Monday, 18, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

M/S.Chennai Metro Rail vs Transtonnelstroy Limited
2025 Latest Caselaw 2306 Mad

Citation : 2025 Latest Caselaw 2306 Mad
Judgement Date : 31 January, 2025

Madras High Court

M/S.Chennai Metro Rail vs Transtonnelstroy Limited on 31 January, 2025

                                    IN THE HIGH COURT OF JUDICATURE AT MADRAS
                                                  DATED: 31-01-2025
                                                      CORAM
                                      THE HONOURABLE MR JUSTICE P.B. BALAJI

                                                   OP Nos. 530 & 531 of 2017
                                                      & A.No.3818 of 2017

                     M/s.Chennai Metro Rail
                     Limited, Admin.Building, Chennai Metro Rail
                     Depot, Poonamalle High Road, Koyambedu,
                     Chennai-600 107.
                                                                                         Petitioner(s)
                                                               Vs
                     Transtonnelstroy Limited
                     4/1, Luganskaya Str, Moscow, 115583, Russia.
                     and another
                                                                                       Respondent(s)
                     For Petitioner(s):
                                      Arjun Suresh
                                      B.Kishore
                                      Raghavendra Ross Divakar
                                      R.Sinduja
                                      M/s.Dua Associates
                                      Palani Centre, No.32,
                                      Venkatnarayana Road, T.Nagar,
                                      Chennai-600 017.
                     For Respondent(s):
                                              Mr.D. Balaraman

                                                            ORDER
                                  Subsequent to the order being pronounced today i.e., 31.01.2025, the
                     learned counsel for the respondent would submit that the bank guarantee has
                     been furnished for 75% on the amount received and in view of the decision
                     in this original petition, it is likely that the petitioner may invoke the bank

                     1/27

https://www.mhc.tn.gov.in/judis
                     guarantee. Hence, he would seek for interim protection.


                                  2.In view of the above, the order dated 31.01.2025 is suspended for a
                     period of four weeks.


                                                                                           31-01-2025
                     ata




                                                                           OP Nos. 530 & 531 of 2017
                                                                               & A.No.3818 of 2017




                     2/27

https://www.mhc.tn.gov.in/judis
                                  IN THE HIGH COURT OF JUDICATURE AT MADRAS

                                              Reserved on       : 09.12.2024
                                              Pronounced on     : 31.01.2025

                                                       CORAM

                                      THE HONOURABLE MR.JUSTICE P.B.BALAJI

                                             O.P.Nos.530 & 531 of 2017

                     M/s.Chennai Metro Rail Limited,
                     Administration Building,
                     Chennai Metro Rail Depot,
                     Poonamalle High Road,
                     Koyambedu, Chennai – 600 107.                                ... Petitioner
                                                                                   in both OPs

                                                        vs.

                     M/s.Transtonnelstroy – Afcons JV
                     Represented by Afcons Infrastructure Limited and
                     comrpmising:

                     1.Transtonnelstroy Limited,
                     4/1 Luganskaya Str,
                     Moscow, 115583,
                     Russia.

                     2.Afcons Infrastructure Limited,
                     Afcons House,
                     16, Shah Industrial Estate,
                     Veera Desai Road, Azad Nagar (P.O),
                     Post Box No.11878, Andheri (W)
                     Mumbai – 400 053.                                   ... Respondent in both
                                                                                          OPs.




                     3/27

https://www.mhc.tn.gov.in/judis
                     PRAYER in O.P.No.530 of 2017: Arbitration Original Petition filed under
                     Sections 34 of the Arbitration and Conciliation Act, 1996, to set aside the
                     impugned award dated 03.06.2017 by the majority of the Arbitral Tribunal,
                     insofar as it allows the claim of Rs.9,35,47,080/- with interest at 12% p.a
                     from 09.04.2015, until the date of the impugned award and 14% p.a on the
                     aforesaid sum (principal + interest) from the date of the impugned award
                     until realization, by allowing this petition with costs throughout.


