Sunday, 17, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

M/S Simplex Projects Ltd. Through ... vs National Sports University (Nsu)
2022 Latest Caselaw 321 Mani

Citation : 2022 Latest Caselaw 321 Mani
Judgement Date : 27 July, 2022

Manipur High Court
M/S Simplex Projects Ltd. Through ... vs National Sports University (Nsu) on 27 July, 2022
                IN THE HIGH COURT OF MANIPUR
                                AT IMPHAL
                           WP(C) No. 428 of 2022

         M/S Simplex Projects Ltd. through its Director 19, Nellie
         Sengupta Sarani 3rd Floor, Kolkata- 70087.

                                                          ... Petitioner.
                                      -Versus -

         1. National Sports University (NSU), thorough its Vice
         chancellor, Office at 2nd Floor, Olympic Bhawan Khuman
         Lampak.

         2. M/S NBCC (India) Ltd., through its Managing Director,
         Office at NBCC Bhawan, Lodhi Road, New Delhi

                                                     ......Respondents



                           BEFORE
         HON'BLE MR. JUSTICE AHANTHEM BIMOL SINGH


           For the petitioner     :    Mr. S.D Singh, Advocate
           For                the :    Mr. M.Devananda, Advocate
           respondents
           Date of Hearing        :    07-07-2022
           Date of Order          :    27-07-2022


                                      ORDER

[1] Heard Mr. S. D Singh, learned counsel appearing for the

petitioner and Mr. M. Devananda, learned counsel appearing for the

respondents.

      WP(C) No. 428 of 2022                                       Page 1
 [2]               The fact of the present case in a nutshell is that M/S

Hindustan Steel Works Construction Ltd., a subsidiary of the NBCC

(India) Ltd., while working as Project Manager Consultant for the Ministry

of Youth Affairs and Sports published a notice inviting e-tender dated 28-

11-2018 for construction of buildings including allied external

development works for National Sports University (Package 2 - A) at

Imphal, Manipur. The value of the said tender was fixed as Rs.

96,40,07,726/- and the period for completion of the contract work was

fixed as 15 (fifteen) months and the date of commencement of the period

was to be reckoned from the 10th day after issuance of the letter of

award.

[3] The said contract work was awarded to the petitioner viz,

M.S Simplex Project Ltd, and the said contract work was to be executed

under the terms and conditions of the contract drawn up between the

parties. When the said contract work could not be completed in time, the

petitioner made a request to the employer for extension of time for

completion of the said contract work and the employer granted

provisional extension of time for completion of the said contract work

which was up to 31-12-2021. Subsequently, when the petitioner could

not complete the execution of the said contract work in time, the period

for completion of the said contract work was extended from time to time

on the request made by the petitioner and ultimately, when the petitioner

failed to complete the execution of the said contract work even during

the extended time, the respondents declined to entertain the request of

WP(C) No. 428 of 2022 Page 2 the petitioner for granting further extension of time and informed the

petitioner that they would terminate the contract and invoke the bank

guarantee. Having been aggrieved, the petitioner filed the present writ

petition praying for granting the following reliefs:

" a. Issue a Rule-in-Nisi;

b. Call for record of the case, hear the parties and make the Rule absolute;

c. Issue the writ of mandamus or any other writ/direction/order of similar nature whereby Respondents are commanded to take practical view of the volume of work and the time which are required for execution of the entire works by constituting an independent Committee and extend the period accordingly enabling the Petitioner to execute the works, even by opening the Escrow Account with full monitoring by the Respondents qua the funds to be disbursed to the agencies who are working at the site and further adhere to their own minutes of meeting and decisions for extension of time, whereby they have committed to extend the period for one year from the date of supply of the final drawings;

d. Issue the writ of prohibition or any other writ/direction/order of similar nature whereby restraining the Respondents herein from invoking and encashing the Bank Guarantees i.e., Bank Guarantee Nos. INBG07921000072 for a sum of Rs.

