Citation : 2025 Latest Caselaw 5548 Mad
Judgement Date : 26 August, 2025
Arb.O.P. (Com.Div.) No.98 of 2023
IN THE HIGH COURT OF JUDICATURE AT MADRAS
Reserved on : 12.08.2025
Pronounced on : 26.08.2025
CORAM:
THE HON'BLE MR. JUSTICE ABDUL QUDDHOSE
Arb.O.P. (Com.Div.) No.98 of 2023
M/s. CHENNAI METROPOLITAN WATER
SUPPLY AND SEWERAGE BOARD,
Rep. by its Superintending Engineer /
Assistant Contracts Engineer,
No.1, Pumping Station Road,
Chintadripet,
Chennai - 600 002. ... Petitioner
Vs.
1. M/s.GKC VISHWA CONSORTIUM,
Rep. by its Authorized Signatory,
Sy. No.9(P), CII Green Building Lane,
Hi-Tech City, Kondapur,
Hyderabad - 500 084.
2. ICICI Bank Ltd.,
Rep. by its Branch Manager,
Commercial Building Level - 1, West Wing,
1-11-256, Wall Street Plaza,
Begumpet, Hyderabad - 500 016.
1/36
https://www.mhc.tn.gov.in/judis ( Uploaded on: 26/08/2025 02:58:02 pm )
Arb.O.P. (Com.Div.) No.98 of 2023
3. IDBI Bank Ltd.,
Rep. by its Branch Manager,
Hyderabad Main Road,
5-9-89/1, Chapel Road,
Post Box No.370,
Hyderabad - 500 001. ... Respondents
Prayer: Petition filed under Section 34 of the Arbitration and
Conciliation Act, 1996 to set aside the arbitral award dated 25.03.2022
passed by the Sole arbitrator to the extent to which it is challenged and to
direct the respondents to pay the costs.
For Petitioner : Mr.Gautam S. Raman
For Respondents : Mr.Satish Parasaran,
Senior Counsel,
for P.J. Rishikesh for R1
ORDER
This petition has been filed under Section 34 of the Arbitration and
Conciliation Act, 1996, challenging the impugned arbitral award dated
25.03.2022. The petitioner is the respondent and the first respondent is
the claimant in the arbitration. The arbitral Tribunal under the impugned
arbitral award dated 25.03.2022 has allowed the claim of the first
respondent against the petitioner to the tune of Rs.33,87,43,444/- and has
denied the counter claim of the petitioner made against the first
respondent to the tune of Rs.57,35,03,000/-. Aggrieved by the same, the
https://www.mhc.tn.gov.in/judis ( Uploaded on: 26/08/2025 02:58:02 pm ) Arb.O.P. (Com.Div.) No.98 of 2023
petitioner has filed this petition under Section 34 of the Arbitration and
Conciliation Act, 1996.
2. The petitioner is the employer and the first respondent is the
contractor, who was awarded the contract by the petitioner for "providing
comprehensive water supply scheme to Manapakkam, Nandambakkam,
Okiyam Thuraipakkam, Ramapuram and providing comprehensive
underground sewerage scheme to Ramapuram". This scheme has been
taken up by the petitioner Board under the Chennai Mega City
Development Mission Fund at an estimated cost of Rs.143.96 crores
under 5 schemes.
3. The petitioner has challenged the impugned arbitral award on
the following grounds:
a) The arbitrator has erroneously awarded loss of profit of
Rs.5,99,56,072/- in favour of the first respondent. According to the
petitioner, by total non application of mind to the fact that the first
respondent was the one, who approached the petitioner for extension of
time for completing the said contract and having stopped work since
https://www.mhc.tn.gov.in/judis ( Uploaded on: 26/08/2025 02:58:02 pm ) Arb.O.P. (Com.Div.) No.98 of 2023
2018, even after granting extension of time by them till 31.03.2019, was
alone responsible for the breach of contract, for which the petitioner
cannot be penalised, by directing them to pay damages by way of loss of
profit for a huge sum of Rs.5,99,56,072/- to the first respondent;
b) Stoppage of work by the first respondent lead to termination of
contract by the petitioner. According to the petitioner, the first
respondent had completely stopped work from April, 2018 onwards,
because of which, the petitioner was forced to terminate the contract as
there was fundamental breach committed by the first respondent;
c) The impugned arbitral award passed in favour of the first
respondent, declaring that the termination of the contract made by the
petitioner is void, despite the first respondent stopping work from April,
2018 onwards, is not only perverse but also patently illegal;
d) The arbitrator did not consider the fact that the first respondent
did not have the financial means to perform the contract, as their lead
partner was facing CIRP proceedings under the provisions of the
Insolvency and Bankruptcy Code, 2016 (In short 'IBC'). Therefore, the
termination of the contract by the petitioner can never be declared to be
illegal;
https://www.mhc.tn.gov.in/judis ( Uploaded on: 26/08/2025 02:58:02 pm ) Arb.O.P. (Com.Div.) No.98 of 2023
e) Time is the essence of the contract. Since the first respondent
had sought for various extensions of time over and above the contractual
period, which was also granted by the petitioner till 31.03.2019, there
was no breach of contract committed by the petitioner. According to the
petitioner, the first respondent has stopped work from April, 2018
onwards and the extensions cannot be granted by the petitioner for an
indefinite period;
f) Liquidated damages can be levied without proving actual loss.