                     PRAYER in O.P.No.531 of 2017: Arbitration Original Petition filed under
                     Sections 34 of the Arbitration and Conciliation Act, 1996, to set aside the
                     impugned award dated 28.04.2017 by the majority of the Arbitral Tribunal,
                     insofar as it allows the claim of Rs.4,81,36,049/- with interest at 12% p.a
                     from 06.01.2015, until the date of the impugned award and 14% p.a on the
                     aforesaid sum (principal + interest) from the date of the impugned award
                     until realization, by allowing this petition with costs throughout.



                                  For Petitioner      : Mr.Yashodh Vardhan
                                                        Senior Counsel
                                                        for Mr.Arjun Suresh (O.P.No.530 of 2017)
                                                        Mr.Arjun Suresh (O.P.No.531 of 2017)

                                  For Respondents : D.Balaraman (In both OPs.)

                                                      **********




                     4/27

https://www.mhc.tn.gov.in/judis
                                                       COMMON ORDER

These Original Petitions are filed at the instance of the Chennai Metro

Rail Limited (CMRL) which has suffered an award before the learned

Arbitrator.

2.The brief facts relating to the above Original Petitions are as

hereunder:

The petitioner was formed as a Special Purpose Vehicle with an equal

50% shareholding of the Central Government and State Government of

Tamil Nadu. The petitioner invited tenders for design and construction of

underground stations in the city of Chennai together with associated tunnels

of Corridors 1 and 2 on a working basis. A Letter of Acceptance was issued

by the petitioner to the respondent on 28.12.2010, followed by a Contract

Agreement being executed on 31.01.2011, with a commencement date of

07.02.2011, for a total contract value of Rs.1566.81 and Rs.1031 crores. The

execution of the work was to be completed within 50 months, on or before

07.04.2015. It is not in dispute that the contract was completed, however not

within the time contemplated under the Contract Agreement.

3.According to the petitioner, the contract was a fixed price contract

subject to changes in costs which were permissible only when there is

https://www.mhc.tn.gov.in/judis change in legislation. The respondents made a price adjustment claim under

the Conditions of Particular Applications (CPA 32).

4.It is the specific case of the petitioner that the respondent was

already paid with price variation in respect of labour component by adopting

price variation formula under CPA 32 to the tune of Rs.166,21,76,679/- in

O.P.No.130 of 2017 and Rs.130.07 crores in O.P.No.131 of 2017. However,

the respondent, contending that the rates of minimum wages were revised

with effect from 16.07.2014 vide G.O.(2D).No.27, Labour & Employment

dated 18.06.2014, claimed additional costs. Initially, the respondents had

made a claim, however the details of which are as follows:

Amended statement of claims In O.P.530 of 2017 In O.P.No.531 of 2017 Local Daily Rs.7,78,20,224/- Local Daily Rs.3,97,61,939/- Local Monthly Rs.1,73,20,056/- Local Monthly Rs.95,64,123/- Labour Supply Rs.4,76,75,753/- Labour Supply Rs.2,15,31,633/-

Total Rs.14,28,16,033/- Total 7,08,57,695/-

The respondents made their respective claims citing changes in law,

relating to revision of minimum wages payable.

5.The defence raised by the petitioner was that the claims itself were

not maintainable as it stood waived by the respondent under clause 20.1 of

https://www.mhc.tn.gov.in/judis the General Conditions of Contract (GCC). That apart, according to the

petitioner, the claims were not substantiated and on a proper reading of

clauses 13.16.1 to 13.16.5 as amended by CPA 37, the respondent cannot

claim additional costs, citing change in law, when the respondent has

already benefited from price adjustment under CPA 32. However, the

Arbitral Tribunal, in and by an award dated 03.06.2017, by a majority of 2:1

partly allowed the claims of the respondents. The said awards in favour of

the respondent are under challenge in the above Original Petitions.