5,30,19.600.00, INBG07921000073 for a sum of Rs. 1,25,00,000.00, INBG07921000074 for a sum of Rs. 1, 25, 00,000.00, INBG07921000075 for a sum of Rs. 1,25,00,000.00 and INBG07921000076 for a sum of Rs. 1,06,99,632.00 Band Guarantee No. INBG07922000069 dated 22-03-2022 for a sum of Rs. 88,36,600.00 valid up to 21-03-2022, Bank Guarantee No. INBG07922000071 dated 22-03-2022 for a sum of Rs. 88,36,600.00 valid up to 21-03-2023 and the respondents be further restrained from taking any coercive action against the

WP(C) No. 428 of 2022 Page 3 Petitioner qua the contract No. HSCL-CPG/GWY15BD003/e094 (LoA)101-8874/G-16945 dated 28-01-2019.

e. Issue a writ of mandamus or any other writ/direction/order or similar nature whereby commanding the Respondents herein not to take any coercive action against the Petitioner qua the Contract No. HSCL-CPG/GWT15BD003/e094 (LoA)101-8874/G- 16945 dated 28-01-2019 and the petitioner be permitted to execute the works as per the specifications and complete the same in accordance with the terms and conditions of contract; f. Pass such and further order (s) as this Hon'ble Court may deem fit ad proper in the facts and circumstances of the present case;

g. Pending the final outcome of the present writ petition. Restrain the Respondents from taking any coercive action against the Petitioner including the invocation and encashment of Bank Guarantees as mentioned above; And/or h. Pass such and further order(s) as this Hon'ble Court may deem fit and proper in the facts and circumstances of the present case."

[4] Mr. M. Devananda, learned counsel appearing for the

respondents raised a preliminary objection on the issue of

maintainability of the present writ petition. It has been submitted by the

learned counsel for the respondents that the works for construction of

buildings including allied and external development works for National

Sports University (Package - 2A) at Imphal, Manipur was originally

awarded to the petitioner by Hindustan Steel Works Construction Ltd.

and thereafter, as per the Memorandum of Understanding dated 25-09-

2019 between the Ministry of Youth Affairs & Sports, Government of

India, and the respondent No. 2 i.e., NBCC (India) Ltd, the respondent

WP(C) No. 428 of 2022 Page 4 No. 2 was tasked with monitoring the execution of the said contract

work and to make payments to the contractors directly. It has also been

submitted by the learned counsel that the head office of the respondent

No. 2 is at New Delhi and the respondent No. 2 is carrying on its

business at New Delhi. After taking over the execution of the said

contract work from the HSCL, an Agreement of Novation and

Assignment in connection with the said contract work was signed and

executed at New Delhi between the respondent No. 2, HSCL and the

petitioner on 13th March, 2020. Learned counsel also submitted that in

Para No. 10 and 12 of the said Agreement of Novation and Assignment

dated 13th March, 2020, it has been laid down as under:

'' 10. NBCC, the Assignee shall be responsible for release of all future payments to SPL as per Agreement dated April 8th, 2019 (for Package 2-A) from the Effective date. Further SPL shall not be entitled to any compensation or any other payments due to or arising out of the present agreement from the Assignor and or the Assignee in any manner.

"12. The Courts of Delhi shall have the sole jurisdiction in respect of any disputes or claims arising out of or in respect to the present Agreement.''

[5] Mr. M. Devananda, learned counsel for the respondents

place before this Court a letter dated 07-09-2021 of the Project Manager

of the petitioner addressed to the Joint Manager of the respondent No. 2

furnishing the details of the bank account of the petitioner maintained at

UCO Bank at New Delhi which shall be used exclusively for payment in

WP(C) No. 428 of 2022 Page 5 connection with the said contract work and also requesting to release

