Sunday, 17, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

P.Anandasundaresan vs M/S.Akshaya Pvt. Ltd
2025 Latest Caselaw 1702 Mad

Citation : 2025 Latest Caselaw 1702 Mad
Judgement Date : 10 January, 2025

Madras High Court

P.Anandasundaresan vs M/S.Akshaya Pvt. Ltd on 10 January, 2025

Author: J.Nisha Banu
Bench: J.Nisha Banu
                                                                              C.M.S.A.No.41 of 2022


                                  IN THE HIGH COURT OF JUDICATURE AT MADRAS

                                        RESERVED ON       :    09.12.2024
                                        PRONOUNCED ON :        10.01.2025


                                                      CORAM:
                                    THE HON'BLE MRS. JUSTICE J.NISHA BANU
                                                       AND
                                     THE HON'BLE MR. JUSTICE R.SAKTHIVEL

                                              C.M.S.A.No.41 of 2022

                                            and C.M.P.Nos.9256 of 2022


                   P.Anandasundaresan                                         ... Appellant

                                                       -vs-


                   M/s.Akshaya Pvt. Ltd.
                   Rep. by its Director, Mr.J.Ravi,
                   No.117/1, LB Road, 7th Floor,
                   Adyar, Chennai 600 020                                     ... Respondent

                   PRAYER: Civil Miscellaneous Second Appeal filed under Section 58 of the
                   TNRERA Act, 2017 r/w section 100 of Civil Procedure Code, 1908, against
                   the order of the Tamil Nadu Real Estate Appellate Tribunal, Chennai dated
                   07.03.2022 passed in Appeal No.103 of 2021 on the file of TNREAT, by


                   ______________
                   Page No.1 of 24


https://www.mhc.tn.gov.in/judis
                                                                                      C.M.S.A.No.41 of 2022


                   reversing the order dated 30.03.2020 passed in CCP No.30 of 2020 on the
                   file of TNRERA, Chennai.
                                         For Appellant     : Mr.C.K.Chandrasekar
                                                             For Mrs.W.R.Subhashini

                                           For Respondent : Mr.Mani Sundaragopal

                                                          ******
                                                     JUDGMENT

(Judgment of this Court made by J.Nisha Banu, J.)

The appellant has approached this Court under Section 58 of the Real

Estate (Regulation and Development) Act, read with Section 100 of the Civil

Procedure Code against the order of the Tamil Nadu Real Estate Appellate

Tribunal, Chennai dated 07.03.2022 passed in Appeal No.103 of 2021 on the

file of TNREAT, which reversed the order dated 30.03.2020 passed in CCP

No.30 of 2020 on the file of Tamil Nadu Real Estate Regulatory Authority

(TN RERA), Chennai filed by the appellant herein.

2. The essential facts of the case would run thus:-

2.1. The appellant herein is a retired General Manager of Bharath

Petroleum Corporation Limited, a Public Sector Undertaking. The

respondent /Promoter has advertised for constructing a residential apartment

______________

https://www.mhc.tn.gov.in/judis

complex at Thaiyur Village, Chengalpet Taluk in Thiruporur bearing the

project name “January”. The said project comprised of construction of

residential flats measuring 1396 sq.ft. in an undivided share of land, in a total

land measuring about 5 Acres and 23.79 cents. The appellant being

interested in the same, approached the respondent/ Promoter and on

30.07.2011, the appellant entered into a Memorandum of Agreement with the

respondent/ Promoter. The total cost payable by the appellant was fixed at

Rs.46,38,000/- (Rupees Forty-Six Lakhs Thirty-Eight Thousand Only) by the

respondent/ Promoter for the alloted plot.

2.2. The schedule of payments, the specification of the flat and the

amenities were provided under the Project name "January" as mentioned in

the above said Memorandum of Agreement. As per the said Agreement, the

flat was to be constructed within a period of 30 months, with a grace period

of 90 days from the date of obtaining the sanction from the Authorities

concerned. The respondent/ Promoter also agreed to provide ten other

amenities which includes Club House, ATM, Restaurant, Supermarket,

Gymnasium ...etc. apart from other common facilities.

