Citation : 2025 Latest Caselaw 2307 Mad
Judgement Date : 31 January, 2025
Arb.O.P(Com.Div.) No.333 of 2024
IN THE HIGH COURT OF JUDICATURE AT MADRAS
Reserved on : 19.12.2024
Pronounced on : 31.01.2025
CORAM
THE HONOURABLE MR.JUSTICE P.B.BALAJI
Arb.O.P(Com.Div.) No.333 of 2024
& E.P.No.13 of 2024
& E.P.DR.No.155146 of 2023
Mr.Narayanan Ramasamy
Sole Proprietor,
Sri Thenandal Films,
Regd. Office No.2/8, Eighty Feet Road,
Devar Garden, Saligramam,
Chennai – 600 093. ... Petitioner
vs.
SUN TV Network Limited,
Murasoli Maran Towers,
No.73, MRC Nagar Main Road,
MRC Nagar,
Chennai – 600 028
Rep. by its authorized signatory
Mr.M.Jyothi Basu ... Respondent
PRAYER: Arbitration Original Petition filed under Sections 11(6) of the
Arbitration and Conciliation Act, 1996, (a) to set aside the Final Award
dated 29.08.2023 passed in Arbitration O.P.(Comm.Div.) No.253 of 2022
passed by Mr.Justice V.Bharathidasan, Former Judge, Madras High Court as
1/19
https://www.mhc.tn.gov.in/judis
Arb.O.P(Com.Div.) No.333 of 2024
Sole Arbitrator in its entirely (b) to direct the respondent to pay the cost.
For Petitioner : Mr.S.Karthikei Balan
For Respondent : Mr.Jose John
for M/s.King & Partridge
ORDER
This Original Petition has been filed under Section 34 of the
Arbitration and Conciliation Act, 1996, to set aside the Final Award dated
29.08.2023 passed in Arbitration O.P.(Comm.Div.) No.253 of 2022 passed
by Mr.Justice V.Bharathidasan, Former Judge, Madras High Court, as Sole
Arbitrator, in its entirely and to direct the respondent to pay the cost.
2.The dispute arise out of a Theatrical Distribution Agreement
pertaining to the film 'Sarkar' vide Agreement dated 26.10.2018. The parties
had agreed on a minimum guarantee sum of Rs.79,50,00,000/- payable by
the petitioner. The petitioner being unable to pay the minimum guarantee
would come up with a payment of Rs.29,00,00,000/- alone, leaving a
balance of Rs.51,00,00,000/-. In order to settle the disputes, the parties
negotiated for an amicable settlement and a Memorandum of Compromise
was entered into between the parties on 23.09.2021, in and by which, the
https://www.mhc.tn.gov.in/judis Arb.O.P(Com.Div.) No.333 of 2024
petitioner transferred his immovable properties in favour of the respondent
towards part settlement of dues to the respondent, leaving a balance of
Rs.33,74,90,090/-. The Memorandum of Compromise contains arbitration
clauses (clauses 10 and 11). The petitioner did not honour the said
compromise and disputes arose between the parties.
3.The respondent/claimant made a claim before the Arbitral Tribunal
and after trial, the Arbitral Tribunal has awarded a sum of Rs.1,08,97,380/-
in favour of the respondent/claimant. Aggrieved by the said award and
challenging the same on the ground that the relief granted to the claimant is
illegal and unsustainable, being outside the scope of arbitration in terms of
Section 28 of the Act r/w Section 34(2)(a)(iv) and 34(2)(b)(ii) of the
Arbitration and Conciliation Act, 1996, the present Original Petition has
been filed.
4.I have heard Mr.Karthikei Balan, learned counsel for the petitioner
and Mr.Jose John, learned counsel for M/s.King Partridge, for the
respondent.
https://www.mhc.tn.gov.in/judis Arb.O.P(Com.Div.) No.333 of 2024
5.The learned counsel for the petitioner, Mr.Karthikei Balan, would
invite my attention to the Memorandum of Compromise dated 23.09.2021,
more specifically clause 10 of the said Memorandum of Understanding
which limits the arbitrable dispute to clause 10 of the Memorandum of
Compromise alone. He would therefore contend that the reliefs granted by
the learned Arbitrator are beyond the scope of arbitration and not arbitrable
disputes in the first place. He would further contend that the award is
opposed to public policy and hit by Section 34 of the Act. He would refer to
the written submissions of the respondent where it is said to have been
admitted by the respondent that the movie 'Sarkar' has made only a
collection of Rs.62,34,94,760.04/- and hence, there could have been no net
receipts generated in the theatrical distribution of the film and the award is
clearly contrary to the said admitted position.