6.I have heard Mr.Yashodh Vardhan, learned Senior Counsel, for

Mr.Arjun Suresh, learned counsel for the petitioner in O.P.No.530 of 2017,

Mr.Arjun Suresh, learned counsel for the petitioner in O.P.531 of 2017 and

Mr.D.Balaraman, learned counsel for the respondents in both the original

petitions. I have also gone through the documents filed by way of typed set

of papers and also the impugned award, besides considering the submissions

advanced by the learned counsel on either side, including the decisions on

which reliance has been placed upon by the learned counsel on both sides.

7.The learned Senior Counsel, Mr.Yashoth Vardhan and Mr.Arjun

Suresh, appearing for the petitioners in the above Original Petitions would

mainly attack the award on the ground of patent illegality under Section

https://www.mhc.tn.gov.in/judis 34(2)(b)(ii) of the Arbitration and Conciliation Act, 1996 and being contrary

to the public policy of India under Section 34(2)(b)(ii), besides also being

contrary to Section 28(3) of the Arbitration and Conciliation Act, 1996.

According to the learned counsel for the petitioners, they would primarily

contend that the interpretation of the vital and relevant clauses 13.16.1 and

13.16.5 by the Arbitral Tribunal is neither a possible nor a plausible view

and on the other hand, the interpretation given by the Tribunal is patently

illegal and contrary to public policy.

8.Further, according to the learned counsel for the petitioners, the

award has virtually rewritten the change in law, clause CPA 37 in the

contract and has imposed revised commercial terms on the petitioners by

awarding additional costs in view of the revision in minimum wages which

has according to the petitioners resulted in unlawful and unjust enrichment

to the respondent. The learned counsel for the petitioners would state that the

Tribunal has ignored essential terms of contract and when the respondent

had not even pleaded, leave alone prove that its performance was impacted

because of the change in law, the Tribunal ought not to have awarded the

claim citing change in law. Therefore, the award is patently illegal according

to the petitioners. The learned counsel would also submit that the Tribunal

https://www.mhc.tn.gov.in/judis has not given any reasons for holding that the claims were maintainable in

the light of clause 20.1 of the GCC and on this ground also the award has to

be set aside, being patently illegal.

9.The learned counsel for the petitioners relied on the following

decisions in support of their contentions:

1.National Highways Authority of India Vs. M/s.ITD Cementation India Limited ((2015) 14 SCC 21).

2.Union of India and Others Vs. Bharat Enterpricse (2023 SCC Online SC 369).

3.Trivenibai & Another Vs. Smt.Lilabai (AIR 1959 SC 6200.

4.Commissioner of Central Excise, Bhavnagar Vs. Saurashtra Chemicals Limited ((2007) 10 SCC 352).

5.Ssangyong Engineering and Construction Company Limited Vs. National Highways Authority of India ((2019) 15 SCC 131).

6.Delhi Metro Rail Corporation Limited Vs. Delhi Airport Metro Express Private Limited ((2024) 6 SCC 357).

10.Per contra, the learned counsel for the respondent,

Mr.D.Balaraman, would support the findings of the Arbitral Tribunal and

contend that in view of the mandate of Section 5 of the Arbitration and

Conciliation Act, the award cannot be interfered with unless as provided in

Section 34 of the Act. According to the learned counsel for the respondents,

the petitioners had not mentioned specifically under which subsection of

https://www.mhc.tn.gov.in/judis Section 34, the challenge to the award is being laid. In this regard, the

learned counsel for the respondent relied on the following decisions:

1.Associate Builders Vs. Delhi Development Authority ((2015) 3 SCC 49).

2.Parsa Kente Collieries Limited Vs. Rajasthan Rajya Vidyut Utpadan Nigam Limited ((2019) 7 SCC 236).

3.S.V.Samudram Vs. State of Karnataka ((2024 3 SCC 623).

4.National Highways Authority of India Vs. Hindustan Construction Company ((2024) 6 SCC 809).

