Monday, 18, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Andal Dorairaj vs /
2025 Latest Caselaw 8965 Mad

Citation : 2025 Latest Caselaw 8965 Mad
Judgement Date : 27 November, 2025

Madras High Court

Andal Dorairaj vs / on 27 November, 2025

Author: G.Jayachandran
Bench: G.Jayachandran
                                  IN THE HIGH COURT OF JUDICATURE AT MADRAS

                                            Reserved on                :10.11.2025

                                            Pronounced on              :27.11.2025

                                                          CORAM

                         THE HONOURABLE Dr. JUSTICE G.JAYACHANDRAN
                                             and
                    THE HONOURABLE MR.JUSTICE MUMMINENI SUDHEER KUMAR

                                       C.M.A.Nos.1212,1213 and 1214 of 2024
                                                         and
                            C.M.P.Nos.10817, 10819 of 2024, 16062 of 2025, 10818 of 2024
                            16063 of 2025, 10821 of 2024, 10822 of 2024 and 16056 of 2025

                  C.M.A.No.1212 of 2024

                  1.Andal Dorairaj
                  W/o Dorairaj,
                  Door No.45,
                  Kamaraj Road, Red Fields,
                  Coimbatore 641 018.

                  2.Vidhya Sharathram
                  W/o Sharathram
                  Door No.45,
                  Kamaraj Road, Red Fields,
                  Coimbatore 641 018.

                  3.D.Sharathram,
                  1/69



https://www.mhc.tn.gov.in/judis               ( Uploaded on: 27/11/2025 06:25:47 pm )
                  S/oDorairaj
                  Door No.45,
                  Kamaraj Road,Red Fields,
                  Coimbatore 641 018.                           ..Appellants/Respondents
                                                                1 to 3

                                                           /versus/




                  1.M/s Rithwik Infrastructure (P)Ltd.,
                  Rep.by its Authorised Signatory
                  Mrs.Priya Rajashekar
                  Registered Office at
                  RR Towers III, TVK Industrial Estate Guindy,
                                                     st
                  Chennai 600 032.                ..1 Respondent/Petitioner

                  2.M/s Hanudev Info Park(P) Ltd.,
                  Rep.by its Authority Signatory R.Neelakantan
                  Registered Office at
                  RR Towers III,
                  TVK Industrial Estate Guindy,
                  Chennai 600 032.

                  3.M/s Rithwik Info Park (P)Ltd.,
                  Registered Office at
                  RR Towers III,TVK Industrial Estate Guindy,
                  Chennai 600 032.               ..Respondents 2 & 3/
                                                 Respondents 4 &5

                            Civil Miscellaneous Appeal has been filed under Section 37(1) of the


                  2/69



https://www.mhc.tn.gov.in/judis               ( Uploaded on: 27/11/2025 06:25:47 pm )
                  Arbitration & Conciliation Act r/w Section 13 of the Commercial Courts Act,

                  2015, against the order dated 17.04.2024 made in Arbo.O.P.No.5 of 2024 on

                  the file of the Commercial Court (District Judge Cadre), Coimbatore.



                            For Appellants   :Mr.M.S.Krishnan, Senior Counsel for
                                              Mr.M.Sundara Kadeswaran

                            For Respondents :Mr.P.H.Arvind Pandian, Senior Counsel
                                            for Mr.Bharathkumar




                  C.M.A.No.1213 of 2024:

                  1.Andal Dorairaj
                  W/o Dorairaj,
                  Door No.45,
                  Kamaraj Road, Red Fields,
                  Coimbatore 641 018.

                  2.Vidhya Sharathram
                  W/o Sharathram
                  Door No.45,
                  Kamaraj Road, Red Fields,
                  Coimbatore 641 018.

                  3.D.Sharathram,
                  3/69



https://www.mhc.tn.gov.in/judis              ( Uploaded on: 27/11/2025 06:25:47 pm )
                  S/o Dorairaj
                  Door No.45,
                  Kamaraj Road,Red Fields,
                  Coimbatore 641 018.                        ..Appellants/Respondents
                                                             1 to 3



                                                        /versus/



                  1.M/s Hanudev Info Park(P) Ltd.,
                  Rep.by its Authority Signatory R.Neelakantan
                  Registered Office at
                  RR Towers III,
                  TVK Industrial Estate Guindy,
                  Chennai 600 032.                      ..1st Respondent/Petitioner

                  2.M/s Rithwik Infrastructure (P)Ltd.,
                  Rep.by its Authorised Signatory
                  Mrs.Priya Rajashekar
                  Registered Office at
                  RR Towers III, TVK Industrial Estate Guindy,
                  Chennai 600 032.




                  3.M/s Rithwik Info Park (P)Ltd.,
                  Registered Office at
                  RR Towers III,TVK Industrial Estate Guindy,
                  Chennai 600 032.                    ..Respondents 2 & 3/
                                                            Respondents 4 &5
                  4/69



https://www.mhc.tn.gov.in/judis            ( Uploaded on: 27/11/2025 06:25:47 pm )
                            Civil Miscellaneous Appeal has been filed under Section 37(1) of the

                  Arbitration & Conciliation Act r/w Section 13 of the Commercial Courts Act,

                  2015, against the order dated 17.04.2024 made in Arbo.O.P.No.6 of 2024 on

                  the file of the Commercial Court (District Judge Cadre), Coimbatore.

                            For Appellants    :Mr.Sathish Parasaran, Senior Counsel for
                                               Mr.K.S.Karthik Raja

                            For Respondents :Mr.P.V.Balasubramanian, Senior Counsel for
                                             Mr.R.Bharath Kumar

                  C.M.A.No.1214 of 2024:
                  1.Andal Dorairaj
                  W/o Dorairaj,
                  Door No.45,
                  Kamaraj Road, Red Fields,
                  Coimbatore 641 018.

                  2.Vidhya Sharathram
                  W/o Sharathram
                  Door No.45,
                  Kamaraj Road, Red Fields,
                  Coimbatore 641 018.

                  3.D.Sharathram,
                  S/o Dorairaj,Door No.45,
                  Kamaraj Road,Red Fields,
                  Coimbatore 641 018.                  ..Appellants/Respondents 1 to 3

                                                           /versus/
                  5/69



https://www.mhc.tn.gov.in/judis               ( Uploaded on: 27/11/2025 06:25:47 pm )
                  1.M/s Rithwik Info Park (P) Ltd.,
                  Rep.by its Authorised Signatory
                  Priya Rajashekar
                  Registered Office at
                  RR Towers III, TVK Industrial Estate Guindy,
                  Chennai 600 032.                     ..1st Respondent/Petitioner



                  2.M/s Hanudev Info Park (P) Ltd.,
                  Rep.by its Authority Signatory R.Neelakantan
                  Registered Office at
                  RR Towers III,
                  TVK Industrial Estate Guindy,
                  Chennai 600 032.

                  3.M/s Rithwik Infrastructure (P)Ltd.,
                  Rep.by its Authorised Signatory
                  Mrs.Priya Rajashekar
                  Registered Office at
                  RR Towers III,
                  TVK Industrial Estate Guindy,
                  Chennai 600 032.                      ..Respondents 2 & 3/
                                                              Respondents 4 &5



                            Civil Miscellaneous Appeal has been filed under Section 37(1) of the

                  Arbitration & Conciliation Act r/w Section 13 of the Commercial Courts Act,

                  2015, against the order dated 17.04.2024 made in Arbo.O.P.No.7 of 2024 on

                  the file of the Commercial Court (District Judge Cadre), Coimbatore.

                  6/69



https://www.mhc.tn.gov.in/judis               ( Uploaded on: 27/11/2025 06:25:47 pm )
                            For Appellants   :Mr.Aniruth Krishnan for
                                              Mr.K.S.Karthik Raja



                            For Respondents :Mr.N.Sridhar for
                                             Mr.R.Bharathkumar
                                                      ------

                                             COMMON JUDGMENT



Dr.G.JAYACHANDRAN,J.

& MUMMINENI SUDHEER KUMAR,J.

These three Appeals C.M.A.No.1212 of 2024, C.M.A.No.1213 of 2024

and C.M.A.No.1214 of 2024 filed under Section 37 of the Arbitration and

Conciliation Act, 1996. The appeals are directed against the Common Order

https://www.mhc.tn.gov.in/judis ( Uploaded on: 27/11/2025 06:25:47 pm ) passed by the Commercial Court at Coimbatore in Arb.O.P.Nos:5, 6 and 7 of

2024 filed under Section 34 of Arbitration and Conciliation Act, 1996.