further payment to the petitioner in respect of the said contract work

into the aforesaid bank account of the petitioner. It has also been

submitted by the learned counsel for the respondents that the bank

account of the respondent No. 2 is also at New Delhi and that the

respondent No. 2 has been making payment to the petitioner in

connection with the said contract work through the bank account of the

respondent No. 2 and that the bank accounts of the petitioner and the

respondent No. 2 are both at New Delhi. Learned counsel accordingly

submitted that, as the respondent No. 2 is carrying on its business at

New Delhi through its head office and as the Agreement of Novation and

Assignment between the petitioner and the respondent No. 2 in

connection with the said contract work was executed at New Delhi and

as the respondent No. 2 has been making payments to the petitioner in

connection with the said contract work through their banks situated at

New Delhi, cause of action arose partly in New Delhi and the Delhi High

Court has also the jurisdiction to entertain and decide any disputes or

claims arising out of or in respect of the said contract work in terms of

the provisions of Section 20 of the CPC, 1908.

[6] Mr. M. Devananda, learned counsel for the respondents

vehemently submitted that the petitioner and the respondent No. 2 have

voluntarily made an agreement in para No. 12 of the Agreement of

Novation and Assignment dated 13-03-2020 that the Courts of Delhi

WP(C) No. 428 of 2022 Page 6 shall have the sole jurisdiction in respect of any disputes or claims

arising out of or in respect of the said contract work and accordingly, the

Delhi High Court shall have the sole jurisdiction to entertain the present

writ petition and the present writ petition is not maintainable since the

jurisdiction of this Court have been ousted by the aforesaid agreement

between the petitioner and the respondent No. 2. In support of his

contention, learned counsel cited the following Judgments of the Apex

Court :-

(i) "New Moga Transport Co., through its Proprietor Krishanlal Jhanwar Vs. United India Insurance Co. Ltd. & Ors" reported in (2004) 4 SCC 677 wherein, it has been held that - "14. By a long series of decisions it has been held that where two courts or more have jurisdiction under CPC to try a suit or proceeding, an agreement between the parties that the dispute between them shall be tried in any one of such courts is not contrary to public policy and in no way contravenes Section 28 of the Indian contract Act, 1872. Therefore, if on the facts of a given case more than one court has jurisdiction, parties by their consent may limit the jurisdiction to one of the two courts. But by an agreement parties cannot confer jurisdiction on a court which otherwise does not have jurisdiction to deal with the matter.

"17. As we observed by this Court in Shriram case referring to Hakam Singh case an agreement affecting jurisdiction of courts is not invalid. It is open to the parties to choose any of the two competent courts to decide the disputes. Once the parties bind themselves as such it is not open for them to choose a different jurisdiction.

"18. Above being the factual and legal position, the inevitable conclusion is that the High Court was not justified in upsetting the order of the first appellate court. It is not a case where the chosen court did not have jurisdiction. The only question, therefore, related to exclusion of the other courts.

           WP(C) No. 428 of 2022                                             Page 7
 "19. The intention of the parties can be culled out from use of             the

expressions "only", "alone" , "exclusive" and the like with reference to a particular court. But the intention to exclude a court's jurisdiction should be reflected in clear, unambiguous, explicit and specific terms. In such case only the accepted notions of contract would bind the parties. The first appellate jurisdiction to try the suit. The High Court did not keep the relevant aspects in view while reversing the judgment of the trial court. Accordingly, we set aside the judgment of the High Court and restore that of the first appellate court. The court at Barnala shall return the plaint to Plaintiff 1 (Respondent

1) with appropriate endorsement under its seal which shall present it within a period of four weeks from the date of such endorsement of return before the proper court at Udaipur. If it is so done, the question of limitation shall not be raised and the suit shall be decided on its own merits in accordance with the law. The appeal is allowed. No cost."

(ii) "AVM Sales Corporation Vs. Anuradha Chemicals Private Ltd." reported in (2012) 2 SCC 315 wherein, it has been held that - "11. However, in this case a slightly different question arises, namely, as to whether if two courts have the jurisdiction to try a suit, can the parties to an agreement mutually agree to exclude the jurisdiction of one court in preference to the other and as to whether the same would amount to violation of the provisions of Sections 23 and 28 of the Contract Act? The said question has been answered in the affirmative by the trial court and has been upheld by the High Court.