11.Relying on the above decisions, the learned counsel for the

respondents would state that if the Arbitral Tribunal has taken a particular

view on the interpretation of a contract, the Court cannot sit over the same in

appeal and over turn the findings of the Arbitrator as long as the construction

of the contract by the Arbitrator is not something that no fair minded or

reasonable person could do. He would further state that the respondent was

clearly entitled to additional costs due to change in law pertaining to the

works as provided in clause 13.16.2. According to the respondent, proper

interpretation of clauses 13.16.2 to 13.16.5 was that clause 13.16.5 allows

additional costs only to the extent not covered by price variation formula and

therefore, the respondent was entitled to claim additional costs in view of the

change in law and therefore, such a view being rightly adopted by the

Tribunal, no interference is warranted with the award.

https://www.mhc.tn.gov.in/judis

12.I have carefully considered the submissions advanced by the

learned counsel on either side.

13.The short question which arises in these Original Petitions is as to

whether the change in law would enable the respondents to compensation

under clause 13.16.5 adopting CPA 32 or change in law would entitle the

respondents to compensation under clause 13.16.2 to 13.16.4 when CPA is

not adopted. In fact, the learned counsel for the respondent would also raise

an objection that this contention that has been argued before me was neither

raised before the Arbitral Tribunal nor in the memorandum of grounds of

challenge to the award under Section 34 before this Court, but raised for the

first time in the oral arguments. The primordial defence of the petitioners

before the Tribunal was that when the respondents were already

compensated for price variation adopting CPA 32, whether the petitioner

was entitled to claim further additional costs owing to change in law in view

of proper interpretation of CPA 37 (clause 13.16.1 to 13.16.5).

14.With regard to the lack of challenge, as contended by the learned

counsel for the respondents, I have gone through the memorandum of

grounds in both the original petitions. The substantial challenge to the award

https://www.mhc.tn.gov.in/judis is only citing contravention of CPA 37 prohibiting the respondents from

making any claim towards additional costs, once price variation formula in

CPA 32 is already been adopted. Therefore, it may not be correct on the part

of the learned counsel for the respondents to contend that such grounds were

not taken in the original petitions. Relevant clauses in the GCC are

reproduced hereunder:

GCC – FIDIC Conditions GCC 13.1 (b) GCC 13.16 The Contract Price 13.1 The Contract Price shall be adjusted to take account of any increase or decrease in Cost resulting from changes in Unless otherwise stated in Part II legislation of the Country, made after the Base Date. Such legislation means any law, order, regulation or by- law having the force of law, including

(b) the Contract Price shall not be currency restrictions, which affects the adjusted for changes in cost of labour, Contractor in the performance of his obligations.

materials or other matters

If the Contractor suffers (or will suffer) delay and/or incurs (or will incur) additional Cost resulting from such changes in legislation made after Base Date, the Contractor shall give notice to the Employer’s Representative. After receipt of such notice the Employer's Representative shall proceed in accordance with Sub-Clause 3.5 to agree or determine:

(a) any extension of time to which the Contractor is entitled under Sub-Clause 8.3, and

(b) the amount of such Cost, which shall be added to the Contract Price, and shall notify the Contractor, accordingly.

https://www.mhc.tn.gov.in/judis The modified clauses under CPA are as hereunder:

Modified clauses under CPA CPA 32 (Replaces Sub-clause 13.1 (b) CPA 37 (Replaces Sub-clause 13.16 of of GCC) GCC) 13.1 (b) I) Price Variation Formula 13.16.1 The contract shall be governed by the laws for the time being in force in

(a)Prices payable to the Contractor, in India accordance with the Contract shall be subject to adjustment during 13.16.2 “Changes in law” means the performance of Contract to reflect occurrence or coming into force of any changes in cost of labour and material of the following, at any time after the components and other inputs to the base date.