2. Andal Dorairaj, Vidya Sharathram and Sharathram are Members

of one family, holding land in their individual name and in the name of minor

children of Sharathram, which they got through partition of their ancestral

property. In respect of their respective shares in the property, three Joint

Venture Agreements (in short “JVA”) were entered on 24.03.2006 and

06.07.2006 with the developer M/s Hanudev Info Park (P) Ltd, a construction

company. The terms in these 3 JDA's were almost identical, except minimal

differences, which are not substantial. Later, on reunion of the family, all the

owners jointly executed a Supplementary Memorandum of Agreement to the

Developer on 13.09.2007 consolidating their lands for convenient

development purpose. The parties agreed to share the build up area at 80%

and 20% between the builder and the owners respectively, which comes

https://www.mhc.tn.gov.in/judis ( Uploaded on: 27/11/2025 06:25:47 pm ) around 2,11,385 sq.ft. in the super build up area and car parking space,

depending upon the FSI. The possession of the property was handed over to

the developer and the owners have received Rs.1,60,00,000/- towards

refundable security deposit. The supplementary agreement substantially

retained the terms and conditions contained in the earlier agreements. The

owners executed sale deed on 16.03.2009 in favour of the Developer M/s

Hanudev Infopark (P) Ltd and its two nominee M/s Rithwik Infrastructure

Pvt. Ltd and M/s Rithwik Infopark Pvt. Ltd in respect of 80% of undivided

share out of total land.

3. As per the terms of the contract, the developer has to commence the

construction and complete the construction of the building within 24 months,

from the date of boomi pooja or such other date on which the construction

actually commences or from the date of receiving the sanctioned plan,

whichever is later. If the construction is not completed within the time agreed,

to the extent of incomplete portion of share, the developer has to pay Rs.15/-

https://www.mhc.tn.gov.in/judis ( Uploaded on: 27/11/2025 06:25:47 pm ) per sq.ft every month as compensation for a period of 6 months. If the

construction is still not completed even after the expiry of the extended 6

months period, the JDA shall stand cancelled.

4. That apart, the developer has agreed to identify tenants for the 20%

portion of the build up area within 6 months from the date of completion of

construction for a period of 8 years, with minimum rent at the rate of Rs.30/-

per sq.ft., per month with enhancement of 15% at the end of every 3 years

and in case of any shortfall in the rent, the developer will make good the

difference.

5. Alleging delay in completing the construction, one of the owners

Andal Dorairaj, issued notice dated 01.11.2011 to the Developer and its

nominee under Section 21 of Arbitration and Conciliation Act, 1996 (in short

“the Act”) to initiate arbitration. Thereafter, she filed O.P.No:808 of 2012

and O.P. No:824 of 2012 before this Court under Section 11(6) of the Act for

https://www.mhc.tn.gov.in/judis ( Uploaded on: 27/11/2025 06:25:47 pm ) appointment of an Arbitrator to resolve the dispute. The OPs were allowed by

the High Court vide order dated 19.02.2016 appointed

Mr. V.Sivasubramaniam a retired District Judge as an Arbitrator. On

29.01.2019, his mandate was terminated and another Arbitrator by name

Mr.S.A.Sreeramulu was appointed. The mandate for Mr. S.A.Sreeramulu was

also terminated in the subsequent order of this Court in O.P.No.694 of 2019

dated 08.09.2019 in which Mr.K.Kannan, a retired High Court Judge was

appointed as Arbitrator. The owners as claimants sought the following relief:-

(i)Award for Rs.24,29,30,250/- as compensation for delay in handing

over the build-up area as per the Joint Development Agreement dated

24.03.2006 and 06.07.2006.

(ii)Award towards rental arrears promised to be paid to the claimant for

Rs.75,67,90,620/- by way of compensation.

(iii)Award for Rs.1,71,81,503/- for the tax mulcted on the 1st claimant.

(iv)Award for Rs.3,63,28,840/- for the tax amount payable by the 3rd

claimant.

https://www.mhc.tn.gov.in/judis ( Uploaded on: 27/11/2025 06:25:47 pm )

(v)Declare the Joint Development Agreement dated 24.03.2006 and

06.07.2006 as cancelled due to non-performance.

(vi)Declare the three Sale Deeds dated 16.03.2009 as null and void.

(vii)Declare the encumbrance created in the property way of equitable

mortgage with LIC and

(viii)Award costs.

6. Before the Learned Arbitrator, preliminary objection raised by the

developer was dismissed. Against the dismissal order dated 15.12.2020, the

developer preferred C.M.A.No.376 of 2021 and same was dismissed on

29.04.2021. S.L.P.No.8005 of 2021 against the dismissal of C.M.A.No.376 of

2021 was also dismissed by the Hon'ble Supreme Court on 26.07.2021.

Thereafter, the Learned Arbitrator completed the arbitral proceedings

(Arbitration Case No:9 of 2020) and passed the Award on 27.10.2021.

7. The result of the Arbitration Award:-

https://www.mhc.tn.gov.in/judis ( Uploaded on: 27/11/2025 06:25:47 pm )

(a)The relief of setting aside the sales, cancellation of JDAs is declined

and in lieu thereof, the claimants are granted the relief or recovery of

possession of 1,95,463.862 sq.ft., of build-up area as corresponding to 2.67

FSI within the undermentioned property. This shall come from Tower-D in

full, which is said to be 1,24,000 sq.ft and the balance will come from Tower-

C. Along with this shall be the entire car park in Tower-D and the place

earmarked for car park for Tower-C that will be proportionate to build-up are

made available to the claimants against the total build-up area in Tower-C.

(b)The damages for the period immediately for a period of six months

immediately on completion of 24 months from 01.11.2008 is declined.

(c)The relief of damages for loss of rent for claimants 1 to 3 shall be

from 01.11.2011 till the end of October 2021, for a sum of

Rs.83,96,23,641.93, which is the aggregate amount payable as calculated in

paragraph 65 of the Order.

(d)The respondents shall be liable to pay to the claimants for each

month, commencing from 01.11.2021 the amount of Rs.89,12,538.70, till the

https://www.mhc.tn.gov.in/judis ( Uploaded on: 27/11/2025 06:25:47 pm ) date of delivery of possession of property.

(e)The amount determined as payable to the claimants shall be

apportioned amongst themselves in the proportion set out in the Supplement

Agreement under Ex.C7.

(f)The amount determined shall constitute a charge over 80% of the

property of the Respondents that have been transferred through Ex.C8 to

C10, in the schedule below in priority of the mortgage created in favour of

LIC Housing Ltd., under Ex.C42 to C44.

(g)The claim for damages for capital gain notice received by claimants

1 & 3 is declined, subject, however, that any amount in excess of the amount

assessed by the authorities for delayed payment shall be recoverable by the

claimants against the respondents.

(h)The Respondents are restrained from selling their property without

performing all obligations under the JDA of completion of all constructions.

(i)The Respondents are liable for the amount determined to pay interest

at 15% per annum from the date of the Award till the date of payment.

https://www.mhc.tn.gov.in/judis ( Uploaded on: 27/11/2025 06:25:47 pm )

(j)The Claimants are entitled to cost of Arbitration of Rs.18,50,000/-

which are the Arbitrator's fee said to have been paid in earlier part of the

arbitral proceedings and evidenced through bank transfers and also the legal

fee, which I determined for seniors and juniors at Rs.25 lakhs and there

would be Rs.5 lakhs towards stationary and out of pocket expenses.

8. Challenging the Arbitral Award, Arbitration Original Petitions under

Section 34 of the Act, were filed by the developers before the District Court

Coimbatore. Later, the same were transferred to the Commercial Court at

Coimbatore and renumbered as Arb.OP Nos: 5, 6 and 7 of 2024.

9. The Commercial Court has set aside the award and allowed the

petitions by its order dated 17.04.2024. The said order is impugned before

this Court under Section 37 of the Act.

https://www.mhc.tn.gov.in/judis ( Uploaded on: 27/11/2025 06:25:47 pm )

10. We before adverting to the merits, for easy reference, the reasons

given by the Commercial Court for interfering the Arbitral Award under

Section 34 of the Act are summarised as under: -

(a) As per the claimants, the date of Multi Storey Building Plan

approval (18.07.2008) is the date of commencement of the construction. The

24 months time to complete the construction ends on or before 17.07.2010.

According to the Developers, the date of completion should be reckoned from

the date of Building License and Plan approval, (i.e.) 28.10.2011. The 24

months period for completion ends only on 27.10.2013. It is nobody's case

that, the commencement of construction starts from the date on which Boomi

Pooja done. However, the Arbitral Tribunal has taken the month of Boomi

Pooja (October, 2006) as the date of commencement of the construction and

held that the building should have been completed on or before September,

2008. This finding according to the Court below is perverse, patently illegal

and against the public policy of India.

https://www.mhc.tn.gov.in/judis ( Uploaded on: 27/11/2025 06:25:47 pm )

(b) In the first legal notice dated 15.03.2011, the claimants admit that

no building plan approval was sanctioned till date and in the second legal

notice dated 01.11.2021 (Ex.D24), they admit that the building plan approval

was obtained only by the Developers. The content of these two notices give

no room for any ambiguity that the claimants are well aware of the difference

between Ex.C11 and Ex.D23 and no allegation of fraud was raised in Ex.C13

and Ex.D24. Thus, without considering those aspects and valid available

evidence, the Arbitral Tribunal wrongly held that the respondents

(Developers) obtained sale deeds by showing Ex.C11 as building approval

plan. This finding is perverse, patently illegal and against the public policy of

India.