According to the petitioner, the arbitrator has erroneously held that for
levying liquidated damages, the petitioner did not prove the actual
damages suffered by them and therefore, the first respondent is entitled
for the recovery of the liquidated damages adjusted by the petitioner
from and out of the first respondent's bills. According to the petitioner,
for levying liquidated damages, actual loss need not be proved as per
Section 74 of the Indian Contract Act, 1872;
g) An insolvent entity cannot be allowed to legally continue with
the arbitral proceedings. According to the petitioner, a consortium
agreement was executed on 05.01.2013 between GKC Projects Limited
and Vishwa Infrastructures and Services Pvt. Ltd. and the said
https://www.mhc.tn.gov.in/judis ( Uploaded on: 26/08/2025 02:58:02 pm ) Arb.O.P. (Com.Div.) No.98 of 2023
consortium was named as GKC Vishwa Consortium, the first respondent
herein. The lead partner is GKC Projects Ltd. According to the
petitioner, the arbitrator failed to take note of the fact that the insolvency
proceeding under Section 7 of the IBC was initiated against GKC
Projects Ltd., which is the lead partner of the first respondent. According
to the petitioner, the arbitrator also failed to take note of the fact that the
lead partner was placed under CIRP and put in moratorium as per
Section 14 of the IBC. Since the moratorium order has been passed under
Section 14 of the IBC against the lead partner of the first respondent, the
institution of suits or continuation of pending suits or proceedings
against the Corporate Debtor in any Court of Law, Tribunal, arbitration
panel or other authority is prohibited. However, according to the
petitioner, in the case on hand, the arbitrator has erroneously encouraged
the first respondent, whose lead partner was in moratorium to continue
with the arbitral proceedings and therefore, the arbitral proceedings is
non est in law.
4. The learned counsel for the petitioner, in support of the
petitioner's contentions, relied upon the following authorities:
https://www.mhc.tn.gov.in/judis ( Uploaded on: 26/08/2025 02:58:02 pm ) Arb.O.P. (Com.Div.) No.98 of 2023
a) Batliboi Environmental Engineers Ltd. Vs. Hindustan Petroleum Corporation Ltd. and Another reported in 2024 (2) SCC 375;
b) Colles Cranes of India Ltd. Vs. Speedeo Spares Corporation of India reported in 1969 SCC Online 40;
c) Cotton Corporation of India Ltd. Vs. M/s.Ramkumar Mills Pvt. Ltd. reported in 2008 SCC Online Bom 488;
d) ONGC Ltd. Vs. Saw Pipes Ltd., reported in 2003 (5) SCC 705;
e) K.S. Oils Ltd. Vs. State Trade Corporation of India Ltd. reported in 2018 (146) SCL 588.
5. Relying upon the aforesaid decisions, the learned counsel for
the petitioner would submit as follows:
a) The first respondent, who has claimed loss of profit due to delay
in execution of work, must prove that other works were lost due to the
said delay;
c) For levying liquidated damages, actual loss need not be proved
as per Section 74 of the Indian Contract Act, 1872;
b) Section 46 of the Indian Contract Act, 1872 stipulates that the
promise must be performed within a reasonable time. The time was fixed,
https://www.mhc.tn.gov.in/judis ( Uploaded on: 26/08/2025 02:58:02 pm ) Arb.O.P. (Com.Div.) No.98 of 2023
but, the promisee extended the time. The extensions could not go on
indefinitely, even by applying the doctrine of reasonable time. The
promise could terminate the contract after certain extensions;
d) The moratorium order passed by the National Company Law
Tribunal (NCLT) under Section 14 of the IBC will apply to proceeding
in any other law for time being in force, including the Arbitration and
Conciliation Act, 1996.