6.The learned counsel for the petitioner would also refer to Income
Tax returns where the respondent has admitted to have forfeited the
amounts to the tune of Rs.1,08,97,380/-. Also referring to the decision of the
Hon'ble Supreme Court in Suresh Shah Vs. Hipad Technology India Private
https://www.mhc.tn.gov.in/judis Arb.O.P(Com.Div.) No.333 of 2024
Limited reported in (2021) 1 SCC 529, the learned counsel for the petitioner
would contend that the eviction of tenancy being a matter granted by a
special statute, disputes are non arbitrable. The relief granted to the
respondent/claimant includes the reliefs for handing over possession and the
learned counsel for the petitioner would argue that the award is patently
illegal and also oppose to public policy and hence, liable to be set aside.
7.Per contra, Mr.Jose John, learned counsel for the respondent would
submit that the petitioner had approached the respondent for grant of
exclusive license for theatrical distribution of film 'Sarkar' and an agreement
was entered into on 26.10.2018, styled as Theatrical Distribution
Agreement, granting a worldwide exclusive right to the petitioner to
distribute the film for a period of one year. The financial terms agreed
between the parties required the petitioner to pay a minimum guarantee of
Rs.79,50,00,000/-, inclusive of GST, out of which, Rs.16,00,00,000/- has to
be paid on the effective date and the remaining amount of Rs.63,50,00,000/-
to be paid prior to the proposed release date agreed upon between the
parties, namely 05.11.2018. It is further agreed that the minimum guarantee
was payable even if the net receipts generated by the film was less than the
https://www.mhc.tn.gov.in/judis Arb.O.P(Com.Div.) No.333 of 2024
minimum guarantee amount of Rs.79,50,00,000/-. It was further agreed
between the parties that any net receipts over and above the minimum
guarantee amount would be shared equally between the petitioner and the
respondent.
8.The learned counsel for the respondent would invite my attention to
the failure on the part of the petitioner to fulfill his obligations under clause
3.3.1 of the Theatrical Distribution Agreement, which required the
petitioner to give daily, weekly and monthly accounts of net receipts to the
respondent. The learned counsel for the respondent would invite my
attention to news reports reporting the huge success of the film and the film
having entered two hundred crore collection club even by day six of its
release. The learned counsel for the respondent would also invite my
attention to the Joint Memorandum of Compromise dated 16.11.2018, in
and by which, not only the petitioner but also his wife and sisters
acknowledged a sum of Rs.51,00,00,000/- to be due to the respondent and
the same was exclusive of GST and interest.
9.According to the learned counsel for the respondent, the petitioner
had failed to honour clause 10 of the Joint Memorandum of Compromise by
https://www.mhc.tn.gov.in/judis Arb.O.P(Com.Div.) No.333 of 2024
making due payments to the respondent, necessitating the respondent to
initiate arbitration proceedings. He would further refer to clause 11 of the
Memorandum of Compromise which enables the parties to raise disputes
between the learned Arbitrator with respect to issues raised in clause 10 of
the Memorandum of Compromise as well. He would further contend that the
claims were not outside the scope of arbitration as contemplated by the
parties. Further, when the petitioner had denied vacant possession of two
properties conveyed to the respondent, by way of adjustment of the
outstanding amount dues, the petitioner was only in wrongly occupation,
without even paying any rent or any other charges and therefore, the
respondent was well within its rights to claim recovery of possession in
respect of the said two properties, besides various other reliefs.