(c) In the petition, compensation for delay in handing over the build up

area claimed only by the first claimant Mrs.Andal Dorairaj for her share of

80,175 sq.ft. No relief of compensation for delay was claimed by the other

claimants 2 and 3. In the claim statement, loss of rental income from

17.01.2011 to 17.04.2019 alone is claimed. Without any prayer, relief of

https://www.mhc.tn.gov.in/judis ( Uploaded on: 27/11/2025 06:25:47 pm ) compensation of Rs.39,99,60,000/- was awarded to the first claimant and the

third claimant as representative of the joint family. Likewise, without any

prayer, the Arbitral Tribunal granted damages for loss of rent for the

claimants 1 to 3, from 01.11.2011 to till the end of October 2021. When the

building is not completed, the question of claiming rent does not arise as per

the terms of the agreement. While so, the Arbitral Tribunal failed to note that

the claimants themselves have demanded compensation for the alleged loss

of rental income up to 17.04.2019, the Arbitral Tribunal erroneously granted

compensation up to 31.10.2021. When the developers are liable to pay the

rent in respect of the completed building only after 6 months of the

completion of the building for 8 years to the second and third claimants and

for 8 years 6 months to the first claimant Mrs.Andal Dorairaj, the finding of

the Tribunal in granting damages for loss of rent from 01.11.2011, till the date

of delivery of possession is not correct. Clause 10 is not obligatory on the

part of the developers to fix a tenant prior to the completion of the building.

The Arbitral Tribunal contrary to the agreed terms of Ex.C-4 and Ex.C-6,

https://www.mhc.tn.gov.in/judis ( Uploaded on: 27/11/2025 06:25:47 pm ) found fault with the developer in finding the tenant in advance, which is not

correct. Hence, fixing compensation to loss of rent is perverse, illegal and

against the public policy of India.

(d) Without pleadings, proof and prayers, the Arbitral Tribunal had

granted charge decree over the 80% share of the developer with priority over

the mortgage created in favour of LIC Housing Finance, which is contrary to

Section 55(4)(b) of the Transfer of Property Act, 1882. After termination of

the JDA's from 01.11.2011, the grant of damages for the past loss of rent and

for future till delivery of possession is in violation of Section 55 of the

Limitation Act, 1963. It is not known, why the Arbitral Tribunal has taken

(Ex.D23) the date of Building Plan approval as date of completion for

computing compensation.

11. Contention of the appellants/Claimants:

11(a) In the appeals under consideration, the learned Senior Counsels

on behalf of the the appellants/claimants contended that, the scope to interfere

https://www.mhc.tn.gov.in/judis ( Uploaded on: 27/11/2025 06:25:47 pm ) an award is limited to the parameters laid in Section 34 and the judicial

interpretations on the scope and ambit of Section 34. While so, the reasoning

of the Court below for interfering with the well considered Arbitral Award is

beyond the scope of Section 34 of the Act. The Court below erred by re-

appreciating the evidence and substituted its view. It had wrongly understood

the law of limitation. It has failed to apply the judicial precedents, which has

held, the power of the arbitrator extends to grant relief not limited to the relief

sought but also to grant any other relief, which subsumes the larger relief

sought/prayed.

11(b) In the instant case, the owners of the land having handed over the

land to the developer in the year 2006, is still waiting for the developer to

hand over 20% of the build area. Though the developer admits, they have

commenced the construction in the year 2006, and completed construction of

two towers by 2009 and promised the owners to fix the tenants and they will

be getting rent from 01.04.2009 and got the sale deeds for the 80% share in

https://www.mhc.tn.gov.in/judis ( Uploaded on: 27/11/2025 06:25:47 pm ) the land, by citing the letter to terminate the contract and the suits filed by the

minors to ascertain their rights in the property, which noway impaired or

impeded the developer from completing the construction and letting it out to

third parties, however, till date the developer is not ready to hand over the

20% build up area as per the terms of the contract. He is also not ready to

disclose the details of the tenants and the rents, he has collected from them.

Due to the erroneous order by the Court below, for nearly two decades, the

owners of the land are deprived from the fruits of their property. On the other

hand, the developer, who had put up the construction, has been enjoying the

proceeds exclusively even without rendering accounts.

11(c) The land owners prayed for cancellation of the agreement relying

on Clause 8 (k) which says, if the developers do not complete and hand over

1,32,000 sq.ft to the owners in such period (i.e 24 months (initial) + 6 months

(extended) from the date of commencement of construction), then the Joint

Development Agreement shall stand cancelled. The Arbitrator had passed the

https://www.mhc.tn.gov.in/judis ( Uploaded on: 27/11/2025 06:25:47 pm ) award balancing the interest of the land owners and the developers. He had

assigned reasons for granting a lesser relief along with justification for not

granting the larger relief, as prayed.

11(d) It is an admitted fact that on the date of filing the claim petition

or even later, though several years have gone, after completion of the

construction, the developer has not handed over the 20% of the build up area

to the land owners, but enjoying it exclusively. Though this one conduct is

suffice for the cancellation of JDA's, the Arbitrator considering the attending

circumstances, has given a lesser relief, which is in fact an advantage to the

developer, who had parted his investment in developing the property. The

relief claimed and the relief granted are not unconnected or beyond the scope

of the reference to the dispute, but well within the scope of the reference.

11(e) Unfortunately, the Court below failed to consider the terms of the

contract and the communications between the parties. It had swayed by

https://www.mhc.tn.gov.in/judis ( Uploaded on: 27/11/2025 06:25:47 pm ) irrelevant factors and had substituted its own view to the facts of the case. It

had set aside the well considered award of the Tribunal by terming it as

perverse, illegal and against the public policy of India. This borrowed

expression employed mechanically without any application of mind by the

Court below needs interference.

11(f) The learned Senior Counsel for the appellants/claimants

submitted that, the Arbitration Act does not prescribe moulding relief within

the terms and scope of the agreement. For that matter, no law condemns

decisions tempered with equity, justice and morality. The Arbitral award had

not gone beyond the matter submitted, while so, in ignorance of the proviso

to Section 34(2)(iv), the Court below had set aside the award in entirety.

11(g) The Court below erred in faulting the finding of the arbitrator

fixing the date of commencement. The expression 'which ever later' in Clause

6 (g) of JDA is not intended to keep the last event to happen. The proper

https://www.mhc.tn.gov.in/judis ( Uploaded on: 27/11/2025 06:25:47 pm ) interpretation of Clause 6(g) of JDA could be, granting 24 months for the

developer to complete the construction. In this case, it is admitted by the

developer as well as the claimants that, the construction commenced much

prior to the building plan approval. The developer in its e-mail dated

18.12.2008, wrote to Sharathram one of the claimants that, "we have a client,

who needs Rs.1 lakh sq.ft. space, and he will be signing the agreement, if the

rent is Rs.20/- per sq.ft. for the first year, Rs.25/- per sq.ft. for the second

year and Rs.30/- per sq.ft. for the third year. The rent will start from March

2009. On the same basis, I have spoken to a few other and expect that by Jan-

2009, the rest of the space will also be leased out. "Having expressly admitted

that the building is ready for occupation and the prospective tenants will

occupy by March 2009 and rent will come from March 2009, still if the

developer claims that he will not hand over the 20% share in the build up area

and neither will pay rent for the space, till the end of 24 months from the date

of plan approval, will be an interpretation of the Clause leading to absurdity.

The Learned Arbitrator had considered the date of planning permission, the

https://www.mhc.tn.gov.in/judis ( Uploaded on: 27/11/2025 06:25:47 pm ) date of tax assessments for the building, as well as the communication of the

developer about the readiness of the building to fetch rent from March 2009

as per the e-mail dated 18.12.2008 followed by another positive assertion in

its e-mail dated 12.01.2009 stating that, he had finally concluded with the

client for a rent of Rs.20/- per sq.ft. the agreement is ready and will be

forwarded for signature. The owners shall start getting rent from the 1st of

April 2019. The Court below ignoring this candid admission by the developer

about the completion of the construction, by making selective reference to the

terms of the contract and communication, has termed the Arbitral Award as

perverse, while the converse being the truth.

11(h) The Arbitrator had concluded that the construction commenced

soon after boomi pooja, which was held during the month of October 2006

based on the evidence given by the witness for the claimants as well as the

witnesses for the developer. They both had admitted that the construction

commenced in the month of October 2008. The witness for developer

https://www.mhc.tn.gov.in/judis ( Uploaded on: 27/11/2025 06:25:47 pm ) admitted in the cross examination that after G.O.Ms.No.169 dated

12.09.1996, it was enough, if the entrepreneurs submit application for

approval to the proper authorities. They need not wait for approval of these

plans before construction.

