide letter dated 04.12.2017 (Annexure-11), which
is addressed to the Chief Engineer (Mech.), O/o the EIC, WR,
Odisha, Bhubaneswar, relating to drawal of pay and allowances
payable to the Petitioner, clearly demonstrates that since the
Petitioner has been absorbed against the existing vacancy of
regular sanctioned post of Assistant Executive Engineer (Mech.),
his pay and allowances will be drawn against the regular post of
Assistant Executive Engineer (Mech.) as usual and his
conditions of service will be regulated as per the Odisha Work-
charged (Appointment and conditions of Service) Instructions,
1974. It is also contended in the Rejoinder Affidavit that 9
Graduate Engineers do not belong to the Cadre of Orissa
Engineering Service and those were very much continuing in the
work-charged establishment, having designated as Assistant
Executive Engineer and pay scale attached to the said post is
made available to them, whereas the same has been denied to
the Petitioner illegally on the ground that judgment under
Annexure-7 cannot be extended to the Petitioner being
judgment in personam.
Further, the stand of the Opposite Parties that the case is
subjudice before this Court is also misleading as all the 10
Graduate Engineers, including the Petitioner, are the Petitioners
in the said Writ Petition and after the Order under Annexure-3
to the Writ Petition was passed, all the Writ Petitioners,
including present Petitioner, were brought over to the work-
charged establishment w.e.f. 08.02.2013. However, the
Petitioner was discriminated on the sole ground that his
appointment is beyond 12.04.1993, which has already been
adjudicated by the Tribunal in the judgment under Annexure-5
to the Writ Petition, vide which the Tribunal has allowed the
Original Application and the said judgment has already been
compiled with by the State Government.
It is also contended in the Rejoinder Affidavit that
appointment of the Petitioner as Estimator against the existing
vacancy of Assistant Executive Engineer (Mech.) is not by way of
mere adjustment/arrangement for compliance of the Tribunal's
Order. Rather, as per communication under Annexure-11, the
Petitioner was absorbed against existing sanctioned post of
Assistant Executive Engineer (Mech.). The post "Estimator" in
the rank of Assistant Executive Engineer (Mech.) under the
Control of EIC, Water Resources, has been granted after
restructuring of Engineering Cadre, vide Annexure-12 i.e. the
Order dated 27.02.2012 of the Government of Odisha,
Department of Water Resources, regarding creation of posts.
15. Relying on the judgments of the apex Court in State of
Karnataka and others vs. C. Lalitha, reported in 2006 1 SCR
971, Purnendu Mukhopadhyay and others vs. V.K. Kapoor
and another, reported in (2007) 7 Supreme 679 and State of
Uttar Pradesh and others vs. Arvind Kumar Srivastava and
others, reported in 2015 1 SCC 347, learned Counsel for the
Petitioner submitted that the action of the Opposite Parties to
reject the representation of the Petitioner, as at Annexure-1, is
illegal, arbitrary and discriminatory and deserves to be set aside
directing the Opposite Parties to extend the same benefits, as
was being extended to his counterparts, vide Notification dated
14.05.2019, as at Annexure-8.
16. Learned Counsel for the State-Opposite Parties reiterating
the stand taken in the Counter Affidavit, submitted that the
appointment of the Petitioner being after 12.04.1993 and the
judgment under Annexure-7 being a judgment in persona and
not a judgment in rem, the Authority concerned were justified to
reject the representation of the Petitioner to treat him at par
with his counterparts, as is being claimed by the Petitioner.
17. In State of Karnataka (supra) the apex Court in
Paragraph-26 has held as follows:
" 26. Service jurisprudence evolved by this Court from time to time postulates that all persons similarly situated should be treated similarly. Only because one person has approached the court that would not mean that persons similarly situated should be treated differently. It is furthermore well- settled that the question of seniority should be governed by the rules. It may be true that this Court took notice of the subsequent events, namely, that in the meantime she had also been promoted as Assistant Commissioner which was a Category I Post but the direction to create a supernumerary post to adjust her must be held to have been issued only with a view to accommodate her therein as otherwise she might have been reverted and not for the purpose of conferring a benefit to which she was not otherwise entitled to."