"12. The question which has been raised in this special leave petition is not new and has been considered by this Court earlier in several decisions. We are, therefore, required to consider as to whether the cause of action for the suit filed by the respondent in Vijayawada arose within the jurisdiction of the court of the Principal Senor Civil Judge at Vijayawada, exclusively, or whether such cause of action arose both in Vijayawada and also Calcutta? "13. As has been mentioned herein before on behalf of the petitioner, it had been urged that the entire cause of action for the suit had arisen within the jurisdiction of the Calcutta courts and the courts at Vijayawada had no jurisdiction whatsoever to entertain a suit pertaining to the understanding and agreement arrived at between the parties. However, it was contended

WP(C) No. 428 of 2022 Page 8 on behalf of the respondent that its registered office was situated at Vijayawada, the invoices for the goods were raised at Vijayawada, the goods were dispatched from Vijayawada and the money was payable to the plaintiff or its nominee at Vijayawada by way of demand drafts and, accordingly, the courts at Vijayawada had the jurisdiction to entertain the suit. "14. It has often been stated by this Court that cause of action comprises a bundle of facts which are relevant for the determination of the lis between the parties. In the instant case, since the invoices for the goods in question were raised at Vijayawada, the goods were dispatched from Vijayawada and the money was payable to the respondents or its nominee at Vijayawada, in our view, the same comprised part of the bundle of facts giving rise to the cause of action for the suit. At the same time, since the petitioner-defendant in the suit had its place of business at Calcutta and the agreement for supply of the goods was entered into at Calcutta and the goods were to be delivered at Calcutta, a part of the cause of action also arose within the jurisdiction of the courts in Calcutta for the purposes of the suit. Accordingly, both the Courts within the jurisdiction of Calcutta and Vijayawada had jurisdiction under Section 20 of the Code of Civil Procedure to try the suit, as part of the cause of action of the suit had arisen within the jurisdiction of both the said courts.

"15. This leads us to the next question as to whether, if two courts have the jurisdiction to entertain a suit, whether the parties may by mutual agreement exclude the jurisdiction of one of the courts, having regard to the provisions of Section 23 and 28 of the Contract Act, 1872. Section 23 of the aforesaid Act indicates what considerations and objects are lawful and what are not, including the considerations or objects of an agreement, if forbidden by law. "18. One of the earlier cases in which this question had arisen, was A.B.C Laminart (P) Ltd v A.P Agencies. In the said case, the cause of action for the suit had arisen both within the jurisdiction of the civil court at Salem in Andhra Pradesh and in the civil court of Kaira in the State of Gujarat. The question arose as to whether since by mutual agreement the jurisdiction had been confined only to the courts within Kaira jurisdiction, the suit filed at Salem was at all maintainable? This Court inter alia held that : "10 ...... there (could) be no doubt that an agreement to oust absolutely the jurisdiction of the court will be unlawful and void being against public policy."

WP(C) No. 428 of 2022 Page 9 However, such a result would ensue if it is shown that the jurisdiction to which the parties had agreed to submit had nothing to do with the contract. If on the other hand, it is found that the jurisdiction agreed would also be a proper jurisdiction in the matter of the contract, it could not be said that it ousted the jurisdiction of the court.

"19. After considering the facts involved in the said case and the submissions made on behalf of the parties, this Court observed as follows: "18 .....Thus it is now a settled principle that where there may be two or more competent courts which can entertain a suit consequent upon a part of the cause of action having arisen there within, if the parties to the contract agreed to vest jurisdiction in one such court to try the dispute which might arise as between themselves the agreement would be valid. If such a contract is clear, unambiguous and explicit and not vague it is not hit by Sections 23 and 28 of the Contract Act. This cannot be understood as parties contracting against the statute."