6. On the other hand, the learned senior counsel appearing for the
first respondent, after drawing the attention of this Court to the impugned
arbitral award, would submit as follows:
a) The impugned arbitral award is reasonable and fair. The award
passed by the arbitrator is not exaggerated or unwarranted. Only based
on the oral and documentary evidence submitted by both the parties, the
impugned arbitral award came to be passed;
b) Most of the delays were caused solely by the petitioner, which
has been extensively discussed by the arbitrator in the impugned arbitral
award;
c) A categorical finding has been rendered by the arbitrator that
https://www.mhc.tn.gov.in/judis ( Uploaded on: 26/08/2025 02:58:02 pm ) Arb.O.P. (Com.Div.) No.98 of 2023
the petitioner failed to handover the work fronts to the first respondent,
thereby preventing the first respondent from proceeding with the works
in various sections;
d) Even if there was any delay on the part of the first respondent,
the same was condoned by the petitioner through the grant of extensions;
e) The arbitrator has clearly given a finding that there was delay on
the part of the petitioner in certifying the bills and making payments to
the first respondent, which resulted in severe financial difficulties for the
first respondent;
f) The arbitrator has also given a finding based on the evidence
with regard to the contributory factors for the delay viz., stoppage of
work due to pending Court cases, assembly elections, and the effects of
governmental decisions such as demonetization, all of which, adversely
impacted the performance of the contract;
g) The arbitrator has rightly relied upon Section 55 of the Indian
Contract Act, 1872 for coming to the conclusion that the time was not the
essence of the contract, given that the delay events were attributable to
the petitioner. Therefore, according to the first respondent, levy of
liquidated damages by the petitioner against the first respondent was
https://www.mhc.tn.gov.in/judis ( Uploaded on: 26/08/2025 02:58:02 pm ) Arb.O.P. (Com.Div.) No.98 of 2023
rightly found to be unjustified by the arbitrator;
h) Additionally, the arbitrator cited Section 74 of the Indian
Contract Act, 1872 that the petitioner has neither suffered any legal
injury nor incurred any actual monetary loss that would justify the
imposition of liquidated damages;
i) The arbitrator has rightly held that the delay was attributable to
the petitioner and has rightly declared the termination of the contract to
be illegal and has rightly awarded the first respondent with loss of profit
amounting to 10% of the total value of the works;
j) The petitioner failed to demonstrate any specific loss resulting
from the alleged delay on the part of the first respondent. The same is
also recorded by the arbitrator in the impugned arbitral award;
k) Inspite of the contract having been terminated by the petitioner
in the month of November, 2018 itself, the petitioner till date has been
unable to complete the works even when the award was passed on
25.03.2022, and the same is also captured in the impugned arbitral
award. This would mean that inspite of the termination of the contract,
the pending works could not be completed by the petitioner and this
would show that the constraints and hindrances continued and the
https://www.mhc.tn.gov.in/judis ( Uploaded on: 26/08/2025 02:58:02 pm ) Arb.O.P. (Com.Div.) No.98 of 2023
petitioner alone is to be held responsible for the same;
l) The petitioner has not challenged the dismissal of the counter
claim, which is with respect to risk and cost and this would mean that
they have indirectly admitted that the termination is illegal and void;
m) The moratorium under Section 14 of the IBC applied only to
one consortium member and bars proceedings against the corporate
debtor, not arbitral proceeding initiated by the Corporate Debtor. The
lead partner of the petitioner has not been declared as an insolvent but
only a new investor has taken over its management, and it remains a
going concern. No relief on this issue was sought or pressed by the
petitioner before the arbitrator;
n) Section 14 (1) (a) of the IBC restricts only debt recovery action
that may affect a corporate debtor's assets. Arbitration proceedings
initiated by the corporate debtor are outside the scope of Section 14 (1)
(a) of the IBC.
DISCUSSION:
7. As seen from the impugned arbitral award, the claims that were
allowed and the claims that were rejected by the arbitrator are detailed
hereunder:
https://www.mhc.tn.gov.in/judis ( Uploaded on: 26/08/2025 02:58:02 pm ) Arb.O.P. (Com.Div.) No.98 of 2023
Claim Nature of Claim Claim Awarded / No. Amount in Rejected Rs.
1. To declare the termination of the contract by 5,99,56,072 Awarded the petitioner as null and void and consequently, award a sum of Rs.5,99,56,072/- in favour of the first respondent.
2. To direct the petitioner to make payment 2,29,10,164 Rejected towards the compensation on account of deployment of additional machinery and equipment beyond the original schedule.
3.a. To direct the petitioner to make payment 3,41,95,291 Rejected towards compensation on account of deployment of additional manpower beyond the original schedule of contract.
3.b. To direct the petitioner to make payment 80,37,099 Rejected towards compensation on account of administrative costs incurred due to delay on the part of the petitioner.
3.c. To direct the petitioner to make payment 1,07,02,351 Rejected towards compensation on account of BG/ Insurance charges incurred beyond the original schedule.
3.d. To direct the petitioner to make payment 1,00,63,757 Rejected towards compensation on account of other miscellaneous costs (Head Office Overheads) incurred beyond the original schedule 4 To direct the petitioner to make payment 8,25,76,612 Rejected towards compensation on account of other financing costs due to negative cash flows during the original schedule 5 To direct the petitioner to make payment 11,90,37,26 Awarded towards the compensation on account of 4 outstanding dues against interim payments 6 To direct the petitioner to make payment 2,58,26,833 Awarded towards Retention monies 7 To direct the petitioner to make payment 1,02,55,864 Awarded towards the amount withheld on GST from
https://www.mhc.tn.gov.in/judis ( Uploaded on: 26/08/2025 02:58:02 pm ) Arb.O.P. (Com.Div.) No.98 of 2023
Claim Nature of Claim Claim Awarded / No. Amount in Rejected Rs.