10.The learned counsel for the respondent would further submit that
Section 34(2)(a)(iv) of the Act which has been invoked as one of the
grounds to set aside the award, dealing with the dispute not contemplated or
not falling within the terms of submission of the arbitration or containing
decisions on matters beyond the scope of submission to arbitration would
not arise in the present case since the Joint Memorandum of Compromise
https://www.mhc.tn.gov.in/judis Arb.O.P(Com.Div.) No.333 of 2024
was entered only in respect of the total amounts due and since the petitioner
was unable to cough up the entire amount, the petitioner voluntarily came
forward to transfer its immovable properties, the value of which was
adjusted in the total amount due and payable to the respondent. Therefore,
the contention of the learned counsel for the respondent is that the claims
were only pertaining to the acknowledgment made by the petitioner in the
Joint Memorandum of Compromise and clearly fell within the terms of
submission to arbitration in clause 10 which is further strengthened by
clause 11 of the Joint Memorandum of Compromise. Therefore, according
to the learned counsel for the respondent, there is no contravention to
Section 34(2)(a)(iv) and hence, the award cannot be set aside on this score.
11.The learned counsel for the respondent would place reliance on
Section 28(3) of the Arbitration and Conciliation Act, 1996, requiring the
Arbitral Tribunal to take into account the terms of the contract and trade
usage applicable to the transaction while deciding and making an award.
The respondent claimant had sought interest only on Rs.33,74,90,090/- from
the date of Theatrical Distribution Agreement i.e., 26.10.2018 in respect of
Rs.51,00,00,000/- which according to the learned counsel for the respondent
https://www.mhc.tn.gov.in/judis Arb.O.P(Com.Div.) No.333 of 2024
was only an inadvertent omission and such omission would not waive or
restrict the respondent's right to receive interest as per clause 10 of the
Memorandum of Compromise. He would further contend that the petitioner
had full opportunity to reply the claim of interest of Rs.51,00,00,000/- and
the Tribunal has afforded a fair and proper opportunity to both the parties
before passing the award and therefore, the inadvertent omission cannot
prejudice the case of the parties, especially in the light of the categorical
acknowledgment to pay interest on Rs.51,00,00,000/- made by the petitioner
in the Joint Memorandum of Compromise. The learned counsel for the
respondent would therefore conclude that the award does not suffer from
any illegality warranting interference under Section 34 of the Arbitration
and Conciliation Act.
12.The learned counsel for the respondent would place reliance on the
decision of the Hon'ble Supreme Court in National Highways Authority of
India Vs. ITD Cementation India Limited reported in (2015) 14 SCC 21,
where the Honble Supreme Court held that construction of terms of a
contract is for the Arbitrator to decide even if it gives rise to determination
of a question of law and the arbitrator construes the terms of a contract in a
https://www.mhc.tn.gov.in/judis Arb.O.P(Com.Div.) No.333 of 2024
reasonable manner, then the award cannot be set aside. In other words, the
Court can interfere only in case of a perverse interpretation i.e., only if the
Arbitrator ends up construing the contract in such a way that it would to be
said to be something that no fair-minded or reasonable person would do.
The Hon'ble Supreme Court further held that the Court exercising the power
under Section 34 does not sit in appeal over findings and decisions of the
Arbitrator.
13.The Hon'ble Supreme Court, in Nayarayan Prasad Lohia Vs.
Nikunj Kumar Lohia and Others reported in (2002) 3 SCC 572, held that the
Arbitration and Conciliation Act provides for challenging the competence,
impartiality and jurisdiction of the Arbitral Tribunal before the Tribunal
itself under Sections 12, 13 and 16 and under Section 16, the Arbitral
Tribunal can rule on any objection, not only with respect to existence of
validity of the arbitration agreement, not confined to the width of the
jurisdiction and also goes to the root of its jurisdiction and when no
objection was raised under Section 16 before the Arbitral Tribunal, there is
a deemed waiver of a right to object. This decision is pressed into service to
fortify the contention of the learned counsel for the respondent by way of an
https://www.mhc.tn.gov.in/judis Arb.O.P(Com.Div.) No.333 of 2024
answer to the petitioner's arguments that the Tribunal had no jurisdiction to
grant the relief of possession and the same being beyond the scope of
arbitration and hit by Section 16 of the Arbitration and Conciliation Act.
14.In the present case on hand, the petitioner has not raised any
objections regarding the jurisdiction of the Arbitral Tribunal as available
under Section 16 and applying the mandate of Section 4, it can only be held
that the petitioner waived its right to object to the jurisdiction of the Arbitral
Tribunal, despite being clearly put on notice about the reliefs prayed for by
the claimant.