Works, in accordance with the following 1. Any new tax which is imposed general formula for each currency after the due date of submission specified: of tender and which impacts the performance of the contractor with increased cost or which [Pn = a +b(Ln/Lo) + c(Sn/So) + results in extra financial gains to d(Cn/Co) ± e(Fn/Fo)] the contractor due to decreased cost in execution of works; and “Pn” is the adjustment factor to be 2. Change in any law pertaining to applied to the estimated value of work work having the above said done in a month, determined by the ER. impact

“b”, “c”, “d”, ‘e” are coefficients Then such additional or reduced cost representing the estimated proportion of shall be certified by the employers each cost element (labour, steel, cement representative after examining records and fuel) in the Works or section thereof, provided by the contractor and shall be as specified in Appendix FT-1 of the paid by or credited to the employer, Form of Tender in the Instructions to subject to sub-clause 13.16.5 below Tenderers (“ITT”) 13.16.3 Any change in the rate of any existing tax will be considered a change “Ln”, “Sn”, “Cn” and “Fn”are the in law , if so related to work. current cost indices or reference prices for month “n’ determined to Item 38 of Appendix FT-1 of the Form of Tender in 13.16.4 Notwithstanding the forgoing, the ITT,applicable to each cost element. such additional or reduced cost shall

https://www.mhc.tn.gov.in/judis Modified clauses under CPA not be separately paid or credited, the same shall have been taken into “Lo”, “So”, “Co” and “Fo” are the account under any other clause under current cost indices or reference prices the contract. for month “n” determined to Item 38 of Appendix FT-1 of the Form of Tender in the ITT, applicable to each cost element. 13.16.5 If the price variation formula in CPA 32 is adopted by the contractor, then no addition or reduction in cost due to changes in law will be allowed except for changes to i) Customs Duties and ii) Excise Duties , iii) Output TN VAT which shall be to the employers account , to the extent that it is not covered by the price variation formula.

15.It is not in dispute that CPA 32 was invoked and price adjustment

claim was made by the respondents in both the cases. In terms of the

amended CPA 37, if CPA 32 is adopted and price variation is claimed by the

contractor, then no addition or reduction in costs due to changes in law will

be allowed, except in three scenarios, namely i) changes in custom duties ii)

changes in excise duties and iii) changes in output TN VAT. As seen from

clause 13.1(b) of GCC, the contract price was not subject to adjustment in

view of the changes in cost of labour, materials or other matters. However,

under CPA 32, the parties agreed for providing price escalation on a

particular formula being adopted.

https://www.mhc.tn.gov.in/judis

16.It is again not disputed that the respondents claimed substantial

monies towards price escalation and the same was also paid by the

petitioners. As rightly pointed out by the learned counsel for the petitioners,

but for CPA 32, if parties were governed only by the original terms of GCC,

then the respondent would not have become entitled to the price escalation

amounts also.

17.The moot question that is required to be dealt with and answered in

these original petitions is as to whether the change in law would entitle the

respondents to compensation under clause 13.16.5 (CPA 37), when CPA 32

had already been adopted. A plain reading of clause 13.16.5 shows that if the

price variation formula in CPA 32 is adopted, then the respondent or the

petitioner for that matter would not be entitled to any addition or reduction

in the costs on account of changes in law/legislation. However, three

exceptions have been carved out, namely customs duty, excise duty and

output TN VAT which shall be to the account of the petitioner in these

original petitions subject to not being covered by the price variation formula.

18.It is the case of the petitioners that CPA 37, post agreement

https://www.mhc.tn.gov.in/judis replacing sub clause 13.16 of the GCC does not provide for additional costs

for change in law and it is subject to application of two scenarios, namely if

CPA 32 is applied, payment for change in law would be available only in

respect of three events, namely change in customs duties, excise duties and

output TN VAT. Secondly, when there is an unrestricted change in law

which is subject to application of the first scenario, if applied, then second

scenario would not be available. The Arbitral Tribunal has found that the

modification of clause 13.16 of GCC vide CPA 37 was only to avoid

duplication in payment. The Tribunal has failed to see that both CPA 32 and

CPA 37 apply in different contexts, namely price escalation and change in

law. Clause 13.16.4 takes care of double payment by clearly stating that

additional or reduced costs shall not be separately paid if the same has

already been taken into account under any other clauses under the contract.