8 To direct the petitioner to make payment 2,02,00,000 Awarded towards the liquidated damages 9 To direct the petitioner to make payment 1,62,04,547 Awarded towards compensation towards interest charges on delayed payments on interim bills amounting to Rs.2,11,02,417/- together with interest at the rate of 9% p.a. for the delayed payment of RA Bills (Except Bill Nos.10 and
12) 10 To direct the petitioner to make payment 4,30,00,000 Awarded towards refund of recovered amount towards material advance 11 To direct the petitioner to return the 2,40,07,000 Awarded performance Bank Guarantee 12 Interest for the outstanding amounts payable Partly by the petitioner under claim Nos.1 to 10. Awarded Interest at the rate of 10% p.a. of award from 05.07.2019 till the date of the passing of the award 13 Costs towards arbitration and other litigation Rejected expenses
8. The following are the undisputed facts:
a) The contract entered into between the petitioner and the first
respondent permits the petitioner to grant extension of time to the first
respondent to complete the contract;
b) The following extensions were granted by the petitioner to the
first respondent and the said extensions were also marked as exhibits as
detailed hereunder:
https://www.mhc.tn.gov.in/judis ( Uploaded on: 26/08/2025 02:58:02 pm ) Arb.O.P. (Com.Div.) No.98 of 2023
S. Name of Schedule Extension Reference to No. Scheme Date of granted Exhibits Completion upto 1 Ramapuram 19.08.2016 18.05.2018 Ex.C18 (letters UGSS dated 18.05.2015, 12.11.2015), Ex.C27, C28, C32 2 Ramapuram 19.02.2016 31.03.2019 Ex.C18 (letters WSY Scheme dated 18.05.2015, 12.11.2015), C22, C23, C29, C31, C32, C33 3 Manapakkam 19.02.2016 31.03.2019 Ex.C18 (letters WSY Scheme dated 18.05.2015, 12.11.2015), C22, C23, C31, C32, C33 4 Okkiam 19.02.2016 31.03.2019 Ex.C18 (letters Thoraipakka dated 18.05.2015, m WSY 12.11.2015), C22, Scheme C23, C30, C32, C33 5 Nandambakk 19.08.2015 31.05.2018 Ex.C18 (letters am WSY dated 18.05.2015, Scheme 12.11.2015), C22, C24, C25, C26 6 31.03.2019 Ex.C6
c) The delay on the part of the petitioner in certifying the bills,
which have been disclosed by the arbitrator in the impugned arbitral
award in paragraph No.128 has not been disputed by the petitioner. It is
once again reproduced by this Court in this order:
https://www.mhc.tn.gov.in/judis ( Uploaded on: 26/08/2025 02:58:02 pm ) Arb.O.P. (Com.Div.) No.98 of 2023
R.A. Date of Particular Bill No. Submission of Net Value of Due date as Certified on Delay in Bill Bill in Rs. per contract days 1 31.10.2013 117,600,000 14.11.2013 05.01.2014 52 2 10.09.2014 6,481,145 24.09.2014 09.10.2014 15 3 09.03.2015 6,719,812 23.03.2015 11.05.2015 49 4 30.03.2015 17,884,162 13.04.2015 15.07.2015 93 5 18.08.2015 28,476,048 01.09.2015 12.10.2015 41 6 05.10.2015 25,130,978 19.10.2015 02.02.2016 106 7 16.11.2015 4,423,336 30.11.2015 29.03.2016 120 8 15.02.2016 15,507,692 29.01.2016 29.06.2016 121 9 08.03.2016 19,237,971 22.03.2016 31.08.2016 162 10 07.04.2016 57,448,415 21.04.2016 25.10.2016 187 11 06.05.2016 24,426,923 19.12.2016 02.03.2017 286 12 09.03.2017 15,201,706 23.03.2017 25.05.2017 63 13 06.04.2017 7,189,618 20.04.2017 21.06.2017 62 14 29.06.2017 20,765,703 13.07.2017 30.11.2017 140 15 26.10.2017 14,323,918 09.11.2017 13.03.2018 124 16 26.10.2017 28,248,166 09.11.2017 13.06.2018 216 17 06.06.2018 40,057,259 20.06.2018 24.06.2019 369
d) As seen from the aforesaid tabular column, there was a delay on
the part of the petitioner in certifying the bills and making payments to
the first respondent, which has also been reproduced by the arbitrator in
paragraph No.129 of the impugned arbitral award, and the same has also
not been disputed by the petitioner.
e) The last extension of time granted by the petitioner through the
petitioner's letter dated 01.06.2018 (Ex. C6) granted extension of time
upto 31.03.2019. But, even before the expiry date of the said extension,
https://www.mhc.tn.gov.in/judis ( Uploaded on: 26/08/2025 02:58:02 pm ) Arb.O.P. (Com.Div.) No.98 of 2023
the petitioner through its communication dated 10.11.2018 (Ex.C13) has
terminated the contract awarded to the respondent;
9) The petitioner contends that the arbitrator under the impugned
arbitral award has failed to take note of the fact that time was the essence
of the contract awarded to the first respondent. The arbitrator under the
impugned arbitral award, after giving due consideration to the evidence,
more particularly, the various extensions granted by the petitioner for
various reasons has held that time was not the essence of the contract and
the said finding was rendered only after taking into consideration the
ratio laid down by various decisions rendered by the Constitutional
Courts.