______________

https://www.mhc.tn.gov.in/judis

2.3. As per the aforesaid Agreement dated 30.07.2011, the respondent

/Promoter has to complete the construction and deliver the flat at least, on or

before 30th April 2014. But the respondent / Promoter handed over the keys

of the flat only on 24.02.2018 and the club house facilities were handed over

only on 26.01.2021. Therefore, the respondent/ Promoter has handed over the

possession of the flat with a long delay of nearly 4 years from 30.04.2014 to

24.02.2018 and with regard to the other club house facilities, a delay of 7

years has been incurred on the side of the respondent/ Promoter.

2.4. Aggrieved against the delay incurred in handing over of the flat by

the respondent/ Promoter, the appellant filed a complaint before TNRERA,

seeking a direction to the respondent/ Promoter to pay a compensation of

Rs.7,56,358/- (Rupees Seven Lakh Fifty-Six Thousand Three Hundred and

Fifty-Eight Only), with interest at 18% per annum. By an order, dated

30.03.2021, the learned Adjudicating Officer, TNRERA, Chennai, directed

the respondent / Promoter to pay a sum of Rs.5,56,358/- as compensation for

delay and interest on the said amount at 10.05% per annum from the date of

filing of the complaint until the date of payment, and a further sum of

______________

https://www.mhc.tn.gov.in/judis

Rs.1,00,000/- towards compensation of mental agony, loss and hardship and

additionally a sum of Rs.20,000/- towards litigation expenses.

2.5. Challenging the aforesaid order of the learned Adjudicating

Officer, TNRERA, Chennai, the respondent/ Promoter has filed an appeal

before the Tamil Nadu Real Estate Appellate Tribunal. The Appellate

Tribunal reversed the order of the learned Adjudicating Officer, TNRERA,

Chennai, vide order, dated 07.03.2022 made in Appeal No.103 of 2021, on

the file of TNREAT, Chennai, thereby allowing the appeal filed by the

respondent/ Promoter by holding that the project “January” of the

respondent/ Promoter was 'not an ongoing project' and therefore, the same

does not attract the provisions of the TN RERA Act and also inferred that the

complaint made by the appellant is not maintainable. Since the Appellate

Tribunal reversed the order of the learned Adjudicating Officer, TNRERA,

Chennai, aggrieved against the same, the appellant has approached this Court

by way of filing this civil miscellaneous second appeal.

3. Mr.C.K.Chandrasekar, learned counsel appearing on behalf of

Mrs.W.R.Subhashini, learned counsel for the appellant, canvassed the

______________

https://www.mhc.tn.gov.in/judis

following arguments before this Court.

3.1. According to the learned counsel for the appellant, there was a

delay in construction. Despite the delay that incurred on the side of the

respondent/ Promoter, demand was made by the respondent/Promoter

through email, to the appellant insisting on making payment of installments.

Even then, the appellant has paid those installments promptly. Apart from the

above said amount of Rs.46,38,000/-, the respondent/ Promoter has collected

amount towards Service Tax, VAT, interest for delayed payment,

infrastructure and basic amenities charges, amounting a total sum of

Rs.3,93,368/- . Therefore, a total sum of Rs.50,31,368/- (Rupees Fifty Lakhs

Thirty One Thousand Three hundred and Sixty Eight only) was paid by the

appellant to the respondent / Promoter for the purchase of the flat.

3.2. Further, the learned counsel submitted that the appellant has

purchased the apartment with a Housing Loan of Rs.35,00,000/- availed from

M/s.Corporation Bank and the payments were released to the respondent/

Promoter directly by the Bank starting from December 2011 to November

2013. The minor delays in release of payments to the respondent/Promoter

______________

https://www.mhc.tn.gov.in/judis

was due to the delay in submission of information sought by the Bank from

the respondent/ Promoter. Nevertheless, the appellant paid the interest

element on receipt of Demand Notice from the respondent/ Promoter. An

amount of Rs.16,58,091/- was paid to the bank as an interest, till taking

possession of the apartment on 24-02-2018.