11(i) In view of this GO, for commencement and completion, approval

of building plan is not significant. In one of his mail, the developer had stated

that, he had not got the full sanction officially. So, he can even hide behind

the Clause, which gives 24 months time for completion from the date of

getting complete plan sanction. However, it is not morally correct. The

Arbitrator, after recording these unassailable evidence that, the construction

started in October 2008, 24 months time for completion ends in October

2010, after the grace period of 6 months is over, the developer is expected to

hand over the 20% build up area to the owners. The developer in fact even

informed one of the owners that they will start getting rent from April 2009.

However, considering the fact that even though the developer had informed

https://www.mhc.tn.gov.in/judis ( Uploaded on: 27/11/2025 06:25:47 pm ) that the owners will start getting rent from April 2009, its occupation could

be only after the approval of plan (Ex.D-23), which was signed on

28.10.2011. Hence, the Arbitrator awarded compensation for rental loss only

from 28.10.2011 and not from October 2010. The Court below had misread

the award and conveniently ignored the admission of the developer. The

award, which in full comity with the fundamental policy of Indian Law and in

consonance with the basic notions of morality and justice was perversely set

aside by the Court below by unreasonably terming it as illegal.

11(j) The reasons stated by the Court below to set aside the award of

the Arbitral Tribunal, are all as a result of improper understanding of the law

and precedents, had led to grave miscarriage of justice.

11(k) The Court below had substituted its view, after re-appreciating

the evidence and gone to the extent of suggesting that, the claimants ought to

have moved the Civil Court for specific performance.

https://www.mhc.tn.gov.in/judis ( Uploaded on: 27/11/2025 06:25:47 pm ) 11(l) Conveniently ignoring the facts on record that Mrs.Andal

Dorairaj sought for arbitration in the year 2011 itself and the application for

appointment of arbirator initiated by Mrs.Andal Dorairaj in the year 2012,

had observed that granting damages covering the period from 2011 is barred

by limitation.

11(m) Likewise, his conclusion that the award of compensation from

October 2019, till the date of handing over the possession, as beyond the

scope of reference, is also erroneous, since the said relief is ancillary to the

relief directing the developer to handover the agreed extent of build up area

as per the terms of the contract.

11(n) In commercial contracts, awarding interest for the delay in

payments is permissible. But, the Court below has termed awarding interest

for the money due and payable as illegal, perverse and contrary to the public

https://www.mhc.tn.gov.in/judis ( Uploaded on: 27/11/2025 06:25:47 pm ) policy. The arbitral award, giving primacy to the charge over 80% of the

property sold by the owners to the developer, is to be viewed from the right

of the owner envisaged under the Transfer of Property Act. The financial

creditor namely, LIC Housing Finance Co, had advanced loan to the

developer subsequently. The sale of property to the developer though

completed, is being coupled with the obligations mentioned under the JDA's,

the developers cannot contend that the provisions of Transfer of Property Act

will not apply. Therefore, the award holding that the charge over the

properties transferred to the developer under Ex.C8 to Ex.C10 to be in

priority of the mortgage created in favour of LIC Housing Ltd under Ex.C42

to Ex.C44, is legal and within the scope of the reference and prayer (vii).

Even if, in view of the Court that there was any transgression from the scope

of reference, it, by applying the principle of severability, ought to have

interfered only in respect of those portions and ought to have not set aside

the entire award.

https://www.mhc.tn.gov.in/judis ( Uploaded on: 27/11/2025 06:25:47 pm )

12. Submission by the Learned Senior Counsels for the Respondents:-

12.(a) In defence of the impugned order passed by the Court below,

the learned Senior Counsels for the respondents/developers and its nominees,

providing a comparative table between the relief sought before the Arbitrator

and the relief actually granted by the Arbitrator emphasised that, the Court

below is right in setting aside the arbitral award which suffers patent illegality

and perversity. He also submits that the Arbitrator had travelled beyond the

terms of the contract as well as the terms of reference. By granting relief,

without prayer, the Arbitrator has re-written the contract. It is a fact that the

developer got the plan approved only on 13.09.2011 and as per Clause 8(h)

and (i) of the Agreement, the 24 months period for completion of the building

commences only from that date. The plain reading of the Clause with no

ambiguity will show that the completion date to be reckoned from any of the

three points which ever is later.

12(b). Clauses 8 (h) and (i):-

https://www.mhc.tn.gov.in/judis ( Uploaded on: 27/11/2025 06:25:47 pm )

(h)Period of completion of construction-24 months

from the date of “Bhoomi” pooja or such other date on

which the construction actually commences or from the date

of receiving the sanctioned plans whichever is later.

(i)The DEVELOPERS agree to complete the

construction of the building all respect within 24 months

from the date of shall be recorded and attested by the

OWNERS and developers whichever is later.

12(c). Without proper reasons, the Arbitrator has awarded damages of

Rs.83,96,23,641.93 calculating from 01.11.2011 to October, 2021 a relief not

even sought for by the owners/claimants. The owners, after entering into

JDAs for themselves and for the minors, set up the minors to challenge the

agreement. They interfered in the project in all manners possible. Leasing of

the 20% of the owners portion was agreed only on the condition that fixation

of rent to be agreed by both the parties mutually. While the communications

between the parties show that tenancy could not be fixed due to the delay in

https://www.mhc.tn.gov.in/judis ( Uploaded on: 27/11/2025 06:25:47 pm ) arriving at a consensus, regarding the rent totally attributing to the owners

conduct. The Arbitrator, ignoring all these facts in lieu of the prayer for

cancellation of the sale deeds and JDA's, had awarded compensation for loss

of rent not only from 01.11.2009 to October 2021 but also ordered the

developers to pay a sum of Rs.89,12,538.70 every month till date of delivery

of 1,95,463.862 sq.ft of build up area.

12(d). When the relief in the claim petition is for cancellation of the

registered documents, which were acted upon, recovery of possession and

damages, from 01.11.2008, being a baseless award, perverse and contrary to

public policy, the Court below has rightly interfered and set aside the award.

12(e). The Court below had not re-appreciated the evidence, but had

examined the evidence and recorded that the Arbitrator has failed to apply the

correct interpretation, while appreciating the evidence. It was pleaded that,

the award creating charge over 80% undivided share of the land sold to the

https://www.mhc.tn.gov.in/judis ( Uploaded on: 27/11/2025 06:25:47 pm ) developers and its nominees by the owners in priority to the mortgage charge

held by LIC Housing Ltd. a secured financial creditor is in gross violation of

law. Awarding 15% interest for the amount wrongfully determined is top of

all perversity.

12(f). The comparative table furnished by the respondents being

comprehensive and precise, the same is extracted below for easy reference:-

Reliefs sought in the claim & Reliefs granted in the award:

Reliefs sought in paragraph 33 of the Reliefs granted in paragraph 91 of the Joint Claim Statement by claimants Award

a)Award of Rs.24,29,30,250/- to 1st Declined (Award paragraph 91b) appellant Andal Dorairaj as compensation for delay in handing over the built-up area as per the JDA dated 24.03.2006 and 06.07.2006.

b)Award of Rs.75,67,90,620/- to 1st Declined (Award paragraph 91b) Appellant Andal Dorairaj as compensation for delay in handing over the built-up area as per the JDA dated 24.03.06 & 06.07.2006.

c)Pay Rs.1,71,81,503/- to 1st appellant Both the reliefs declined. Andal Dorairaj towards proceedings initiated by the IT Department for capital Instead recovery from the respondents if gain concerning the Sale deeds dated any excess amount assessed by the IT 16.03.2009. Department for delayed payments.

https://www.mhc.tn.gov.in/judis ( Uploaded on: 27/11/2025 06:25:47 pm )

d)Pay Rs.3,63,28,840/- to 3rd claimant (But no prayer) (Award paragraph 91g) towards proceedings initiated by the IT Department for capital gain concerning the Sale deeds dated 16.03.2009.

e)Declare that the JDAs dated 24.03.2006 Both the reliefs declined and 06.07.2006 as cancelled due to non-

performance, fraudulent representation and In lieu thereof recovery of possession of misrepresentation on the part of respondent. 1,95,463,862 sq.ft of build up area is granted

f)Declare that the three Sale Deeds dated 16.03.2009 as null and void. (But no Prayer) (Award Paragraph 91a)

g)Direct the respondents to clear the No discussion with regard to this relief. encumbrance created in the property by creating an equitable mortgage with LIC Housing Finance Limited.