10. In Mc. Dermott International INC Vs. Burn Standard Co. Ltd
[2006 (11) SCC 181], the Hon'ble Supreme Court held that it is normal
for the parties to proclaim that "time is the essence of the contract", but,
in actual practice, it is not so. The case on hand is also one such case.
Mere words in the contract that time is the essence of the contract are not
enough to prove that “time is the essence of the contract”. The conduct
https://www.mhc.tn.gov.in/judis ( Uploaded on: 26/08/2025 02:58:02 pm ) Arb.O.P. (Com.Div.) No.98 of 2023
of the parties plays a pivotal role to decide whether time is the essence of
the contract.
11. The Honourable Supreme Court in its judgment rendered in the
case of Welspun Speciality Solutions Ltd. Vs. Oil and Natural Gas
Corporation reported in 2021 SCC Online SC 1053 has reiterated the
principles for deciding whether time is the essence of the contract. The
Honourable Supreme Court held that collective reading of the entire
contract and its surrounding circumstances is imperative to decide
whether "time is the essence of the contract". The arbitrator under the
impugned arbitral award has followed the aforesaid decision of the
Honourable Supreme Court for coming to the conclusion that based on
the evidence placed on record which includes the extensions granted to
the petitioner by the first respondent that "time was not the essence of the
contract".
12. The Honourable Supreme Court in the aforesaid decision
concurred with the arbitral Tribunal's conclusion that the existence of
extension clauses has diluted the employers clause that time was the
https://www.mhc.tn.gov.in/judis ( Uploaded on: 26/08/2025 02:58:02 pm ) Arb.O.P. (Com.Div.) No.98 of 2023
essence of the contract.
13. The arbitrator has rightly appreciated the evidence placed on
record before him which includes various extensions granted by the
petitioner in favour of the first respondent for completing the project and
has come to the right conclusion that time was not the essence of the
contract and has rightly partly allowed various claims made by the first
respondent and has also rejected the counter-claim of the petitioner.
14. The view taken by the arbitrator under the impugned arbitral
award is reasonable, plausible and has to be sustained. The arbitrator has
rightly held, based on the evidence available on record, that the time was
not the essence of the contract if the contract provides for extension of
time as well as liquidated damages. Once the petitioner has waived the
claim for liquidated damages in the earlier extensions issued by the
petitioner, the petitioner cannot claim liquidated damages for further
extensions.
https://www.mhc.tn.gov.in/judis ( Uploaded on: 26/08/2025 02:58:02 pm ) Arb.O.P. (Com.Div.) No.98 of 2023
15. In Welspun Speciality Solutions Ltd. case referred to supra,
the Honourable Supreme Court has also observed that the Court should
not interfere or set aside awards in a casual manner. While doing so, the
Court should come to a clear understanding that the award is patently
illegal. In the case on hand, eventhough the contract was extended by the
petitioner in favour of the first respondent through the petitioner's letter
dated 01.06.2018, marked as Ex.C6, which gets expired only on
31.03.2019, the petitioner had terminated the contract even before the
expiry date through the petitioner's communication dated 10.11.2018
(Ex.C13).
16. The petitioner contends that the first respondent had
completely stopped the work which forced the petitioner to terminate the
contract even before the deadline fixed under the letter of extension
dated 01.06.2018 (Ex.C6) granted to the first respondent which is
31.03.2019.
https://www.mhc.tn.gov.in/judis ( Uploaded on: 26/08/2025 02:58:02 pm ) Arb.O.P. (Com.Div.) No.98 of 2023
17. The Honourable Supreme Court in Welspun Speciality
Solutions Ltd. case referred to supra, also observed as follows:
a) Subject to the nature of the contract, the promissor is bound to
complete the obligation by the date for completion stated in the contract;
b) The same is subject to the exception that the promissee is not
entitled to the liquidated damages, if the promisee's own act or omission,
the promissor was prevented from completing the work before the
completion date;
c) It must be culled out from the reading of the entire contract as
well as the surrounding circumstances as to whether time is the essence
of the contract and nearly having explicit clauses to these things may be
sufficient.