3.3. According to the learned counsel for the appellant, the respondent/

Promoter has admitted before the Adjudicating Officer that the project was

"an ongoing project" on the date of the commencement of the Act. But the

learned Appellate Tribunal has failed to consider the definition of

'completion certificate' as per Section 2 (q) of the RERA Act, 2016. It is the

contention of the learned counsel that the conclusion reached by the

Appellate Tribunal is contrary to records and it ought to have discredited the

document submitted by the respondent/ Promoter, which is not a completion

certificate.

3.4. The learned counsel for the appellant drew the attention of this

Court to Clause 8 of Memorandum of Agreement dated 30.07.2011, wherein

the respondent/ Promoter has undertaken to pay a sum of Rs.7,500/- per

______________

https://www.mhc.tn.gov.in/judis

month as compensation for the delay of delivery of possession. The

respondent has revised the said amount of compensation, increasing the same

from Rs.7,500/- to Rs.10,000/- per month with effect from May 2016 vide

e-mail dated 26.10.2015, in respect of 'Wednesday Block', by their revised

timeline. But the respondent/ Promoter has not paid any amount, towards the

said compensation for delayed delivery, when they handed over the

possession on 24.02.2018 and for the other amenities in the year 2021.

3.5. It is the contention of the learned counsel for the appellant that the

Appellate Tribunal erred in considering the letter issued by the President of

the Panchayat as that of "Completion Certificate" and the same is contrary to

law. The said letter cannot be equated with the Completion Certificate issued

by the competent authority and admittedly, the project was incomplete on the

date of issuance of such letter. Moreover, the Appellate Tribunal failed to

see that the respondent/ Promoter did not submit any application to the

CMDA enclosing any certificate from the Architect / Licenses Surveyor/

Structural Engineer as mandated in Rule 2 (h)(ii) of the TN RERA Act, Rules

2017.

______________

https://www.mhc.tn.gov.in/judis

3.6. The learned counsel vehemently argued that an application

seeking completion certificate could be submitted only to the CMDA, as they

are the Competent Authority to issue the certificate after verification about

the compliance of the approved plan and completion of the project as per the

plan. But in the present case, no such completion certificate obtained from

the CMDA was furnished by the respondent/ Promoter. Moreover, at the time

when the Panchayat President issued a letter on 26.02.2014, the project was

still under construction, which aspect was not looked into by the Appellate

Tribunal.

3.7. The learned counsel for the appellant further submitted that the

Tribunal failed to see the interest statement of the builder, dated 17.2.2020

which proved that the construction itself was undertaken after 14.2.2017,

where the project got extended due to the delay/fault of the Builder and

respondent also collected interest at 18% for the belated payment by the

buyer, for the lapse on their part in not constructing and handing over the

Flat/Project within the agreed period i.e 30.04.2014.

______________

https://www.mhc.tn.gov.in/judis

3.8. Even though there was abundant material to prove that the

construction was incomplete, handing over the flats to the owner was

incomplete till 2018 and the common amenities were not even constructed as

per the project plan till 2021 and maintenance was also not complete until

2017, the learned Tribunal failed to consider the same and passed an

erroneous order, which deserves to be set aside.

3.9. The learned counsel for the appellant relied on the judgment of

this Court made in C.M.S.A.No.27 of 2020 dated 16.02.2021, wherein the

term 'completion certificate' was extensively discussed and in that case, it

was held as follows:-

“.... completion must be with reference to the provisions of the Act and not based on the certificate of completion issued by the Executive Officer, Town Panchayat, who issues such certificates mostly on extraneous considerations. Thus, this Court is of the considered opinion that the certificates are not issued after inspection but obtained ....

.... Thus, any certificate issued by such Executive Officer, Town Panchayat cannot be taken as a conclusive factor, If

______________

https://www.mhc.tn.gov.in/judis

a literal meaning is adopted, with reference to Section 3(2)(b) of the RERA Act, then many number of builders/ Developers who are all in the process of construction will escape from the clutches of law and that is not the intention of the Parliament.”

Therefore, considering the above, the learned counsel for the appellant

submitted that the order of the Tamil Nadu Real Estate Appellate Tribunal,

Chennai dated 07.03.2022 passed in Appeal No.103 of 2021 on the file of

TNREAT is liable to be dismissed and prayed for allowing the appeal.