                   No prayer                                      Damages      for   loss    of   rent    of
                                                                  Rs.83,96,23,641.93 to the claimants 1 to 3
                                                                  from 1.11.2011 to October 2021.
                                                                  (Award Paragraph 91c)
                   No prayer                                      Directing the respondent to pay a sum of
                                                                  Rs.89,12,538.70 for each month till date of
                                                                  delivery of possession.
                                                                  (Award paragraph 91 d)
                   No prayer                                      Charge decree is granted over the 80%
                                                                  share of the property of the respondent for
                                                                  the amount determined above i.e., amount
                                                                  mentioned in Award paragraph 91c & d

                                                                  (Award paragraph 91 f) in priority of the
                                                                  mortgage created in favour of LIC Housing
                                                                  Limited.
                   No prayer                                      Respondents are restrained from selling





https://www.mhc.tn.gov.in/judis               ( Uploaded on: 27/11/2025 06:25:47 pm )
                                                                      their property until their obligations for
                                                                      completion of construction under the JDA
                                                                      (Award paragraph 91h)
                   No prayer                                          Interest at 15% ordered for the amount
                                                                      determined. (Award paragraph 19i)




                            13. Court finding:-

The scope and power of the Courts under Sections 34 and 37 of the Act

been dealt by the Courts adequately and the Learned Senior Counsels

appearing on either side, had relied on multiple decisions on the same

proposition of law to enlighten about the position of law and precedents.

However, from out of those decisions cited, the recent and relevant judgments

necessary for this Court to decide the points for consideration are:

(1)Gayathri Balasamy -vs- ISG Novasoft Tech Ltd.reported in [(2025)

7 SCC 1];

(2)Larsen and Tubro Ltd -vs- Puri Construction Pvt Ltd. Reported in

[2025 SCC Online SC 830];

(3)IRCTC -vs- M/s Brandavan Food Products Ltd. reported in [2025

https://www.mhc.tn.gov.in/judis ( Uploaded on: 27/11/2025 06:25:47 pm ) SCC Online SC 2369];

(4)SSangyong Engineering and Construction Co Ltd -vs- National

Highways Authority of India (NHAI) reported in [(2019) 15 SCC 131];

(5)Adavya Projects Pvt. Ltd. -vs- Vishal Structural Pvt. Ltd. and others

reported in [AIR 2025 SC 2485].

14. Other judgements referred by the learned Senior Counsels are

mostly referred and discussed in the above judgements. Hence, we refrain

from listing out all those judgments.

15. The Hon'ble Apex Court had consistently held that, the powers of

the Appellant Court under Section 37 of the Act is not broader, than those of

the Courts under Section 34 of the Act. The recent judgment dated

21.04.2025, by a Bench consisting of two Hon'ble Judges of the Supreme

Court, in Larsen and Toubro Limited v. Puri Construction Pvt.Ltd. and

others reported in (2025 SCC OnLine SC 830 at paragraph 56). With this

https://www.mhc.tn.gov.in/judis ( Uploaded on: 27/11/2025 06:25:47 pm ) prelude, we proceed with the recent judgment of the Hon'ble Suprme Court,

Indian Railways Catering and Tourism Corp.Ltd. v. Brandavan Food

Products reported in [2025 SCC Online SC 2369], wherein the Hon'ble

Supreme Court had discussed the earlier judgments on the powers of Courts

under Sections 34 and 37 of the Act and has held as below:-

62. .......It is now well settled that Section 34 of the

Act of 1996 provides limited grounds on which an arbitral

award can be set aside. Section 34(1) makes it clear that

recourse to a Court against an award may be made only by

an application to set it aside in accordance with sub-sections

(2) and (3) thereof. Section 34(2) details the grounds on

which an award may be set aside. For the purposes of this

adjudication, Section 34(2A) is also relevant. This provision

was inserted with retrospective effect from 23.10.2015, vide

Amendment Act No. 3 of 2016. It states to the effect that a

domestic arbitral award may be set aside if the Court finds

that the said award is vitiated by patent illegality appearing

on the face of that award. The proviso thereto, however, adds

a caveat that an award should not be set aside merely on the

ground of an erroneous application of the law or by re

appreciation of evidence.

63. Pertinently, Section 34(2)(b)(ii) provides that if

https://www.mhc.tn.gov.in/judis ( Uploaded on: 27/11/2025 06:25:47 pm ) the Court finds that an arbitral award is in conflict with the

public policy of India, the Court would be justified in setting

it aside. Explanation 1, as it presently reads, and

Explanation 2 were inserted by the Amendment Act No. 3 of

2016 with retrospective effect from 23.10.2015. Explanation

1 provides that, for the avoidance of doubt, it is clarified that

an award is in conflict with the public policy of India only if

its making was induced or affected by fraud or corruption or

was in violation of Sections 75 or 81 of the Act of 1996 or it

is in contravention with the fundamental policy of Indian law

or it is in conflict with the most basic notions of morality or

justice. Explanation 2 provides that, for the avoidance of

doubt, the test as to whether there is a contravention with the

fundamental policy of Indian law shall not entail a review on

the merits of the dispute.

64. In Sangyong Engineering and Construction

Company Limited v. National Highway Authority of India

(.............), this Court dealt with the expression ‘most basic

notions of morality or justice’ mentioned in Explanation 1. It

was opined that the breach must be of some fundamental

principle of justice, substantively or procedurally, which

shocks the Court's conscience. On facts, this Court found

that the award created a new contract by applying a

Circular that was not even placed before the arbitral

tribunal. It was, therefore, opined that a fundamental

https://www.mhc.tn.gov.in/judis ( Uploaded on: 27/11/2025 06:25:47 pm ) principle of justice was breached, viz., that unilateral

alteration of a contract cannot be foisted upon an unwilling

party nor can a party to an agreement be made liable to

perform a bargain not entered into with the other party. This

Court held that such course of conduct was contrary to

fundamental principles of justice followed in this country

and shocked its conscience. It was, however, cautioned that

this ground would be available in exceptional circumstances

only and under no circumstance can a Court interfere with

an award on the ground that justice, in its opinion, was not

done.

65. Again, in PSA Sical Terminals Private Limited v.

Board of Trustees of V.O. Chidambranar Port Trust,

Tuticorin6, this Court found that the arbitral tribunal had

thrust a new term into the agreement between the parties

and thereby created a new contract for them. Referring to

Ssangyong Engineering (supra), this Court affirmed that

rewriting a contract for the parties would be a breach of the

fundamental principles of justice, entitling a Court to

interfere as it would shock its conscience and would fall

within the exceptional category.

66. A little later, in State of Chhattisgarh v. SAL

Udyog Private Limited (...............), a 3-Judge Bench of this

Court dealt with the issue as to what would constitute

https://www.mhc.tn.gov.in/judis ( Uploaded on: 27/11/2025 06:25:47 pm ) ‘patent illegality’ appearing on the face of the award, in

terms of Section 34(2A) of the Act of 1996. Reference was

made to the earlier decisions in Associate Builders v. Delhi

Development Authority (..........) and Ssangyong Engineering

(supra) and it was held that the failure of the arbitral

tribunal to decide in accordance with the terms of the

contract g overning the parties would certainly attract the

‘patent illegality’ ground as the said oversight amounted to

gross contravention of Section 28(3) of the Act of 1996,

which enjoined the arbitral tribunal to take into account the

terms of the contract while making the award.

16. Again in the judgment dated 30.04.2025 rendered by the

Constitutional Bench consisting of 5 Learned Judges in Gayatri Balasamy

-vs- ISG Novasoft Tech Ltd, reported in [(2025)7 SCC 1], had reiterated while

answering the questions referred to the Constitutional Bench. Those answers

provides necessary guidelines for this Court to determine the point under

consideration.

17. For easy reference the answers to the reference is extracted below:-

https://www.mhc.tn.gov.in/judis ( Uploaded on: 27/11/2025 06:25:47 pm ) "Answers to the reference:

264.In view of the discussion herein above, the reference is

answered in the following terms:

Question 1

264.1. As set out in the body of the judgment, while

exercising power under Section 34 of the A&C Act and

consequently the Courts in the appellate hierarchy do not

have the power to modify the arbitral award.

Question 2

264.2. Modification and severance are two different concepts

while modification is not permitted under Section 34,

severance of the award failing foul of Section 34 is

permissible in exercise of powers under Section 34. Such a

power of severance is also available to the Courts in the

appellate hierarchy to the Section 34 Court.

Question 3 & 4

264.3. The power to set aside will not include the power to

modify since the power to modify is not a lesser power

subsumed in the power to set aside and as held herein above,

the power to set aside and power to modify do not emanate

from the same genus and are qualitatively different powers in

the context of the A&C Act.

Question 5

264.4. The judgment in Hakeem, insofar as it holds that a

Section 34 Court has no power to modify the award, lays

https://www.mhc.tn.gov.in/judis ( Uploaded on: 27/11/2025 06:25:47 pm ) down the correct law. The only exception made in the

judgment is with regard to the power to carry out corrections

in computational errors, clerical errors or, typographical

errors and any other errors of similar nature. This is based on

the principle of actus curiae neminem gravabit (act of court

shall prejudice no one).

265. Appreciation is recorded for the painstaking efforts put

in by the learned Solicitor General and all the learned Senior

Counsel/Counsel who addressed arguments and to the teams

assisting them.”