18. In the case on hand, on account of the various extensions
granted by the petitioner to the first respondent for completing the
contract and on account of the fact that there was a delay on the part of
the petitioner in certifying the bills of the first respondent in settling their
dues, the arbitrator has rightly come to the finding that time was not the
essence of the contract. The arbitrator has rightly held that merely having
https://www.mhc.tn.gov.in/judis ( Uploaded on: 26/08/2025 02:58:02 pm ) Arb.O.P. (Com.Div.) No.98 of 2023
an explicit clause in the contract that "time is the essence of the contract"
is not sufficient to conclude that time is the essence of the contract as it
depended upon other surrounding circumstances and the conduct of the
parties. The conduct of the petitioner in granting several extensions to
the first respondent for completing the project makes it clear that time
was not the essence of the contract as rightly held by the arbitrator in the
impugned arbitral award.
19. Section 55 of the Indian Contract Act deals with failure to
perform the contract within the agreed time in the event, time is of the
essence, and the failure to perform an obligation within the stipulated
time renders the contract voidable at the option of the innocent party. In
such a case, the innocent party is entitled to (a) terminate performance of
the contract; and (b) claim damages from the breaching party on the basis
that it has committed the fundamental breach of the contract. However,
inspite of avoiding the contract, if the innocent party accepts to hold the
performance of the contract, it may not claim compensation for any loss
occasioned by the non performance of the contract at the time granted,
unless, at the time of such acceptance, he gives notice to the promissor of
https://www.mhc.tn.gov.in/judis ( Uploaded on: 26/08/2025 02:58:02 pm ) Arb.O.P. (Com.Div.) No.98 of 2023
his intention to do so.
20. In the case on hand, as observed earlier, the conduct of the
petitioner in granting extension of time to the first respondent for various
reasons not attributable to the first respondent will lead to the conclusion
that time was not the essence of the contract and the petitioner had
committed breach of the contract. In order to signify time as the essence
of the contract, there must be a specific and fixed date within which the
extended performance of the obligation has to be effected, failing which,
it has to be held that the parties themselves by their conduct have waived
the original terms of the contract, more particularly in respect of the time
being the essence of the contract.
21. Sections 73 and 74 of the Contract Act deal with the law of
damages in India. Section 73 provides for actual damages suffered by a
party in the usual course (unliquidated damages). Section 74 applies
wherein the same has been specified in the contract which is a genuine
estimate of the loss agreed by the parties.
https://www.mhc.tn.gov.in/judis ( Uploaded on: 26/08/2025 02:58:02 pm ) Arb.O.P. (Com.Div.) No.98 of 2023
22. Most of the delays were caused solely by the petitioner. The
delays caused by the petitioner has been extensively discussed by the
arbitrator in the impugned arbitral award. The arbitrator has given
adequate reasons in the impugned arbitral award for arriving at a finding
that the amount of Rs.2,02,00,000/- levied on the first respondent as
adhoc liquidated damages is unjustified. The arbitrator has thereafter
directed the return of the adhoc liquidated damages amounting to
Rs.2,02,00,000/- to the first respondent adjusted by the petitioner
erroneously without justification. The reasons given for arriving at such a
finding by the arbitrator are as follows:
a) The petitioner has to prove that it had suffered loss or legal
injury due to the breach of contract alleged to have been committed by
the first respondent, which they have failed.
b) The petitioner has not even pleaded that loss has been caused to
the petitioner for the purpose of levying liquidated damages on the first
respondent;
c) A party claiming compensation has to show that quantified
amount of loss has been caused due to act or omission of the other party;
d) In the case on hand, the petitioner has not shown with sufficient
https://www.mhc.tn.gov.in/judis ( Uploaded on: 26/08/2025 02:58:02 pm ) Arb.O.P. (Com.Div.) No.98 of 2023
evidence that loss has been caused to them due to the delay caused by the
first respondent in executing the work;
e) The levy of liquidated damages by the petitioner will amount to
unjust enrichment at the cost the first respondent;
f) Several authorities on the subject of levy of liquidated damages
listed out in the impugned arbitral award have also been considered by
the arbitrator for coming to the conclusion that the amount of
Rs.2,02,00,000/- levied by the petitioner against the first respondent
towards adhoc liquidated damages is unjust;
g) The petitioner has not satisfied the requirements of Section 74
of the Indian Contract Act, 1872 for the levy of liquidated damages on
the first respondent.
23. The above findings were given by the arbitrator only based on
the evidence placed on record before him by both the parties to the
dispute. This Court does not find any infirmity in the findings of the
arbitrator, who has rightly held that the levy of liquidated damages by the
petitioner is unjustified.
https://www.mhc.tn.gov.in/judis ( Uploaded on: 26/08/2025 02:58:02 pm ) Arb.O.P. (Com.Div.) No.98 of 2023
24. The Arbitrator has rightly held that the termination of the
contract by the petitioner is invalid as the petitioner was responsible for
the first respondent in not proceeding with the work due to the delay on
the part of the petitioner in certifying the bills payable to the first
respondent and for the delay in making payments to the first respondent
for the said bills. The Arbitrator has given proper and valid reasons for
adjudicating various claims made by the first respondent as well as the
counter-claim made by the petitioner.
