Citation : 2026 Latest Caselaw 1726 Mad
Judgement Date : 9 April, 2026
OP No. 446 of 2019
IN THE HIGH COURT OF JUDICATURE AT MADRAS
DATED: 09.04.2026
CORAM
THE HON'BLE MR JUSTICE SENTHILKUMAR RAMAMOORTHY
OP No. 446 of 2019
M/s.JV Engineering Associat
Civil Engineering Contractors,
17, Kuttakattu Valasu,
Elumathur (PO), Modakkurichi (via)
Erode 638 104 (Tamil Nadu),
Rep. by its Partner Mr.S.Jaikumar
..Petitioner
Vs
General Manager,
CORE, Allahabad, Represented by
Deputy Chief Engineer, Railway Electrification,
Chennai, Egmore.
..Respondent
Petition filed under Section 34(2)(b)(ii) of The Arbitration and
Conciliation Act, 1996 to set aside the Award dated 07.11.2018 passed by
Shri V.K.Manoharan, the Sole Arbitrator
For Petitioner: Ms.Pavithra M
for M/s P.J.Rishikesh
For Respondent: Mr. P.T. Ramkumar
Standing Counsel
ORDER
An arbitral award dated 07.11.2018 pertaining to a contract for the
construction of control room for Traction Sub Station (TSS), including
earth filling and retaining wall at Uppala and Thokur and construction of
OHE depot and tower wagon shed at Mangalore junction in Palakkad
Division of Southern Railway is the subject of challenge in this petition.
__________ Page1 of 7 https://www.mhc.tn.gov.in/judis
The present challenge is the second round. In the first round, the
petitioner assailed the award on the ground that the arbitrator was
disqualified. Learned single Judge accepted the ground of challenge and
set aside the award. On appeal, a Division Bench of this Court, by
judgment dated 11.08.2021 in O.S.A.No.119 of 2021, concluded that the
petitioner had waived/consented in terms of Section 12(5) of the
Arbitration and Conciliation Act, 1996 (A & C Act) to the appointment of
the arbitrator. Therefore, the order of the learned single Judge was set
aside and the award was restored. The Supreme Court rejected the
special leave petition against said judgment. Matters were however
remanded to this Court for consideration on merits.
2. Learned counsel for the petitioner assails the arbitration award on
the following grounds:
2.1 Price variation was granted in respect of the first
three extensions of time. As regards the fourth extension, in
spite of the petitioner submitting rider agreement dated
12.12.2017 pertaining to another contract with the Railways,
wherein price variation was granted partly, the Arbitral
Tribunal disregarded such evidence;
2.2 The award is inadequately and improperly
reasoned. In Dyna Technologies Private Limited vs.
Crompton Greaves Limited [(2019) 20 SCC 1], the Supreme
Court interfered with an arbitral award on the ground that
__________ Page2 of 7 https://www.mhc.tn.gov.in/judis
provision of reasons is mandatory under Section 31(3) of A
& C Act unless parties agree otherwise. Applying said
principle to this case, learned counsel contends that the
award is vitiated by inadequate or improper reasoning.
3. In response, learned standing counsel for the Railways submits
that the petitioner signed rider agreement dated 29.06.2017 for extension
of the agreement from 01.04.2017 to 31.07.2017 under Clause 17-A(ii) of
the General Conditions of Contract without applicability of price variation.
He referred to the counter statement before the Arbitral Tribunal in
support of his contention. Referring to the arbitral award, learned counsel
pointed out that the Arbitral Tribunal took note of the fact that the rider
agreement was executed in relation to the fourth extension without price
variation. As regards the reference to the submission of the rider
agreement pertaining to an unconnected contract, learned counsel
contends that price variation cannot be granted merely because it was
agreed to in another contract.
4. The claims made by the petitioner before the Arbitral Tribunal are
as under:
S.No. Details of Claims Claim Amount
in Rs.
1 The PVC calculations have been 3,26,470/-
made upto CC VII. For further bills
and final bill, clear instructions with regard to RBI indices are awaited from Railway Board
__________ Page3 of 7 https://www.mhc.tn.gov.in/judis
S.No. Details of Claims Claim Amount in Rs.
2 Legal cost 1,00,000/-
(lumpsum) 3 Compensation for mental agony, 5,00,000/-
unnecessarily making me to run (lumpsum) pillar to post just to establish the genuineness of my claim 4 Interest for the delay in making the 19,588/-
payment of PVC (Unspecified, From 24.08.2017
depending on the period of delay) @ 12% simple
interest
Total 9,46, 058/-
5. Out of the above claims, the claims for legal cost and interest are
contingent on the petitioner succeeding in relation to the primary claims
for price variation and compensation for mental agony. A claim for
compensation for mental agony cannot be made in relation to a
commercial contract between parties. In any event, no evidence has been
adduced in support of the claim for mental agony. Therefore, no case is
made out to interfere with the rejection of said claim.
6. As regards the claim for price variation, learned counsel for the
petitioner contended that price variation was granted in respect of the
first three extensions of time. She also submitted that price variation was
granted in relation to an unconnected contract with the Railways with
price variation notwithstanding the rider agreement. The agreed position
is that the rider agreement was executed in the case at hand in relation to
the fourth extension without price variation. As a creature of contract,
the Arbitral Tribunal is bound by the terms of such rider agreement unless
__________ Page4 of 7 https://www.mhc.tn.gov.in/judis
the petitioner were to establish that such rider agreement is either void or
voidable. There was neither pleading nor evidence to support and
establish that rider agreement was void or voidable. In those
circumstances, the Arbitral Tribunal examined the claim for price variation
and held as follows:
Reasons for the award:
On going through the relevant records, it is noticed
that the initial currency of this work was upto 18.04.2016.
Claimant had asked for 4 extensions and all 3 currency
extension were given with PVC and 4 th extension was
given without PVC and accordingly rider agreement was
also executed.
The respondent made it clear in his submission that
the PVC amount for the period upto 31.07.2017 for which
the extension was granted with PVC, the claimant is
eligible for PVC amount. However, the claimant not yet
submitted the claim for PVC amount. The 4th extension was
granted without PVC by the competent authority. Hence,
not eligible for any PVC amount. Moreover, claimant’s
claim of considering the PVC is mandatory if the extension
is granted under 17(A) or 17(B) as similarly done in some
other Railways, sufficient time was given to submit the
record of similar cases with other Railways, but claimant
__________ Page5 of 7 https://www.mhc.tn.gov.in/judis
could not submit any proof to substantiate his claim. In
view of the above, claimant’s claim is not valid.
7. The Arbitral Tribunal has taken note of the fact that the fourth
extension was given without price variation and that the rider agreement
was executed in that regard. For reasons discussed above, the Arbitral
Tribunal was bound to take note of the contractual clauses accepted by
the parties. Therefore, I find no infirmity warranting interference under
Section 34 of the A & C Act. Hence the challenge to the arbitral award
fails and the original petition is dismissed without any order as to costs.
09.04.2026 Index: Yes/No Neutral Citation: Yes/No mmi
To
The General Manager, CORE, Allahabad, Represented by Deputy Chief Engineer, Railway Electrification, Chennai, Egmore.
__________ Page6 of 7 https://www.mhc.tn.gov.in/judis
SENTHILKUMAR RAMAMOORTHY, J.
mmi
09.04.2026
__________ Page7 of 7 https://www.mhc.tn.gov.in/judis
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!