19.A proper reading of CPA 37 would indicate that the respondent

would be entitled to additional costs for change in law either under

subsection 13.16.5 when CPA 32 has been adopted or under subsection

13.16.2 to 13.16.4 when CPA 32 is not adopted. In fact, clause 13.16.2

referring to changes in law sets out various scenarios, viz., coming into force

of any new tax imposed on the due date, impacting the performance of the

https://www.mhc.tn.gov.in/judis contractor and increasing the costs, resulting in extra financial gains to the

contractor due to decreased costs, then such additional or reduced costs shall

have to be certified by the petitioner's representative and shall be paid or

credited, subject to clause 13.16.5. Clause 13.16.1 to 13.16.5 have to be read

not only harmoniously but together.

20.Clause 13.16.2 is clearly subject to 13.16.5. Therefore, when price

variation formula in CPA 32 is adopted, then the respondents cannot be

entitled to claim any additional costs, unless there is a claim falling under

the three exceptions, namely customs duty, excise duty and output TN VAT

which also is again subject to the rider that it will be paid to the extent that it

is not covered by the price variation formula. Therefore, the employment of

the words in 13.16.5 that 'to the extent that it is not covered by the price

variation formula' only reinforces that there would be no duplication in

payment. The Tribunal has misread the clauses and erroneously proceeded to

hold that clause 13.16 of GCC entitles the respondent for price adjustment

because of change in legislation after the base date. However, the express

modifications made by CPA 37, replacing sub clause 13.16 of GCC have not

been factored or looked into by the Tribunal.

https://www.mhc.tn.gov.in/judis

21.The omnibus entitlement for price adjustment under clause 13.16

was watered down in CPA 37 to a great extent, entitling the respondents to

seek additional costs on account of change in law, only if the respondent has

not adopted the price variation formula in CPA 32, unless under three

exceptions carved out, namely customs duty, excise duty and output

TNVAT. Therefore, the only possible interpretation that can be given to

13.16.5 is that if the contractor has already claimed the price variation

invoking CPA 32 which provides for a formula, then the contractor cannot

claim any additional costs citing change in law, except where the change in

law is pertaining to customs duties, excise duties and TNVAT. However,

this only possible and right interpretation of the clauses has not been adopted

by the Tribunal and the Tribunal erroneously held that irrespective of being

compensated under CPA 32, the respondents would still be entitled to claim

additional costs due to change in law which is clearly patently illegal and the

Tribunal erroneously held that there is a mandatory requirement for the price

adjustment on account of change in law which is contrary to the terms and

conditions, especially after the modifications ushered in by CPA 37. The

interpretation of clause 13.16.5 by the Tribunal is not in consonance with

Section 28(3) of the Arbitration and Conciliation Act and if the

interpretation given by the Tribunal is accepted, then it would in fact amount

https://www.mhc.tn.gov.in/judis to rewriting the contract, especially clause 13.16.5.

22.Apparently, the Tribunal has not harmoniously read clauses

13.16.2 to 13.16.5 of CPA 37 which replaced 13.16 of the GCC. Therefore,

the Tribunal, in my considered opinion, has ignored the vital material terms

of contract and has violated the mandate of Section 28(3) of the Arbitration

and Conciliation Act.

23.Yet another reason for the Tribunal to have taken such a view was

clause 13.16.2.2, which according to the Tribunal, if the petitioner's

argument was accepted then there would be no meaning to 13.16.2.2. Clause

13.16.2.2 provides for change in law pertaining to work having the above

said impact i.e., there must be a change in law which has impacted the

performance of the contractor because of increased costs which again has

been clearly subjected to sub clause 13.16.5. Therefore, the interpretation

arrived at by the Tribunal ignoring the specific clauses and the words

employed thereunder has certainly resulted in the patently illegal award,

ignoring the very contractual terms between the parties.