(emphasis supplied)
18. Similarly, in the case of Purnendu Mukhopadhyay (supra),
vide Paragraph-19, the apex Court held as follows:
"19. In a case of this nature, in particular having regard to the fact that the respondents have granted similar benefits to others, we fail to understand as to how the decision of this Court in J.S. Parihar (supra) and Mittanlal (supra) could be applicable. The State cannot treat employees similarly situated differently. It cannot implement the orders in relation to one and refuse to do so in relation to others. It is also not a case like J.S. Parihar (supra) where while implementing the orders, a particular stand has been taken by the employer giving rise to a subsequent cause of action. It is also not a case where the order of this Court is capable to two interpretations. (See State of Bihar v. Rani Sonabati Kumari7, AIR 1961 SC 221, State of Keral v. Unni8, (2007) (2) SCC 365 and Sneh Enterprises v. Commissioner of Customs9, 2006 (7) SCC 714)."
(emphasis supplied)
19. In case of State of Uttar Pradesh (supra) vide Paragraph-
23, it was held as follows:
"23. The legal principles which emerge from the reading of the aforesaid judgments, cited both by the appellants as well as the respondents, can be summed up as under:
(1) Normal rule is that when a particular set of employees is given relief by the Court, all other identically situated persons need to be treated alike by extending that benefit. Not doing so would amount to discrimination and would be violative of Article 14 of the Constitution of India. This principle needs to be applied in service matters more emphatically as the service jurisprudence evolved by this Court from time to time postulates that all similarly situated persons should be treated similarly.
Therefore, the normal rule would be that merely because other similarly situated persons did not
approach the Court earlier, they are not to be treated differently.
(2) However, this principle is subject to well recognized exceptions in the form of laches and delays as well as acquiescence. Those persons who did not challenge the wrongful action in their cases and acquiesced into the same and woke up after long delay only because of the reason that their counterparts who had approached the Court earlier in time succeeded in their efforts, then such employees cannot claim that the benefit of the judgment rendered in the case of similarly situated persons be extended to them. They would be treated as fence-sitters and laches and delays, and/or the acquiescence, would be a valid ground to dismiss their claim.
(3) However, this exception may not apply in those cases where the judgment pronounced by the Court was judgment in rem with intention to give benefit to all similarly situated persons, whether they approached the Court or not. With such a pronouncement the obligation is cast upon the authorities to itself extend the benefit thereof to all similarly situated person. Such a situation can occur when the subject matter of the decision touches upon the policy matters, like scheme of regularisation and the like (see K.C. Sharma & Ors. v. Union of India (supra). On the other hand, if the judgment of the Court was in personam holding that benefit of the said judgment shall accrue to the parties before the Court and such an intention is stated expressly in the judgment or it can be impliedly found out from the tenor and language of the judgment, those who want to get the benefit of the said judgment extended to them shall have to satisfy that their petition does not suffer from either laches and delays or acquiescence."
(emphasis supplied)
20. It is pertinent to mention that a similar stand had been
taken by the Opposite Parties in O.A. No.2415(C) of 2015
preferred by the Petitioner before the Tribunal as to non-
consideration of the case of the Petitioner on the ground that he
was not engaged prior to 12.04.1993, so also letter of the
Government dated 05.06.1993 imposing ban for engagement of
Work-charged/NMR/DLRs and the Tribunal, vide Paragraph-6
of the said judgment dated 03.03.2017, held as follows:
"6. From the contents of the letter it appears that appointment of the applicant was found necessary, for which Govt. approved the appointment of the applicant. The order fully satisfies the requirement of the letter of the Govt. dated 5.6.1993 (Annexure-9). Since the engagement of the applicant was after 12.04.1993 but with due approval of the Govt.; he can not be discriminated from other nine graduate Engineers, who have been brought over to the work charged establishment vide order at Annexure-7 and has to be treated at par with them.