4. Mr.Mani Sundaragopal, learned counsel appearing for the

respondent / promoter would submit that the Completion Certificate for the

above said Project was issued by the Thaiyur Panchayat on 26.02.2014 and

he relied on section 2(q) of the RERA Act which defines Completion

Certificate as follows:-

“means the completion certificate, or such other certificate, by whatever name called, issued by the competent authority certifying that the real estate

______________

https://www.mhc.tn.gov.in/judis

project has been developed according to the sanctioned plan, layout plan and specifications, as approved by the competent authority under the local laws ”.

4.2. The learned counsel further relied on Section 3 of the RERA Act

which stipulates that projects for which Completion Certificate has not been

issued on the date of commencement of this Act ie., on 01.05.2017 (Section

3 to 9 etc., were notified only on 01.05.2017), alone are liable to be

registered under the Act. In view of the same, the provisions of the Act are

not applicable in respect of the said Project, "January" and hence the

complaint for Compensation u/s 18, 70 and 71 of the Act, made by the

appellant is not maintainable.

4.3. The learned counsel further submitted that the appellant

committed several defaults by making delayed stage-wise payments. As per

Clause 8 of the Memorandum of Agreement, dated 30.07.2011 entered

between the parties, the appellant becomes eligible for rental compensation

only in the event of making timely stage-wise payments without any delay.

______________

https://www.mhc.tn.gov.in/judis

Therefore, it is the contention of the learned counsel that the appellant is

fully aware that he is not entitled for rental compensation for the alleged

delay in delivery of possession and that is the reason why the appellant has

taken delivery of possession on 24.02.2018 without insisting on rental

compensation.

4.4. Further, the learned counsel for the respondent/ Promoter

submitted that the complaint for compensation was filed by the appellant on

29.11.2019 i.e., after 1 year and 7 months of taking possession and after 2

years and 6 months after commencement of the Act in respect of a Project for

which Completion Certificate was issued on 26.02.2014, i.e.3 years and 3

months prior to commencement of the Act. Such an attempt would amount to

giving retrospective operation to the provisions of the Act in respect of

concluded past transactions, contrary to the spirit and intent of the

Legislation in Sec.3 of the RERA Act and therefore, according to the learned

counsel for the respondent/ Promoter, the complaint of the appellant for

compensation is not maintainable.

4.5. Moreover, the learned counsel for respondent / Promoter

______________

https://www.mhc.tn.gov.in/judis

submitted that the allegation made by the appellant that the Completion

Certificate is a false document, merely on the basis that the delivery of

possession was given on 24.02.2018 is unsustainable in law. The parameters

and criteria for issuance of 'Competition Certificate' are totally different from

the parameters for the issuance of 'Occupancy Certificate'. Therefore,

according to the learned counsel for the respondent/Promoter, the handing

over of possession does not have any significance with regard to the

exemption from Registration of Projects for which Completion Certificate

has been issued on the date of commencement of the Act. In view of the

same, the order passed by the Tamil Nadu Real Estate Appellate Tribunal,

Chennai dated 07.03.2022 in Appeal No.103 of 2021 on the file of TNREAT,

by reversing the order dated 30.03.2020 passed in CCP No.30 of 2020 on

the file of TNRERA, Chennai is a well – reasoned order and the same does

not seek the interference of this Court and accordingly, prayed for dismissing

the appeal.

5. Heard the learned counsel for the appellant as well as the respondent

and perused the materials placed before this Court.

______________

https://www.mhc.tn.gov.in/judis

6. Perusal of records would reveal that the learned Adjudicating

officer, TNRERA, Chennai, vide order dated 30.03.2021 has directed the

respondent/ Promoter to deposit a sum of Rs.7,90,000/- to the credit of

Appeal No.103 of 2021 on the file of Tamil Nadu Real Estate Appellate

Tribunal, Chennai. When this matter was taken up for hearing, this Court had

granted an interim order of Status Quo, dated 15.06.2022, in C.M.P.No.9256

of 2022 with an observation that the respondent/ Promoter shall not

withdraw the aforesaid amount which was earlier deposited to the credit of

Appeal No.103 of 2021 on the file of Tamil Nadu Real Estate Appellate

Tribunal, Chennai till the disposal of this Appeal and framed the following

substantial questions of law.