18. Thus, from the judgements, we with no pale of doubt are able to

say :-

(a) Section 34 of the Act provides limited grounds on which an arbitral

award can be set aside. After the insertion of the proviso by amendment Act 3

of 2006, a domestic arbitral award may be set aside if the Courts, finds that

the said award is vitiated by patent illegality appearing on the face of that

award. The proviso also adds a caveat, that an award should not be set aside

merely on the ground of an erroneous application of the law or by re-

appreciation of evidence. (Paragraph 62 in IRCTC - Brandavan Food

https://www.mhc.tn.gov.in/judis ( Uploaded on: 27/11/2025 06:25:47 pm ) Products cited supra)

(b) The expression, 'most basic notions of morality or justice', used in

Clause (iii) to explain the term 'conflict with the public policy of India' under

Section 34 (2)(v)(ii) of Arbitration and Conciliation Act, 1996 is to mean any

breach in fundamental principle of justice, substantively or procedurally,

which shocks the Court conscious. (Ssangyong Engineering and

Constructive Ltd -vs- NHAI cited supra).

(c)Thrusting a new term into the agreement between the parties and

thereby creating a new contract for them, tantamount to rewriting a contract

and that will amount to breach of the fundamental principles of justice. (PSA

Sical Terminal Pvt Ltd -vs- Board of Trustees of V.O.Chidambaranar Port,

Tuticorin and Ors. reported in [AIR 2021 SC 4661].

(d)Failure of the arbitral Tribunal to decide in accordance with the

terms of the contract governing the parties would attract the 'patent illegality'

ground and violation of Section 28(3) of the Act. (Associate Builders -vs-

Delhi Development Authority reported in [AIR 2015 SC 620]).

https://www.mhc.tn.gov.in/judis ( Uploaded on: 27/11/2025 06:25:47 pm )

(e) Modification and severance are two different concepts. While

modification is not permitted under Section 34, severance of the award is

failing foul of Section 34. Such a power of severance is also available to the

Courts in the appellate hierarchy to the Section 34. ( Gayathri Balasamy -vs-

ISG Novasoft Technologies Ltd. cited supra ).

19. If, we go back to the relief sought for by the claimants and relief

granted by the Arbitrator, which is given in the comparative table at

paragraph No.13 of this judgement, for each of the relief, we find reasoning

and justification in the award of the Arbitrator. Those reasonings are based on

the evidence on record. The parties having given a go-by to the time line

agreed. The Arbitrator has taken the admitted facts and facts proved through

documents for fixing the date of commencement of the construction and the

probable date of completion of construction. The expression 'whichever is

later' found in Clause 8 speaks about the future action of the parties. It

depends on the future conduct of the parties. Same applied on the facts

https://www.mhc.tn.gov.in/judis ( Uploaded on: 27/11/2025 06:25:47 pm ) happened after the agreement and how the parties understood the expression

and conducted themselves. Turning to the e-mail of the developer dated

24.12.2008 and 12.01.2009, it is obviously clear that the developer has

conceded that taking cover under the expression 'whichever is later' is not

correct morally and he will see to that rent start coming from April 2009.

While so, the Arbitrator on assessing the facts and evidence along with the

building plan approval and license to occupy dated 28.10.2011, had fixed the

month of completion as October, 2011.This could be the only view in the

given facts and circumstance. If for any reason one closes his eyes and claim

that the terms of contract says, 24 months period for completion must be

reckoned on the later date i.e 28.10.2011 and not the date on which the

construction actually completed, that would be the most perverse finding.

The power under Section 34 of the A&C Act is not to test the reasonableness

of the reason assigned by the Arbitrator, nor to re-appreciate the evidence for

the purpose of substituting the alternate view probable, in the view of the

Court. The power of the Court is limited to find out any patent illegality or

https://www.mhc.tn.gov.in/judis ( Uploaded on: 27/11/2025 06:25:47 pm ) perversity which shock the conscious.

20. But unfortunately the Court under Section 34 re-appreciated this

aspect of the matter and by totally ignoring the admitted stand of the

Developer that the construction was complete before April, 2009 and

payment of rent would commence from the month of April, 2009, proceeded

to hold that the Developer is entitled to complete construction on or before

27.10.2013, contra to the evidence available on record. Thus, the Court

below, erroneously interfered with the well considered findings of the learned

Arbitrator, which are based on appreciation of oral and documentary

evidence before him.

21. In fact, the learned Arbitrator, while considering the prayer and

relief sought, had consciously recorded that, “in lieu of the relief to cancel

the JDA agreements and sale, I grant the relief mentioned in the award,

upholding the sales only because I foresee the possibility of handing over

https://www.mhc.tn.gov.in/judis ( Uploaded on: 27/11/2025 06:25:47 pm ) possession in future and that will feed consideration to the sales, only in

order that the product of human labour shall not be trashed and brought to

debris.". For arriving at such conclusion, the learned Arbitrator has reduced

his decision making process into writing as is evident from paragraph Nos.66

to 70 of the Award.

22. The learned Arbitrator, thus having arrived at a conclusion that the

Developer, having got 80% of the land transferred from the claimants under

Ex.C-8, Ex.C-9 and Ex.C-10 registered documents, failed to deliver the 20%

of built up area to the claimants, instead of granting the relief of cancellation

of JDAs and Sale Deeds, deemed it appropriate to grant a lesser relief, and

accordingly granted the relief of damages for loss of rent from 01.11.2011 till

the end of October, 2021 duly arriving at a sum of Rs.83,96,23,641.93 in

terms of condition of JDAs as is evident from paragraph No.65 of the Award.

The learned Arbitrator also having taken note of the fact that Developer has

already got right over 80% of the land in terms of the JDAs, thought it fit to

https://www.mhc.tn.gov.in/judis ( Uploaded on: 27/11/2025 06:25:47 pm ) ensure that the claimants shall also get the built up area in terms of the JDAs

and accordingly ordered for the delivery of 20% of the built up area

i.e.1,95,463.862 sq.ft to the claimants from out of the construction made by

the Developer.

23. Unmindful of the decision making process undergone by the

learned Arbitrator and the reasoning for granting compensation and damages

for the delayed execution of the contract, instead of cancelling it and bring

down the construction, the Court below had set aside the award as illegal,

perverse and contrary to public policy, in total ignorance of the limitation

expressly mentioned in Section 34 of the Act, We are of the considered view

that these expressions have to go for the common judgment of the Court

below which is impugned in these appeals.

24. When the learned Arbitrator, after having arrived at the conclusions

as noted above and while declining the larger relief, granted the lesser relief

https://www.mhc.tn.gov.in/judis ( Uploaded on: 27/11/2025 06:25:47 pm ) of granting compensation etc, the Court below considered the same as the

reliefs granted without there being any prayer in that regard. If the larger

relief of cancellation of JDAs and sale deeds is granted by the learned

Arbitrator, the claimants and respondents would go back to their situation in

2006 and the developer also would loose the entire investment made on the

construction. Admittedly, the construction that was made by the developer in

Tower-C and Tower-D has been yielding rental income, though no account is

made available by the respondents to the learned Arbitrator or to the

claimants at any point of time. When the Arbitrator has balanced the

situation, taking into consideration the overall facts and circumstances,

granting the lesser relief than the relief sought for by the claimants, the same

cannot be said to be the relief granted without any prayer for the same. Thus,

the court below, without looking into these crucial aspects and without any

proper application of mind, fell in error and held that the reliefs granted by

the learned Arbitrator are without any prayer and moulding the relief is not

permissible for the Arbitral Tribunal. It is not a case where the learned

https://www.mhc.tn.gov.in/judis ( Uploaded on: 27/11/2025 06:25:47 pm ) Arbitrator moulded the relief but here it is a case of granting lesser relief than

the relief sought for. As a matter of fact, the claimants have sought for

compensation for the delay in handing over the built up area in terms of

JDAs and also towards rental arrears promised to be paid in terms of JDAs in

the claim statement, no doubt, while seeking to declare the JDAs as cancelled

due to non-performance. When there is a specific prayer that compensation

for delay and towards rental arrears, the conclusion of the court below that

the said reliefs were granted without there being any relief is absurd. So also,

when the learned Arbitrator had come to the conclusion that it would not be

in the interest of either parties to cancel the JDAs and sale deeds allowed the

same to operate. The necessary corollary is to allow the claimants to receive

their entitlement of 20% built up area in terms of JDAs in the context of the

admitted fact that the developer has already received 80% of the land towards

consideration in terms of the JDAs. But, unfortunately, the court below

adopted a pedantic, hyper technical and mechanical approach to the facts of

the case and erroneously interfered with the findings of the learned Arbitrator

https://www.mhc.tn.gov.in/judis ( Uploaded on: 27/11/2025 06:25:47 pm ) by exceeding its jurisdiction under Section 34 of the Act, 1996. At this stage,

it would be appropriate to observe that what all learned Arbitrator did is only

giving effect to the terms and conditions of JDAs and all the major reliefs

that were granted by learned Arbitrator are all well within the scope of the

JDAs. When the respondents are not seeking for cancellation of JDAs, the

respondents cannot be said to be having grievance when the JDAs are

ordered to be acted upon by the parties to the same.