Accordingly, the O.A. is allowed, the respondent authorities are directed to treat the applicant at par with the graduate Engineers, who have been brought over to the work charged establishment as per order vide Annexure-7 and appropriate notification be issued giving him all benefits as has been extended to his counter parts vide order at Annexure-7. However, the said order is subject to the out come of the order of the Hon'ble High Court in W.P.(C) No.1748 of 2007. Action as per the observation be taken within a period of two months from the date of receipt of copy of this Order.
7. With these orders, the O.A. is disposed of."
Admittedly, the said judgment passed by the Tribunal in
O.A. No.2415(C) of 2015 has attained finality, being
implemented by the State-Opposite Parties.
21. Similarly, the Tribunal, vide common judgment dated
16.05.2018, as at Annexure-7, while allowing the said O.As,
held/directed as follows:
"15. Hence, in the result, both the O.As. are allowed. The Respod. No.3 i.e. OPSC is directed not to make recruitment pursuant to its advertisement dt.17.4.2015 so far as the post of Asst. Engineer (re-designated as Asst. Executive Engineer) which 9 nos. of applicants are holding. The applicants be treated as work-charged Asst. Executive Engineer against the post, which was upgraded and they be given all service and financial benefits from the date the post were up- graded. Besides this, the State-respondents are directed to take a policy decision to absorb the applicants in the regular service of Asst. Executive Engineer (Civil).
All these exercise be completed within a period of four months from the date of receipt of a copy this order."
(emphasis supplied)
22. Though a stand has been taken in the Counter Affidavit
that W.P.(C) No.1748/2007 is still pending for consideration
before this Court and the learned Counsel for the Petitioner also
did not controvert the said averments made in the Counter
Affidavit filed by the State-Opposite Parties, this Court made a
query, as to present status of the said Writ Petition in the
Website, and it came to the notice of the Court that the said
Writ Petition has been disposed of on 14.03.2022 with the
following Order:
" Learned counsel for the Petitioners states that in a subsequent development, these very Petitioners approached the Odisha Administrative Tribunal (OAT) with the original applications i.e. O.A. No.1036(C) of 2016 and O.A. NO.1089(C) of 2016 seeking regularization of their services. An order dated 16th May, 2018 was passed by the OAT, Cuttack allowing the said OAs. It appears that the State Government has not challenged that order and it has attained finality. He further states that a contempt petition has been filed seeking implementation of the said order. The contempt petition is pending.
It may be noted here that by an interim order passed by this Court in the present petition, it had been clarified by this Court that notwithstanding with the present petition the case of the Petitioners for regularization can still be considered. It appears that pursuant to the said interim order, the above developments have taken place.
In view of the above developments, learned counsel for the Petitioners seeks not to press the present petition with liberty to pursue the contempt petition which is stated to be pending.
The writ petition is disposed of with the above liberty."
23. In view of the admitted facts on record, as discussed in
detail in the fore-going paragraphs, so also settled position of
law, it is not open for the Opposite Parties to take a contrary
stand denying the claim made by the Petitioner to treat him at
par with his counterparts, who were applicants in O.A.
No.1089(c) of 2016 and the impugned Order of rejection, as at
Annexure-1, dated 26.11.2019 being illegal, arbitrary and
discriminatory, and contrary to judgment dated 03.03.2017 in
O.A. No.2415(C) of 2015, deserves to be set aside and
accordingly, the same is hereby set aside.
24. The Opposite Parties are directed to release all the service
and financial benefits to the Petitioner, as has already been
granted to the counterparts of the Petitioners under
Annexure-8, within a period of three months from the date of
communication of the certified copy of this order.
25. Accordingly, the Writ Petition stands disposed of. No
Order as to costs.
26. Needless to mention here that if the financial benefits in
terms of the direction given by this Court is not granted to the
Petitioner within the time stipulated, the same shall carry 8%
interest from the date of Order till the date of actual payment is
made by the Opposite Parties.
(S.K. MISHRA) JUDGE
Orissa High Court, Cuttack The 7th December, 2022/PCD
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!