15.Further, no application under Section 16 of the Arbitration and
Conciliation Act has already been filed. Also, the requirement of handing
over possession was not on account of any Lease Agreement or any eviction
notice issued by the respondent/claimant. The relief warranting handing
over possession was only stemming from the fact that the petitioner had
offered these properties towards adjustment of his dues to the respondent
and both these properties were assigned specific market values which were
justifiable only when the properties were encumbrance free and the
https://www.mhc.tn.gov.in/judis Arb.O.P(Com.Div.) No.333 of 2024
respondent/claimant had full benefit of the transfer of said properties,
including possession of the said properties. Therefore, I am in agreement
with the argument of the learned counsel for the respondent that the
reference to arbitration under clause 10 clearly relates only to the
outstanding amount of Rs.33,74,09,090/- which would consequently and
automatically attract the other clauses 4 and 11 of the Joint Memorandum of
Compromise.
16.The contention of the learned counsel for the petitioner is that the
reference was only in respect of clause 10 and any other claim or
consequent award in favour of the claimant was beyond the scope of the
arbitration reference itself. Though the learned counsel for the petitioner
had placed reliance on the decision of the Hon'ble Supreme Court in Suresh
Shah Vs. Hipad Technology India Private Limited, reported in 2021 1 SCC
529, regarding non arbitrability of tenancy or eviction issue, I do not find
the said decision applying to the fact of the present case where the issue is
not even arising out of a lease or tenancy agreement.
17.In fact, in a later decision of the Hon'ble Supreme Court, in
Vidhya Drolia and Others Vs. Durga Trading Corporation reported in
https://www.mhc.tn.gov.in/judis Arb.O.P(Com.Div.) No.333 of 2024
(2021) 2 SCC 1, the Hon'ble Supreme Court has held that even landlord
tenant disputes governed by the Transfer of Property Act are arbitrable since
the provisions of the Transfer of Property Act do not expressly or by
implication / arbitration and as long as such disputes are not covered and
governed by rent control institutions, the same would be arbitrable.
18.The Hon'ble Supreme Court in Ssangyong Engineering &
Constructions Co.Ltd., reported in 2019 15 SCC 131, has held that so long
as disputes raised or within the ken of the arbitration agreement or the
disputes submitted to the arbitration, then they cannot be said to be disputes
which are either contemplated by nor fall outside the arbitration agreement.
It is further reiterated that where matters, though not in issue or connected
with matters in issue, they would not readily be held to be matters that could
be considered to be outside beyond the scope of arbitration. The said ratio
laid down by the Hon'ble Supreme Court in the above said case would
squarely apply to the facts of the present case. As already discussed and
held, the claim in monetary terms was the dispute which was referred to
arbitration and there has been admittedly transfer of properties towards
adjustment of the amounts due and payable to the respondent. There is a
https://www.mhc.tn.gov.in/judis Arb.O.P(Com.Div.) No.333 of 2024
short fall and also in view of the fact of not handing over vacant possession,
prejudice has been caused to the claimant, especially in view of the warranty
regarding the market value of the two properties which sum has been
adjusted from and out of the total amount due to the respondent. Therefore,
this is certainly within the ken of arbitration as held by the Hon'ble Supreme
Court and cannot be said to be beyond the scope of arbitration.
19.Further, the Hon'ble Supreme Court also in Ssangyong
Engineering's case, has held that if an Arbitrator is alleged to have
wandered outside the contract and dealt with matters not allotted to him,
then it would be a jurisdictional error which could be corrected on the
ground of patent illegality. However, to bring in, by back door grounds
referring to Section 28(3) of the Arbitration and Conciliation Act to be
matters beyond the scope of submission to arbitration under Section
34(2)(a)(iv) would not be permissible as Section 34(2)(a)(iv) would have to
be construed narrowly and while so construing, the Court must refer only to
matters which are beyond the arbitration agreement or beyond the reference
to the Arbitral Tribunal.
https://www.mhc.tn.gov.in/judis Arb.O.P(Com.Div.) No.333 of 2024
20.In view of the above, I do not find that the awarded claims by the
Arbitral Tribunal are beyond the scope of the reference to arbitration and
therefore, cannot be said to be hit by Section 34(2)(a)(iv) of the Arbitration
and Conciliation Act.
21.In Suryadev Alloys's case, the Division Bench of this Court, on a
judgment dated 12.04.2024, has held that interfering with the grant of
interest would amount to modification of the award, which is impermissible.