"20. A similar view was taken by this Court in Angile Insulations Vs. Davy Ashmore India Ltd., wherein, the Hon'ble Judges while referring to the decision of this Court in A.B.C Laminart (P) Ltd., case, inter alia, held that where two courts have the jurisdiction consequent upon the cause of action or a part thereof arising therein, if the parties agree in clear and unambiguous terms to exclude the jurisdiction of the other, the said decision could not offend the provisions of Section 23 of the Contract Act. In such a case, the suit would lie in the court to be agreed upon by the parties. "21. This Court has consistently taken the same view in several subsequent cases. We may refer to one such decision of this Court in Hanil Era Textiles Ltd. V. Puromatic Filters (P) Ltd., where part of the cause of action arose at both Delhi and Bombay. This Court held that the mutual agreement to exclude the jurisdiction of the Delhi courts to entertain the suit was not opposed to public policy and was valid.

"22. As indicated herein earlier, in this case also the cause of action for Original Suit No. 519 of 1991 filed by the respondent before the Principal Senior Civil Judge, Vijayawada arose partly within the jurisdiction of the Calcutta courts and the courts at Vijayawada.

"23. Having regard to the provisions referred to herein above, though the courts at Vijayawada would also have jurisdiction, along with the courts at

WP(C) No. 428 of 2022 Page 10 Calcutta, to entertain and try a suit relating to and arising out of the agreement dated 23-12-1988, and the mutual understanding dated 15-05- 1989, such jurisdiction of the courts at Vijayawada would stand ousted by virtue of the exclusion clause in the agreement."

(iii) "Swastik Gases Private Limited Vs. Indian Oil Corporation Limited" reported in (2013) 9 SCC 32 wherein, the Apex Court after considering a number of its earlier judgments held that - "29. When it comes to the question of territorial jurisdiction relating to the application under Section 11, besides the above legislative provisions, Section 20 of the Code is relevant. Section 20 of the Code states that subject to the limitations provided in Sections 15 to 19, every suit shall be instituted in a court within the local limits of whose jurisdiction;

(a) the defendant, or each of the defendants, where there are more than one, at the time of commencement of the suit, actually and voluntarily resides, or carry on business, or personally works for gain; or

(b) any of the defendants, where there are more than one, at the time of the commencement of the suit, actually and voluntarily resides, or carries on business, or personally works for gain, provided that in such case either the leave of the court is given, or the defendants who do not reside, or carry on business or personally work for gain, as aforesaid, acquiesce in such institution; or

(c) the cause of action, wholly or in part arises.

"30. The Explanation appended to Section 20 clarifies that a corporation shall be deemed to carry on business at its sole or principal office in India or, in respect of any cause of action arising at any place where it has also a subordinate office, at such place.

"31. In the instant case, the appellant does not dispute that part of cause of action has arisen in Kolkata. What appellant says is that part of cause of action has also arisen in Jaipur and, therefore, the Chief Justice of the Rajasthan High Court or the designate Judge has jurisdiction to consider the application made by the appellant for the appointment of an arbitrator under Section 11. Having regard to Section 11 (12)(b) and Section 2 (e) of the 1996 Act read with Section 20 (c) of the Code, there remains no doubt that the Chief Justice or the designate Judge of the Rajasthan High Court has

WP(C) No. 428 of 2022 Page 11 jurisdiction in the matter. The question is, whether parties by virtue of Clause 18 of the agreement have agreed to exclude the jurisdiction of the courts of Jaipur or; in other words, whether in view of Clause 18 of the agreement, the jurisdiction of the Chief Justice of the Rajasthan High Court has been excluded?

"32. For answer to the above question, we have to see the effect of the jurisdiction clause in the agreement which provides that the agreement shall be subject to jurisdiction of the courts at Kolkata. It is a fact that whilst providing for jurisdiction clause in the agreement the words like "alone", "only", "exclusive" or "exclusive jurisdiction" have not been used but this, in our view, is not decisive and does not make any material difference. The intention of the parties - by having Clause 18 in the agreement - is clear and unambiguous that the courts at Kolkata shall have jurisdiction which means that the courts in Kolkata alone shall have jurisdiction. It is so, because for construction of jurisdiction clause, like Clause 18 in the agreement, the maxim expressio unius est exclucio alterius comes into play as there is nothing to indicate to the contrary . This legal maxim means that expression of one is the exclusion of another. By making a provision that the agreement is subject to the jurisdiction of the courts at Kolkata, the parties have impliedly excluded the jurisdiction of other courts. Where the contract specifies the jurisdiction of the courts at a particular place and such courts have jurisdiction to deal with the manner, we think that an inference may be drawn that parties intended to exclude all other courts. A clause like this is not hit by Section 23 of the Contract Act at all. Such clause is neither forbidden by law nor it is against the public policy. It does not offend Section 28 of the Contract Act in any manner.