24.Even insofar as the Tribunal's reliance on clause 70.8 of the

judgment of the Hon'ble Supreme Court in National Highways Authority of

https://www.mhc.tn.gov.in/judis India Vs. ITD Cementation India Limited reported in (2015) 14 SCC 21, as

rightly pointed out by the learned counsel for the petitioners, clause 70.8 in

the contract which is subject matter of the said judgment is not pari materia

with sub clause 13.16.5 of CPA 37 and therefore, basing the award on the

decision of the Hon'ble Supreme Court with this specific reference to clause

70.8 of the said judgment was clearly erroneous.

25.Yet another argument of the learned counsel for the petitioners

which finds force is that the respondents have not even pleaded, leave alone

proved that the change in law had impacted the performance. The claim

statement filed by the respondents does not plead anything with regard to the

revision in the minimum wages impacting the performance of the

respondents. The petitioner in his statement of defence has specifically

pleaded that the revision in minimum wages had no impact on the contract.

Though while amending the claim statement on 08.10.2016, the respondents

have averred that the amendment to minimum wages had an impact, it is not

substantiated or proved by leading any evidence during the arbitral

proceedings. The Tribunal has also not considered this aspect and rendered

any finding that the increase in minimum wages had impacted the

performance of the contract at the hands of the respondent. As rightly

https://www.mhc.tn.gov.in/judis pointed by the learned counsel for the petitioners, clause 13.16.2 as modified

by CPA 37 entitles the contractor to additional costs owing to change in law

only when such new tax imposed after the base date impacts the

performance of the contractor with increased costs. Therefore, even

assuming that the respondents were entitled to interpretation of the contract

as understood by the Tribunal, even then without pleading and proving any

impact and the consequences of such new tax on the contract, the respondent

cannot succeed in its claim for additional costs.

26.I have already discussed the ratio laid down by the Hon'ble

Supreme Court in National Highways Authority of India's case, and no

doubt in the decisions relied on by the learned counsel for the respondent,

the principles laid down are that the construction of terms of the contract are

primarily for the Tribunal to decide and the Court while considering

challenge to the award cannot sit in appeal over the findings. However, in all

the decisions which have been relied on even by the learned counsel for the

respondents, the Courts have always carved out an exception that if the

Tribunal construes the contract in a manner that no fair minded or

reasonable person would do, then the award is subject to inference under

Section 34 of the Arbitration and Conciliation Act.

https://www.mhc.tn.gov.in/judis

27.Yet another argument placed by the learned counsel for the

petitioners is with reference to clause 20.1 of GCC which is extracted

hereunder for easy reference.

“Procedure for 20.1 Claims 20.1 If the Contractor intends to claim any additional payment under any Clause of these Conditions or otherwise, the Contractor shall give notice to the Employer's Representative a soon as possible and in any event within 28 days of the start of the event giving rise to the claim.

The Contractor shall keep such contemporary records as may be necessary to substantiate any claim, either on the Site or at another location acceptable to the Employer's Representative. Without admitting the Employer's liability the Employer's Representative shall, on receipt of such notice, inspect such records and may instruct the Contractor to keep further contemporary records. The Contrary shall permit the Employer's Representative to inspect all such records, and shall (if instructed) submit copies to the Employer's Representative.

Within 28 day of such notice, or such other time as may be agreed by the Employer's Representative, the Contractor shall send to the Employer's Representative an account, giving detailed particulars of the amount and basis of the claim. Where the even giving rise to the claim has a continuing effect, such account shall be considered as interim. The Contractor shall then, at such intervals as the Employer's Representative may reasonably require, send further interim accounts giving the accumulated amount of the claim and any further particulars. Where interim accounts are sent to the Employer's Representative, the Contractor shall send a final account

https://www.mhc.tn.gov.in/judis within 28 days of the end of the effects resulting from the event.”

28.Though the learned counsel for the respondents also relied on the

decisions of the Hon'ble Supreme Court to fortify his contention that points

which are not pressed at the time of arguments would have to be presumed

to have been given up, having gone through the entire award, I am unable to

countenance the said submission of the learned counsel for the respondents.