25. Most of the delays were caused solely by the petitioner on
account of the delay in certifying the bills, delay in making payments and
the delay in handing over the land; and only due to the same, the first
respondent was unable to complete the project. The Arbitrator has
rendered findings with regard to each of the claims made by the first
respondent as well as the counter-claim made by the petitioner only
based on the evidence available on record.
26. The Arbitrator has rightly found that the termination of the
https://www.mhc.tn.gov.in/judis ( Uploaded on: 26/08/2025 02:58:02 pm ) Arb.O.P. (Com.Div.) No.98 of 2023
contract dated 10.11.2018 made by the petitioner terminating the contract
of the first respondent is void. The Arbitrator has rightly allowed the
claim of the first respondent for a sum of Rs.5,99,56,072/- towards the
loss of profit. The first respondent is entitled for the said sum, since the
work could not be completed only due to the fault of the petitioner. The
first respondent in the normal course of its business would have earned a
minimum profit of 10% on the total value of the contract. The Arbitrator
has rightly followed the decision of the Hon'ble Supreme Court in the
case of A.T.Brij Pant Singh (cited supra) and K.Baskaran (cited supra),
wherein the Hon'ble Supreme Court had granted compensation towards
loss of profit at 10% on the total contract value in identical
circumstances. Therefore, this Court does not find any infirmity in the
award passed by the Arbitrator with regard to claim No.1 made by the
first respondent.
27. The Arbitrator has rightly rejected claim Nos.2, 3(a), 3(b), 3(c),
3(d) and 4. The said claims pertain to; (a) compensation on account of
deployment of additional machinery and equipment beyond the original
schedule of the contract; (b) compensation on account of deployment of
https://www.mhc.tn.gov.in/judis ( Uploaded on: 26/08/2025 02:58:02 pm ) Arb.O.P. (Com.Div.) No.98 of 2023
additional manpower beyond the original schedule of the contract; (c)
compensation on account of administrative costs incurred due to the
delay on the part of the petitioner; (d) compensation on account of
BG/insurance charges incurred beyond the original schedule of the
contract; (e) compensation on account of other miscellaneous costs
(Head office overheads) incurred beyond the original schedule of the
contract; and (f) compensation on account of other financing costs due to
negative cash flows during the original schedule of the contract.
28. In respect of claim No.5, the Arbitrator has rightly awarded a
sum of Rs.11,90,37,264/- in favour of the first respondent. The
Arbitrator has rightly found the following while adjudicating claim
No.5:-
(a) The claim made by the first respondent for a sum of
Rs.3,82,57,706/- towards payment of RA bill No.7 has been admitted by
the petitioner in their statement of defence dated 30.10.2019.
(b) The petitioner has also admitted a sum of Rs.3,46,55,564/- in
their statement of defence. Though the said sum for the unbilled and
executed works, the petitioner is liable to pay the said sum to the first
https://www.mhc.tn.gov.in/judis ( Uploaded on: 26/08/2025 02:58:02 pm ) Arb.O.P. (Com.Div.) No.98 of 2023
respondent.
(c) The commissioning of the project could not take place only due
to the improper termination of the contract by the petitioner. Hence, a
sum of Rs.4,61,23,994/-, which was withheld by the petitioner from RA
bill Nos.1 to 16, should be paid to the first respondent.
29. The findings rendered by the Arbitrator for claim No.6 made
by the first respondent against the petitioner cannot be faulted with as
those findings are based on the evidence placed on record. The
Arbitrator while adjudicating claim No.6 made by the first respondent
has rightly determined that a sum of Rs.2,58,26,833/- was erroneously
withheld by the petitioner as retention money from RA bill Nos.1 to 16.
The Arbitrator for coming to such a finding with regard to claim No.6
has taken into consideration the admission made by the petitioner in its
statement of defence. Therefore, the Arbitrator has rightly directed the
petitioner to pay the said sum of Rs.2,58,26,833/- to the first respondent.
30. The Arbitrator has rightly given a finding that the petitioner
https://www.mhc.tn.gov.in/judis ( Uploaded on: 26/08/2025 02:58:02 pm ) Arb.O.P. (Com.Div.) No.98 of 2023
has falsely withheld the payment of Rs.1,02,55,864/- towards GST from
RA bill Nos.15 and 16 of the first respondent. The Arbitrator has rightly
taken into consideration the admission made by the petitioner in their
statement of defence filed before the Arbitrator for awarding a sum of
Rs.1,02,55,864/- in favour of the first respondent in respect of claim
No.7.
31. In respect of claim No.8, the Arbitrator has rightly awarded a
sum of Rs.2,02,00,000/- to the first respondent, which is the amount
withheld by the petitioner as liquidated damages. The Arbitrator has
rightly found that withholding of the liquidated damages is invalid, since
the first respondent is not responsible for the delay in completing the
project. The first respondent having produced evidence before the
Arbitrator that the petitioner was responsible for the delay in completing
the project, the Arbitrator was right in directing the petitioner to return a
sum of Rs.2,02,00,000/- falsely withheld by them by way of liquidated
damages.