"33. The above view finds support for the decisions of this Court in Hakam Singh, A.B.C Laminart, R.S.D.V Finance, Angile Insulations, Shriram City, Hanil Era Textiles and Balaji Coke.

"34. In view of the above, we answer the question in the affirmative and hold that the impugned order does not suffer from any error of law. The civil appeal is, accordingly, dismissed with no order as to costs. The appellant shall be at liberty to pursue its remedy under Section 11 of the 1996 Act in the Calcutta High Court."

  WP(C) No. 428 of 2022                                               Page 12
 [7]             Mr. S. D Singh, learned counsel for the petitioner

did not deny or controvert any of the factual position submitted by

the learned counsel for the respondents, however, learned counsel

strenuously submitted that some cause of action arose in Delhi is

irrelevant inasmuch as the contract work is to be executed in the

State of Manipur and this Court has jurisdiction to entertain and

decide the present writ petition. Learned counsel further submitted

that the agreement in Para No. 12 of the Agreement of Novation

and Assignment dated 13-03-2020 is not valid for the reason that a

private agreement entered into between the petitioner and the

respondent No. 2 cannot exclude/oust the writ jurisdiction of this

Court or confer jurisdiction in a court where no cause of action

arose. The learned counsel accordingly submitted that there is no

merit in the submission advanced by the learned counsel for the

respondents and that the present writ petition is maintainable. In

support of his contention, learned counsel for the petitioner relied

on the judgment of the Apex Court rendered in the case of

"Maharashtra Chess Association Vs. Union of India & Ors"

reported in (2020) 13 SCC 285 wherein, it has been held as

under:

"17. The observation extracted above raises an important consideration with respect to the present case. If, by the self-

imposed rule, the writ jurisdiction of High Courts is circumscribed by the existence of a suitable alternate remedy, whether constitutional, statutory, or contractual, then a High court should

WP(C) No. 428 of 2022 Page 13 not exercise its writ jurisdiction where such an alternate remedy exists. Thus, before we address the question of whether or not Clause 21 of the Constitution and bye-laws compel the Bombay High Court to abstain from entertaining the appellant's writ petition, we must first address ourselves to whether, even in the absence of Clause 21, the existence of an alternate remedy would create a bar on the Bombay High Court entertaining the appellant's writ petition.

"18. The case of the second respondent is that the dispute should be heard and decided at Chennai. It follows that if the respondents argument is accepted, the High Court of Madras would hear the present matter. Therefore, the alternate remedy (i.e, a writ petition before the High Court of Madras) is equal in every way to the present remedy sought by the appellant. The High Court of Madras imbued with the same powers in the exercise of its writ jurisdiction. The submission on the above premises is that the appellant can avail of the same relief at Chennai as it may in Mumbai. Hence, the agreement between the parties may prevail and the writ jurisdiction of the Bombay High Court under Article 226 stands ousted.

"19. This argument of the second respondent is misconceived. The existence of the alternate remedy, whether adequate or not, does not alter the fundamentally discretionary nature of the High Court writ jurisdiction and therefore, does not create an absolute legal bar on the exercise of the writ jurisdiction by a High Court. The decision whether or not to entertain an action under its writ jurisdiction remains a decision to be taken by the High Court on an examination of the facts and circumstances of a particular case.