(i) Whether a letter issued by President of Panchayat will be equivalent to a Completion Certificate as contemplated under Sec.2(h)(ii) of TN RERA Act?

(ii) Whether a certificate issued by an incompetent person other than CMDA will amount to a completion certificate as defined under Sec.2(h)(ii) of TNRERA Act?

(iii) Whether the Tribunal is correct in holding that the

______________

https://www.mhc.tn.gov.in/judis

TNRERA Act is not applicable to the appellant's case, when the building and the amenities of the gated community were not completed by the builder, even after TNRERA Act came into force and therefore the Act was applicable?

(iv) Whether the statutory mandate of getting completion certificate be waived by the issuance of a mere letter by Panchayat, especially when the actual project completion was delayed by more than 4 years after 2014 and the entire gated community with amenities were not handed over by the Builder until 2018 as per the project plan?

(v) Whether the Appellate Tribunal, in the absence of material evidence hold that an ongoing project as completed and thereby take way a builder from the purview of the RERA Act, which is applicable to ongoing projects on the date of the introduction of the Act and also deprive the compensation to an affected buyer for the delayed handover?

7. Questions (i), (ii) & (iii): For the purpose of answering these

issues, it would be appropriate to extract Sec.2(h)(ii) &(iii) of TN RERA Act

and the same reads as under:-

“Section 2: Definitions

______________

https://www.mhc.tn.gov.in/judis

(h) “Ongoing project” means, a project where development is going on and for which completion certificate has not been issued but excludes such projects which fulfill any of the following criteria on the date of coming into force of sub-section (1) of section 3 of the Act:-

(i) ...

(ii) the projects in Chennai Metropolitan Area for which application for completion certificate has been filed with Chennai Metropolitan Development Authority subject to furnishing certificate from the architect/licensed surveyor/ structural engineer associated with the project to the effect that all the buildings in the projects have been structurally completed i.e. all the columns, beams and slabs have been erected supported with photographs. Chennai Metropolitan Development Authority will issue, completion certificate for those projects in compliance with Completion Certificate norms prescribed. In Completion Certificate filed cases, if the Completion Certificate is rejected by Chennai Metropolitan Development Authority for violation of norms, such projects will be intimated to the Real Estate Regulatory Authority and will be bound for registration with Real Estate Regulatory Authority. The details of all projects where Completion Certificate application has been filed with

______________

https://www.mhc.tn.gov.in/judis

Chennai Metropolitan Development Authority prior to notification of these rules will be disclosed to the public by publishing the list of all such projects on the website of Chennai Metropolitan Development Authority and Real Estate Regulatory Authority immediately after notification of these rules.”

(iii) in the case of projects under execution outside Chennai Metropolitan Area, as no provision and procedure has yet been prescribed for issue of completion certificate, if the construction is structurally completed meaning that all the columns, beams and slabs have been erected and certified by the architect or structural engineer/licensed surveyor associated with the project supported with photographs. Such projects shall be intimated to the concerned Local Planning Authority or Regional Deputy Director of the Town and Country Planning Department within 15 days from the date of notification of these rules with a copy marked to the office of the Director of Town and Country Planning. The Director of Town and Country Planning will make public the list of all such projects in his official website, on the 16th day of notification of the rules besides publication of the same in the website of Real Estate Regulatory Authority.”

______________

https://www.mhc.tn.gov.in/judis

(a) First and foremost, it can be inferred that the completion certificate

obtained by the respondent/ Promoter from Thaiyur Panchayat on 26.02.2014

cannot be considered as a valid completion certificate, since at that point of

time, the construction of the subject building was not completed and the

respondent/ Promoter himself has requested the buyers through an email,

dated 26.10.2015 stating that they would regret for the inconvenience caused

to the buyers with regard to the delay incurred in completing the Project and

has rescheduled the dates of completion and also vide the same email, has

revised the compensation amount for 1 BHK, 2BHK & 3BHK as Rs.5,000/-,

Rs.7,500/- & Rs/10,000/- per month post the revised timeline.