However, if the award consisting of several claims is severable from other
parts of the award, then some of the claims alone can be set aside while
sustaining the other claims awarded. This decision is relied on by the
learned counsel for the respondent in respect to the interest claim made for
restricted sum of Rs.34,74,90,090/- odd, instead of Rs.51,00,00,000/-.
22.In fact, the Hon'ble Supreme Court has confirmed the said decision
of this Court in the above said case, as well in Gujarat Urja Vikas Nigam
Limited Vs. Amit Gupta reported in 2021 7 SCC 209, where the Hon'ble
Supreme Court, construing accounts expressions 'relating to' and 'arising out
of', held that such words can have different meaning, depending on the
https://www.mhc.tn.gov.in/judis Arb.O.P(Com.Div.) No.333 of 2024
subject and context and phrases 'arising out of' and 'relating to' have been
given a expansive interpreted in several cases and therefore, it is necessary
to bear in mind the context in which the phrases have been used.
23.Keeping in mind the ratio laid down by the Hon'ble Supreme
Court as well as the Division Bench of this Court, I do not find that the
Arbitral Tribunal has exceeded its jurisdiction and has traveled beyond the
reference to award claims in favour of the respondent. The claims awarded
are certainly related to clause 10 of the Joint Compromise and cannot be
said to be extraneous and non arbitrable as contended by the learned counsel
for the petitioner.
24.Even with regard to the interest component, the petitioner has
challenged the award of interest from the date of the Theatrical Distribution
Agreement on Rs.51,00,00,000/-, when the claim itself was only in respect
of Rs.34,74,90,090/- odd. The parties were already loggerheads and with a
view to purchase peace, they had entered into a Joint Memorandum of
Compromise on 23.11.2018 which was in fact made part of a common
decretal order passed by this Court in A.Nos.8786 & 8787 of 2018. The said
https://www.mhc.tn.gov.in/judis Arb.O.P(Com.Div.) No.333 of 2024
Joint Memorandum of Compromise, more specifically at clause 10, the
petitioner and his relatives had agreed to pay interest at 12% on the balance
minimum guarantee amount of Rs.51,00,00,000/- that was outstanding then.
25.It is certainly by sheer inadvertence that the said figure of
Rs.51,00,00,000/- has been incorrectly mentioned as Rs.33,74,90,090/-.
which is only the balance amount, after adjusting the value of two
immovable properties. Though there is a typographical error in mentioning
the amount on which interest is payable, it would not take away the vested
right to claim interest on Rs.51,00,00,000/-, in terms of clause 10 of the
Joint Memorandum of Compromise and the award of such interest by the
Arbitral Tribunal is certainly a plausible view and cannot be said to be
perverse or patently illegal. Therefore, even on this ground, I am unable to
accept the argument of the learned counsel for the petitioner that the award
is unsustainable and is liable to be interfered with. Even in respect of the
factual aspects that have been argued, especially relating to the net receipts,
GST, etc., the Arbitral Tribunal has discussed the available oral and
documentary evidence and assessed the terms of the Joint Memorandum of
Compromise in a proper and plausible perspective and thereby there is
absolutely no reasons or grounds available to set aside the said award.
https://www.mhc.tn.gov.in/judis Arb.O.P(Com.Div.) No.333 of 2024
26.For all the above reasons and especially keeping in mind the ratio
laid down by the Hon'ble Supreme Court, for interfering under Section 34,
the award must strictly fall within the pigeonhole rule of the grounds
available and enumerated under Section 34, failing which the award is not
liable to be interfered with by this Court exercising power and jurisdiction
under Section 34 of the Act.
27.In fine, the Original Petition is dismissed. However, there shall be
no order as to costs. Registry is directed to number E.P.DR.No.155146 of
2023, if it is otherwise in order and list the same along with E.P.No.13 of
2024 for further hearing on 13.02.2025.
31.01.2025
ata Index : Yes / No Internet : Yes / No
https://www.mhc.tn.gov.in/judis Arb.O.P(Com.Div.) No.333 of 2024
P.B.BALAJI, J., ata
Arb.O.P(Com.Div.) No.333 of 2024
31.01.2025
https://www.mhc.tn.gov.in/judis
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!