"20. This understanding has been laid down in several decisions of this Court. In U.P State Spg. Co. Ltd. v R.S. Pandey this Court held (SCC p. 270, para 11) "11. Except for a period when Article 226 was amended by the Constitution (Forty-second Amendment) Act,, 1976, the power relating to alternative remedy has been

WP(C) No. 428 of 2022 Page 14 considered to be a rule of self-imposed limitation. It is essentially a rule of policy, convenience and discretion and never a rule of law. Despite the existence of an alternative remedy it is within the jurisdiction or discretion of the High Court to grant relief under Article 266 of the Constitution. At the same time, it cannot be lost sight of that though the matter relating to alternative remedy has nothing to do with the jurisdiction of the case, normally the High Court should not interefere if there is an adequate efficacious alternative remedy."

"21. The principle that the writ jurisdiction of a High Court can be exercised where on adequate alternative remedies exists can be traced further back to the decision of the Constitution Bench of this Court in State of U.P v Mohd. Nooh where Vivian Bose, J. observed: (AIR p. 93, para 10) "10. In the next place it must be borne in mind that there is no rule, with regard to certiorari as there is with mandamus, that it will lie only where there is no other equally effective remedy. It is well established that, provided the requisite grounds exist, certiorari will lie although a right of appeal have been conferred by statute. (Halsbury's Laws of England, 3rd Edn., Vol. 11, p. 130 and the cases cited there). The fact that the aggrieved party has another an adequate remedy may be taken into consideration by the superior court in arriving at a conclusion as to whether it should, in exercise of its discretion, issue a writ or certiorari to quash the proceedings and decisions of inferior court subordinate to it and ordinarily the superior court will decline to interfere until the aggrieved party has exhausted his other statutory remedies, if any. But this rule requiring the exhaustion of statutory remedies before the writ will be granted is a rule of policy, convenience and discretion rather than a rule of law and instances are numerous where a writ of certiorari has been issued inspite of the fact that the aggrieved party had other adequate legal remedies."

"22. The mere existence of alternate forums where the aggrieved party may secure relief does not create a legal bar on a

WP(C) No. 428 of 2022 Page 15 High Court to exercise its writ jurisdiction. It is a factor to be taken into consideration by the High Court amongst several factors. Thus, the mere fact that the High Court a Madras is capable of granting adequate relief to the appellant does not create a legal bar on the Bombay High Court exercising its writ jurisdiction in the present matter.

"26. In the present case, the Bombay High Court has relied solely on Clause 21 of the Constitution and bye-laws to hold that its own jurisdiction is ousted. The Bombay High Court has failed to examine the case holistically and make a considered determination as to whether or not it should, in its discretion exercise its powers under Article 226. The scrutiny to be applied to every writ petition under Article 226 by the High Court is crucial safeguard of the rule of law under the Constitution in the relevant territorial jurisdiction. It is not open to a High Court to abdicate this responsibility merely due to the existence of a privately negotiated document ousting its jurisdiction.

"27. It is certainly open to the High Court to take into consideration the fact that the appellant and the second respondent consented to resolve all their legal disputes before the courts at Chennai. However, this can be a factor within the broader factual matrix of the case. The High Court may decline to exercise jurisdiction under Article 226 invoking the principle of forum non conveniens in an appropriate case. The High Courto must look at the case of the appellant holistically and make a determination as to whether it would be proper to exercise its writ jurisdiction. We do not express an opinion as to what factors should be considered by the High Court in the present case, nor the corresponding gravity that should be accorded to such factors. Such principles are well known to the High Court and it is not for this Court to interfere in the discretion of the High Court in determining when to engage its writ jurisdiction unless exercise arbitrarily or erroneously. The sole and absolute reliance by the Bombay High Court on Clause 21 of the Constitution and bye-laws

WP(C) No. 428 of 2022 Page 16 to determine its jurisdiction under Article 226 is ousted, is however one such instance.

"28. We accordingly allow the appeal and set aside the impugned judgment and order of the High Court dated 25-09- 2018. Writ Petition No. 7770 of 2017 is accordingly restored to the file of the High Court for being considered afresh. No costs. Pending application (s), if any, shall stand disposed of."