(b) Obviously, this would suffice answering the issues in favour of the

appellant, since the handing over of the building was made only on

24.02.2018 and handing over of the amenities mentioned by the

respondent/Promoter was made only on 26.01.2021 with a long delay of

nearly 4 years and 7 years respectively from 30.04.2014, which is the actual

date of handing over as stated by the respondent/ Promoter.

______________

https://www.mhc.tn.gov.in/judis

(c) Moreover, in the above said clause 2(h) (ii) of the TN RERA Act,

the competent Authority to issue Completion Certificate will be the Chennai

Metropolitan Development Authority. For projects under execution outside

Chennai Metropolitan Area, as no such provision and procedure are

prescribed for issue of completion certificate yet, such projects shall be

intimated to the concerned Local Planning Authority or Regional Deputy

Director of the Town and Country Planning Department within 15 days from

the date of notification of these rules with a copy marked to the office of the

Director of Town and Country Planning. After which, the Director of Town

and Country Planning will make public the list of all such projects in his

official website, on the 16th day of notification of the rules besides

publication of the same in the website of Real Estate Regulatory Authority.

Since no such procedures were found to be followed in the respondent/

Promoter's case, the Project “January” is concluded only to be 'an ongoing

project', which would fall under the provisions of the TN RERA Act.

Accordingly, Issues (i), (ii) & (iii) are answered in favour of the appellant.

______________

https://www.mhc.tn.gov.in/judis

8. Question no.(iv): When Section 2(h) (ii) of the TN RERA Act is

read in consonance with Section 11 (4)(b) of the RERA Act, which states

that it is the duty of the promoter to obtain the completion certificate or the

occupancy certificate, or both, as applicable, from the relevant competent

authority as per local laws or other laws for the time being in force and to

make it available to the allottees individually or to the association of

allottees, as the case may be. In the present case on hand, as obtaining

completion certificate is not a discretionary but a mandatory one as per the

provisions mandated under the TNRERA Act, the same cannot be waived by

any other similar letter issued by the Panchayat under the guise of alleged

completion. Hence, Question (iv) is answered in favour of the appellant.

9. Question no.(v): From the submissions made by the learned counsel

appearing on either side as well as the perusal of the material evidences

submitted before this Court, this Court is of the considered opinion that the

project 'January' of the respondent/ promoter is an ongoing project and it

definitely falls under the provisions of the TN RERA Act. Therefore, the

______________

https://www.mhc.tn.gov.in/judis

respondent/ Promoter cannot evade from paying compensation to the

appellant for delayed handover as ordered by the learned Adjudicating

Officer,TNRERA, Chennai vide order dated 30.03.2020 passed in CCP

No.30 of 2020. Accordingly, the Question no.(v) is also answered in favour

of the appellant.

10. In the result,

(i) This Civil Miscellaneous Second Appeal stands Allowed;

(ii) The order passed by the Tamil Nadu Real Estate Appellate Tribunal, Chennai dated 07.03.2022 in Appeal No.103 of 2021 is hereby setaside and the order passed by the learned Adjudicating Officer,TNRERA, Chennai vide order dated 30.03.2020 passed in CCP No.30 of 2020 is upheld; and

(iii) The compensation awarded to the appellant by the learned Adjudicating Officer,TNRERA, Chennai vide order dated 30.03.2020 passed in CCP No.30 of 2020 stands confirmed. No costs. Consequently, connected miscellaneous petition stands closed.





                   ______________



https://www.mhc.tn.gov.in/judis



                                      (J.N.B.J)       (R.S.V.J)
                                           10.01.2025




                   ______________



https://www.mhc.tn.gov.in/judis



                                                    J.NISHA BANU, J.
                                                               and
                                                    R.SAKTHIVEL, J.




                                                                          sts
                   Internet : Yes/No
                   Index: Yes/No
                   Speaking Order: Yes/No

                   sts



                   To:

                   The Tamil Nadu Real
                    Estate Appellate Tribunal,
                   Chennai.



                                                     Judgment made in





                                                                Dated:
                                                            10.01.2025



                   ______________



https://www.mhc.tn.gov.in/judis

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 

LatestLaws Partner Event : IJJ

 
 
Latestlaws Newsletter