25. If the common order passed by the court below is allowed to stand,

the resultant situation would be that the developer would retain the entire

built up area constructed over the land belonging to the claimants together

with the right over 80% of the undivided share of land and continue to enjoy

the rental income from the built up area and the claimants would be left with

no remedy and no benefit out of the JDAs. If such a situation is allowed to

operate, the same is nothing but travesty of justice and mockery of the entire

judicial process/system and the confidence in the entire judicial system

https://www.mhc.tn.gov.in/judis ( Uploaded on: 27/11/2025 06:25:47 pm ) would be at stake. Thus, in the light of the above, we are of the considered

view that the approach of the Court below, while exercising power under

Section 34 of the Act, 1996 is liable to be declared as perverse and nothing

but exceeding its jurisdiction.

26. The next contentious point is with regard to adding interest for the

compensation and damages. The learned Senior counsel for the appellants in

support of the arbitral award granting interest relies on, the two judgments of

the Supreme Court one, 'The Secretary, Irrigation Depat, Govt of Oriss and

others -vs- G.C.Roy (1992(1) SCC 508)' which approves imposing interest

pendente lite and another, 'Morgan Securities and credits Pvt Ltd -vs- Video

con Industries Ltd. ( 2023 (1) SCC 602)' which has held Section 31(7)(b) of

the Act does not fetter or restrict the discretion of the arbitrator to order post-

award interest, holding granting post award interest on the part of the sum are

valid.

https://www.mhc.tn.gov.in/judis ( Uploaded on: 27/11/2025 06:25:47 pm )

27. In response to the above contention made by the appellants, the

Learned Senior Counsel for the respondents states that these judgments will

have any relevance only if 'interest' for delay is part of the terms of the

agreement and not otherwise. Section 31(7)(a) and (b) of the Act and Section

28(3) of the Act if read together, the illegality in the award of the arbitrator

could be seen.

28. We find answer for this issue in paragraph 43 (i) and (ii) of

Secretary Irrigation Department, Government of Orissa and others -vs-

G.C.Roy reported in [(1992)1 SCC 508], which reads as below:-

“43.The questions till remains whether arbitrator has the power to award interest pendente lite, and if so on what

principle. We must reiterate that we are dealing with the

situation where the agreement does not provide for grant of

such interest nor does it prohibit such grant. In other words,

we are dealing with a case where the agreement is silent as to

award of interest. On a conspectus of aforementioned

decisions the following principles emerge:

(i)A person deprived of the use of money to which he

https://www.mhc.tn.gov.in/judis ( Uploaded on: 27/11/2025 06:25:47 pm ) is legitimately entitled has a right to be compensated for the

deprivation, call it by any name. It may be called interest,

compensation or damages. This basic consideration is as

valid for the period the dispute is pending before the

arbitrator as it is for the period prior to the arbitrator entering

upon the reference. This is the principle of Section 34, Civil

Procedure Code and there is no reason or principle to hold

otherwise in the case of arbitrator.

(ii)As arbitrator is an alternative form (sic forum) for

resolution of disputes arising between the parties. If so, he

must have the power to decide all the disputes or differences

arising between the parties. If the arbitrator has no power to

award interest pendente lite, the party claiming it would have

to approach the Court for that purpose, even though he may

have obtained satisfaction in respect of other claims from the

arbitrator. This would lead to multiplicity of proceedings.”

29. On turning to the Constitutional Bench of the Hon'ble Supreme

Court in Gayathri Balasamy v. ISG NOVASOFT Technologies Limited

reported in [(2025) 7 SCC 1], paragraphs 73 to 80, under the caption Post -

Award Interest, we get further clarity on this contentious issue.

IX Post-award Interest

https://www.mhc.tn.gov.in/judis ( Uploaded on: 27/11/2025 06:25:47 pm ) “73.The next question that arises is:Do courts

possess the power to declare or modify interest, especially

post-award interest? In respect of pendente lite interest,

Section 31(7)(a) (Annexure A), states that unless otherwise

agreed by the parties, the Arbitral Tribunal may include in its

sum for the award, interest, at such rate it deems reasonable

on whole or part of the money for whole or part of the period

on which the cause of action arose and the date on which the

award is made. In respect of post-award interest, Section

31(7)(b) (Annexure A) states that unless an award provides

for interest on a sum directed to be paid by it, the sum will

carry an interest at a 2% higher rate than the current rate of

interest prevalent on the date of the award, from the date of

the award till the date of payment. The Explanation defines

the expression “current rate of interest”.

74.There can be instances of violation of Section

31(7)(a), and the pendente lite interest awarded may be

contrary to the contractual provision. We are of the opinion

that, in such cases, the Court while examining objections

under Section 34 of the 1996 Act will have two options. First

is to set aside the rate of interest or second, recourse may be

had to the powers of remand under Section 34(4).

75.For the post-award interest in terms of Section

31(7)(b), the courts will retain the power to modify the

interest where the facts justify such modification. This is

https://www.mhc.tn.gov.in/judis ( Uploaded on: 27/11/2025 06:25:47 pm ) why the standard rate stipulated in clause (b) applies when

the award itself does not specify the applicable post-award

interest. There can be a situation where the party to be paid

money is at fault and is guilty of delay which may require a

modification in the rate of interest. In the absence of grant of

post-award interest in the award, the Court also possesses the

power to grant post-award interest. Clearly, as per the

legislative mandate, it is not the sole prerogative of the

arbitrator.

76.Compare Section 31 of the 1996 Act with Section

31 of the Model Law. While both sections are titled similarly

—“Form and Contents of Award”—only the 1996 Act

addresses interest in Section 31(7). The Model Law does not

provide standards governing the determination of interest

rates. Thus, Section 31(7) is a unique creation of the Indian

legislature. It was not borrowed from the Model Law.

Specifically, under Section 31(7)(b), the legislature has

established a standard rate of interest to guide the arbitrator's

discretion when it comes to determining the post-award

interest rate. While the arbitrator retains his flexibility based

on facts and circumstances of the case, the standard set by

the legislature must weigh in on their consideration. Further,

as there is a standard prescribed by the legislature, the post-

award interest awarded can be scrutinised by courts against

the standards prescribed.

https://www.mhc.tn.gov.in/judis ( Uploaded on: 27/11/2025 06:25:47 pm )

77.Our reasoning is bolstered when considering the

practical aspects. The Arbitral Tribunals, when determining

post-award interest, cannot foresee future issues that may

arise. Post-award interest is inherently future-oriented and

depends on facts and circumstances that unfold after the

award is issued. Since the future is unpredictable and

unknown to the arbitrator at the time of the award, it would

be unreasonable to suggest that the arbitrator, as a

soothsayer, could have anticipated or predicted future events

with certainty. Therefore, it is appropriate for the Section 34

Court to have the authority to intervene and modify the post-

award interest if the facts and circumstances justify such a

change.

78.Inherent in the discussion above, is the Court's

power to both increase or decrease the post-award interest

rate. It would be incorrect to state that the Court's power to

interfere with this interest rate is limited solely to decreasing

the interest rate. Situations may arise where the rate should

be increased due to delays or obstructions in the execution of

the award. Interest rates may also fluctuate over time.

79.However, the Court, while exercising this power,

must be cautious and mindful not to overstep its role by

altering the interest rate unless there are compelling and

well-founded reasons to do so. In exercising this power, the

Court is not acting in an appellate capacity, but rather under

https://www.mhc.tn.gov.in/judis ( Uploaded on: 27/11/2025 06:25:47 pm ) limited authority. For instance, the 1996 Act stipulates a

standard post-award interest rate. When the statute itself

benchmarks a standard, unless there are special and specific

reasons, the rate of interest stipulated by the statute should

be applied.

80.Nevertheless, this limited power is significant, as

it can help avoid further rounds of litigation. Without it, the

Court may be forced to set aside the entire award or order a

fresh round of arbitration because of an erroneous interest

rate rather than simply adjusting this rate.”

30. In the light of the principle laid by the Hon'ble Supreme Court, we

find no illegality or perversity in granting interest, where the agreement

between the parties does not prohibit grant of interest and the claimants who

were deprived of the lawful entitlement in the build up area and the rental

income for years together, their legitimate entitlement to be compensated, call

it by any name. It may be called interest, compensation or damages.

Nomenclature is not the matter but whether the award is within the law. If

sufficient cause is shown by the Developer, under Section 34 it is permissible

to either to set aside the rate of interest or remand under Section 34 (4) of the

https://www.mhc.tn.gov.in/judis ( Uploaded on: 27/11/2025 06:25:47 pm ) Act, In this case, neither of the situation will arise because, the rate of

interest is less than the current rate of interest as explained in the award itself.

The ordinary law emanated from the common law principle envisages

inclusion of interest to the delayed payment of monetary claims.