[8] After hearing the rival submissions of the learned

counsel for the parties, this Court is of the considered view that

there is no dispute with regard to the fact that the cause of action

arose partly in Delhi and accordingly both this Court and the High

Court of Delhi have jurisdiction to entertain and decide the disputes

raised in the present writ petition.

[9] The principle of law that when two Courts have

concurrent jurisdiction to try the dispute between the parties and

the parties have agreed that the disputes should be tried by only

one of the courts, then the court mentioned in the agreement shall

have jurisdiction has been well settled by the Hon'ble Supreme

Court in a catenae of its judgments. In my considered view, such

principle of law had been clearly laid down by the Hon'ble Apex

Court in the case of "Hanil Era Textiles Ltd." (supra), "A.V.M

Steel Corporation" (supra), "Swastika Gases Private Ltd."

(supra) etc., relied on by the learned counsel for the petitioner.

[10] In the present case, having regard to the

undisputed facts and as the petitioner and the respondent No. 2

WP(C) No. 428 of 2022 Page 17 have voluntarily entered into an agreement in Para No. 12 of the

Agreement of Novation and Assignment dated 13-03-2020 that the

courts of Delhi shall have the sole jurisdiction in respect of any

disputes or claims arising out of or in respect of the said contract

work, this Court has no hesitation to hold that only courts of Delhi

shall have the sole jurisdiction to decide the disputes raised in the

present writ petition and in view of the exclusion clause in the

agreement, jurisdiction of this Court would stand ousted.

[11] The facts of the case of "Maharashtra Chess

Association" (supra) cited by the counsel for the petitioner is

totally different from the facts of the present case. In the said case,

no issue was raised or considered as to whether both the Courts at

Chennai and Bombay High Court have concurrent jurisdiction to

entertain and decide the disputes involved in the said case and that

it has been clearly held by the Apex Court in Para No. 26 of the said

judgment that the Bombay High Court relied solely on Clause 21 of

the Constitution and By-Laws to hold that the Bombay High Court

has no jurisdiction and that the said High Court has failed to

examine the case holistically and make a considered determination

as to whether or not it should, in its discretion, exercise its power

under Article 226. It has been further held that the scrutiny to be

applied to every writ petition under Article 226 by the High Court is

crucial safeguard of the rule of law under the Constitution in the

WP(C) No. 428 of 2022 Page 18 relevant territorial jurisdiction and that it is not open to a High

Court to abdicate the responsibility merely due to the existence of

the privately negotiated document ousting its jurisdiction.

[12] In Para No. 9 of the said judgment, the Hon'ble

Apex Court clearly upheld the principle of law that where parties to

a contract confer jurisdiction on one amongst multiple courts having

proper jurisdiction to the exclusion of all other courts, the parties

cannot be said to have ousted the jurisdiction of all court and that

such a contract is valid and will bind the parties to a civil action.

[13] In view of the above, this Court is of the considered

view that the judgment of the Apex Court in the case of

"Maharashtra Chess Association" (supra) relied by the counsel

for the petitioner is not applicable in the facts and circumstances of

the present case.

[14] Having regards to the undisputed facts of the

present case and in view of the settled principle of law laid down by

the Hon'ble Apex Court in the case relied on by the learned counsel

for the respondents, this Court is of the considered view that the

jurisdiction of this Court would stand ousted and that only the

courts of Delhi shall have the sole jurisdiction to entertain and

decide the disputes raised by the petitioner in the present writ

petition and accordingly, the present writ petition is hereby

dismissed as not maintainable. It is, however, made clear that the

WP(C) No. 428 of 2022 Page 19 petitioner will have liberty to file appropriate proceedings before the

appropriate Court to redresses any of its grievances raised in the

present writ petition. Having regard to the facts and circumstances

of the present case, the parties are to bear their own cost.




                                                  JUDGE

     FR/NFR


     kim




  WP(C) No. 428 of 2022                                        Page 20
 

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 

LatestLaws Partner Event : IJJ

 
 
Latestlaws Newsletter