It has been the consistent contention and argument of the respondent that in

view of revised / amended 13.16 by CPA 37, the respondents cannot be

entitled to any additional costs when price variation formula was already

invoked under CPA 32. Therefore, I am unable to accept the argument of the

learned counsel for the respondents that such argument has been taken

before this Court for the first time and was not raised before the Arbitral

Tribunal. I have already found that sufficient grounds have been raised in the

memorandum of grounds for challenge in the Section 34 petition as well.

29.According to the petitioners, if the contractor i.e., the respondent

intended to make any additional claim under any clause of GCC or

otherwise, then the respondent was obligated to give a notice to the

petitioners' representative within 28 days of the start of the event giving rise

to the claim. It is also made clear that if the contractor fails to comply with

https://www.mhc.tn.gov.in/judis the sub clause, then he shall not be entitled to additional payment. It is the

specific contention of the petitioners that the Arbitral Tribunal has not

adverted its attention to this issue. The amendment to minimum wages was

introduced on 18.06.2015 with effect from 16.07.2014. Applying clause 20.1

of the GCC, the respondents ought to have made their claims within 28 days.

Admittedly, the same was not done and thereby the last portion of clause

20.1 would kick in, disentitling the respondents from any additional

payment.

30.In this regard, reliance has also been placed on the decision of the

Hon'ble Supreme Court in Union of India and Others Vs. Bharat Enterprise

reported 2023 SCC Online SC 369, where the Hon'ble Supreme Court has

held that if there is a waiver clause in the contract, then it would be binding

on the parties and the Tribunal cannot ignore the same. The ratio laid down

by the Hon'ble Supreme Court would squarely apply to the facts of the

present case. Even assuming the respondents were entitled to make a claim

for additional costs owing to revision of the minimum wages by the

legislature, then as required under clause 20.1 of GCC, the respondents

ought to have notified the petitioner within 28 days, at least from

16.07.2014. However, the Tribunal contrary to the above clause, has

https://www.mhc.tn.gov.in/judis observed in the award that the respondents had rightly notified the claim

vide letter dated 19.09.2014, which admittedly is clearly beyond 28 days

even from 16.07.2014. Therefore, even on this score the respondents could

not have become entitled to any additional costs.

31.In view of the above and applying the ratio laid down by the

Hon'ble Supreme Court in Delhi Metro Rail Corporation Limited Vs. Delhi

Airport Metro Express Private Limited's case, when the interpretation of

contract by the Tribunal has been unreasonable and not even a possible view

is taken, then the award has to be held to be perverse. Further, the

interpretation as provided by the Tribunal is not only unreasonable but also

would frustrate the very clause 13.16.5 and therefore, the interpretation

which is neither possible nor plausible cannot be sustained by this Court.

32.Even in Ssangyong Engineering and Construction Company

Limited's case, the Hon'ble Supreme Court held that the true import of

Section 28(3) of the Arbitration and Conciliation Act is that when the

Arbitrator's view is not even a possible view to take and and the Arbitrator

wanders outside the contract and deals with matters not allotted to him, the

Arbitrator commits an error of jurisdiction which is a ground for challenge

under Section 34(2)-A. I have already found that the interpretation of

https://www.mhc.tn.gov.in/judis 13.16.2 to 13.16.5 is not even a possible view, especially when such view

would virtually amount to rewriting the contract terms itself.

33.Therefore, for all the above grounds, I find that the petitioners have

indeed made out a case for interference with the award of the Arbitral

Tribunal.

34.In fine, these Original Petitions are allowed and the award of the

Arbitral Tribunal dated 03.06.2017 challenged in O.P.No.530 of 2017 and

the award dated 28.04.2017 challenged in O.P.No.531 of 2017 are hereby set

aside. However, there shall be no order as to costs.

31.01.2025

ata Index : Yes / No Internet : Yes / No

P.B.BALAJI, J., ata

https://www.mhc.tn.gov.in/judis O.P.Nos.530 & 531 of 2017

31.01.2025

https://www.mhc.tn.gov.in/judis

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 

LatestLaws Partner Event : IJJ

 
 
Latestlaws Newsletter