31. Regarding the issues, (a)whether award of the arbitrator giving

primacy to the award decree over the mortgage charge with LIC Housing

Finance Ltd, in the absence of any prayer and without hearing LIC and

(b) to the issue of fastening the additional tax on capital gains if arise

due to delay in payment of the tax as demanded by the department, the

learned Senior Counsel on the side of the appellants contend that, the reliefs

mentioned in para 91 (f) and 91 (g) are permissible in law and not illegal. The

relief is part of the prayer in the claim petition and within the scope of the

arbitral reference. That apart, for any reason the Court exercising power

under Section 34 of the Act had opined that these relief are beyond the scope

of reference, it should have applied the 'principle of severability'. It ought not

https://www.mhc.tn.gov.in/judis ( Uploaded on: 27/11/2025 06:25:47 pm ) have held the award in entirety illegal.

32. In this aspect, it is profitable to refer the judgment in

J.G.Engineers Private Limited v. Union of India and another reported in

[(2011) 5 SCC 758], wherein the Hon'ble Supreme Court has held as below:

“25. It is now well settled that if an award deals with and

decides several claims separately and distinctly, even if the Court

finds that the award in regard to some items is bad, the Court will

segregate the award on items which did not suffer from any infirmity

and uphold the award to that extent. As the award on items 2,4,6,7,8

and 9 was upheld by the Civil Court and as the High Court in

appeal did not find any infirmity in regard to the award on those

claims, the judgment of the High Court setting aside the award in

regard to Clause 2,4,6,7,8 and 9 of the appellant, cannot be

sustained. The judgment to that extent is liable to be set aside and

the award has to be upheld in regard to Claims 2,4,6,7,8 and 9.”

33. The claim petition in this case contain several claims which are

distinct and severable. The two reliefs granted 91(f) and 91 (g) are as below:-

91(f) The amounts determined shall constitute a charge over

80% of the property of the Respondents that have been transferred

https://www.mhc.tn.gov.in/judis ( Uploaded on: 27/11/2025 06:25:47 pm ) through Ex.C8 to Ex.C10, in the schedule below in priority of the

mortgage created in favour of LIC Housing Ltd., under Ex.C42 to

C44.

91(g) The claim for damages for capital gain notice received

by claimants 1 & 3 is declined, subject, however, that any amount in

excess of the amount assessed by the authorities for delayed

payments shall be recoverable by the claimants against the

respondents.

34. The corresponding prayers are:

(iii)Award for Rs.1,71,81,503/- for the tax mulched on the first

claimant (Andal Dorarirraj) and

(vii) Declare the encumbrance created in the property way of equitable

mortgage with LIC.

35. The claimants under Ex.C8 to Ex.C10, dated 16.03.2009 have

transferred to the Developer and his two nominees 80% of their right in the

https://www.mhc.tn.gov.in/judis ( Uploaded on: 27/11/2025 06:25:47 pm ) subject property totally measuring 8.03 acres. After the sale of 80% share in

the properties to the Developers and his nominees, the claimants received

notice for payment of capital gains from the Income Tax Department

demanding Tax on Capital Gains to the tune of Rs.3,63,28,840/-

36. The Arbitrator,` who framed 19 main Issues and two additional

Issues, had answered each one of the issues. In sofar as the capital gains tax,

issue 'whether the respondents 1 to 3 are liable to pay the third claimant

Rs.3,63,28,840/- towards the alleged damages suffered by the third claimant

as capital gain tax to the Income Tax Department by virtue of sale deed dated

16.03.2009?” was framed.

37. The Arbitrator under the caption “Liability to Capital Gains”

discussed this issue and finally held against the claimants. He has held that

the liability to pay the capital gains referred to the demand notice is on the

https://www.mhc.tn.gov.in/judis ( Uploaded on: 27/11/2025 06:25:47 pm ) owners. He further added, only if any excess amount demanded for delayed

payment, the same is recoverable from the respondents/ developers.

38. In this regard, we find the owners of the property sought for refund

of the demand made by the Income Tax Department for capital gains. The

Arbitrator while declining the prayer of the owners regarding payment of

capital gains, ordered the developer to pay any excess amount, if imposed by

the Income Tax Department for the delayed payment in future. This situation

may arise only if Income Tax Department issued additional demand. To grant

a releif in case of any future contingency without any cause of action for the

present, falls outside the scope of reference and invalid. Even otherwise this

relief has become infructuous as the mortgage with LIC been discharged by

the Developer prior to the date of award.

39. The Doctrine of Severability is not an unknown principle in the

domain of arbitration. In R.S.Jiwani (M/s), Mumbai v. Ircon International

https://www.mhc.tn.gov.in/judis ( Uploaded on: 27/11/2025 06:25:47 pm ) Ltd., Mumbai reported in [2010(1) Mh.L.J 547], the Full Bench of Bombay

High Court held that “severability is an established concept. It is largely

applicable to various branches of civil jurisprudence. Where it is possible to

sever the bad part from the good part, the good part of the contract can

always be enforced and partial relief can be granted. Doctrine of severability

has been applied to law of Contract, since time immemorial.”

40. In our view, the reliefs granted in para 91(f) has become

infructuous and 91 (g) falls outside the scope of the reference. However, from

out of multiple claims, these two reliefs are severable. If it is excluded as

unenforceable and invalid, the remaining part of award will sustain and it is

not suffered from any infirmity.

41. Payment of capital gains is the responsibility of the vendor. Since

there was an apparent delay in payment of consideration, the Arbitrator

https://www.mhc.tn.gov.in/judis ( Uploaded on: 27/11/2025 06:25:47 pm ) though declined prayer to return the capital gains demanded by the IT

Department has ordered payment of interest, if any claimed for delayed

payment. Such relief is not within the scope of reference, however, it is

severable. Applying the dictum laid in R.S.Jiwani's case (cited supra) and

J.G.Engineers Private Limited v. Union of India and another reported in

[(2011) 5 SCC 758], the relief regarding liberty to claim the additional capital

gain, if demanded for delayed payment sounds preposterous and being a

relief severable, the same is held as invalid.

42. Contrary to the settled legal position, the Lower Court had set aside

the entire award. Though deviation could be find only in these two reliefs in

which the relief granted in para 91(f) has become infructuous even on the

date of award. The relief granted in para 91(g) II part without any cause of

action, is invalid.

43. If in a pot of milk, a drop of poison is mixed, the entire milk need

https://www.mhc.tn.gov.in/judis ( Uploaded on: 27/11/2025 06:25:47 pm ) to be discarded, but if in a heap of grains, a few chaff pieces are found, it is

prudent to remove the chaff and retain the grains. Likewise, in this case, the

award of the Arbitrator has to be retained, removing the relief, which has

become infrucutous and another, which is invalid, both being severable. It

will be a total absurdity to set aside the entire award and suggest the parties to

re-litigate after spending nearly 20 years.

44. As a result, the Common Order of the Lower Court setting aside the

well considered Arbitraotr award is hereby set aside. As a consequence, the

Arbitration award is restored except the two reliefs mentioned in para 91 (f)

and (g), which reads as below: .

(f)The amounts determined shall constitute a charge over 80% of the

property of the respondents that have been transferred through Ex.C8 to

Ex.C10 in the schedule below in priority of the mortgage created in favour of

LIC Housing Ltd., under Ex.C42 to Ex.C44.

(g)The claim for damages for capital gain notice received by claimants

https://www.mhc.tn.gov.in/judis ( Uploaded on: 27/11/2025 06:25:47 pm ) 1 and 3 is declined (confirmed); subject, however, that any amount in excess

of the amount assessed by the authorities for delayed payments shall be

recoverable by the claimants against the respondents(invalid). The rest of the

award upheld.

45. In fine, C.M.A.Nos.1212, 1213 and 1214 of 2024 are partly allowed

with costs. Connected Miscellaneous Petitions are closed.

(Dr.G.J.J.) & (M.S.K.J.) .11.2025 Index:yes/no Internet:yes Speaking order/non speaking order Neutral citation:yes/no ari

To The Commercial Court (District Judge Cadre), Coimbatore.

https://www.mhc.tn.gov.in/judis ( Uploaded on: 27/11/2025 06:25:47 pm ) Dr.G.JAYACHANDRAN, J.

and MUMMINENI SUDHEER KUMAR,J.

ari

https://www.mhc.tn.gov.in/judis ( Uploaded on: 27/11/2025 06:25:47 pm ) Common Judgment made in C.M.A.Nos.1212,1213 and 1214 of 2024 and C.M.P.Nos.10817, 10819 of 2024, 16062 of 2025, 10818 of 2024 16063 of 2025, 10821 of 2024, 10822 of 2024 and 16056 of 2025

27.11.2025

https://www.mhc.tn.gov.in/judis ( Uploaded on: 27/11/2025 06:25:47 pm )

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 

LatestLaws Partner Event : IJJ

 
 
Latestlaws Newsletter