32. In respect of claim No.9 made by the first respondent, the
https://www.mhc.tn.gov.in/judis ( Uploaded on: 26/08/2025 02:58:02 pm ) Arb.O.P. (Com.Div.) No.98 of 2023
Arbitrator has rightly awarded a sum of Rs.1,62,04,547/- in favour of the
petitioner for the delayed payment of RA bills (except bill Nos.10 to 12)
in favour of the first respondent, though awarding interest at the rate of
9% per annum instead of 13.5% per annum claimed by the first
respondent. Admittedly, there were delays on the part of the petitioner in
making payments to the first respondent under RA bills raised by the first
respondent. Therefore, this Court does not find any infirmity in the
finding of the Arbitrator in respect of claim No.9 made by the first
respondent.
33. Claim No.10 was made by the first respondent seeking refund
of the Material Bank Guarantee amounting to Rs.4,30,00,000/-. The
Arbitrator has rightly held that since the termination of the contract by
the petitioner is invalid and the evidence placed on record also proves
that the materials had been used by the first respondent at the work site,
the first respondent is entitled for the fund of Material Bank Guarantee
amounting to Rs.4,30,00,000/-.
34. Claim No.11 was made by the first respondent seeking refund
https://www.mhc.tn.gov.in/judis ( Uploaded on: 26/08/2025 02:58:02 pm ) Arb.O.P. (Com.Div.) No.98 of 2023
of the Performance Bank Guarantee furnished by the first respondent to
the tune of Rs.2,40,07,000/-. The Arbitrator has rightly held that the first
respondent is entitled to the refund of the said amount, since the
termination of the contract made by the petitioner is invalid.
35. In respect of claim No.12, the interest awarded by the
Arbitrator at the rate of 10% per annum on the determined amount from
the date of filing of the claim statement before the Arbitrator, i.e., on
05.07.2019, till the date of the passing of the award, is also proper, and
this Court does not find any infirmity in the said finding, since the
petitioner has wrongfully terminated the contract awarded to the first
respondent.
36. Since only based on the evidence available on record, the
Arbitrator has rightly held that the termination of the contract made by
the petitioner is invalid, the question of awarding counter-claim in favour
of the petitioner does not arise. The Arbitrator has rightly rejected the
counter-claim made by the petitioner against the first respondent in the
arbitration.
https://www.mhc.tn.gov.in/judis ( Uploaded on: 26/08/2025 02:58:02 pm ) Arb.O.P. (Com.Div.) No.98 of 2023
37. Section 14 of the IBC Insolvency and Bankruptcy Code, 2016,
does not bar the proceedings initiated by the corporate debtor. The
Insolvency and Bankruptcy Code, 2016, is a beneficial legislation, which
endeavours to revive the corporate debtors and ensures that the corporate
debtor continues as a going concern during the insolvency process. The
moratorium imposed in terms of Section 14 of the Code does not in any
express terms apply to proceedings which are to the benefit of corporate
debtors. The entire object, purpose and import of Section 14 is to protect
and preserve the assets of the corporate debtor during the resolution
process by halting the proceedings initiated against the corporate debtor,
which may result in depreciation or alienation of the assets of the
corporate debtor. Section 14 does not in any express terms impinges
upon or halts proceedings initiated by the corporate debtor which result
in appreciation of its assets or its enrichment. The aforesaid scheme of
the act is discernible from various provisions of the Insolvency and
Bankruptcy Code. Therefore, the contention of the petitioner that since
the lead partner of the petitioner "GKC Projects Ltd." was facing CIRP
proceedings and on account of the passing of the moratorium order, the
https://www.mhc.tn.gov.in/judis ( Uploaded on: 26/08/2025 02:58:02 pm ) Arb.O.P. (Com.Div.) No.98 of 2023
arbitral award passed in favour of the first respondent is in violation of
Section 14 of the IBC, has to be rejected by this Court.
38. The decisions relied upon by the learned counsel for the
petitioner referred to in paragraph No.4 of this order have also got no
bearing to the facts of the instant case for the following reasons:-
(a) Since the termination of the contract by the petitioner is
invalid, the first respondent is entitled for the loss of profit at 10% on the
total value of the contract as held by the Hon'ble Supreme Court in
A.T.Brij Pant Singh (cited supra).
(b) In the case on hand, the first respondent has proved through
oral and documentary evidence that the petitioner had erroneously
terminated the contract even before the deadline fixed under the earlier
extension and the Arbitrator has also rightly given a finding that the
termination of the contract by the petitioner is invalid. Therefore, since
the termination of the contract is found to be invalid, the question of levy
of liquidated damages by the petitioner does not arise. Therefore, no
amount of money can be retained by the petitioner, which is due and
payable to the first respondent as per the contract.
https://www.mhc.tn.gov.in/judis ( Uploaded on: 26/08/2025 02:58:02 pm ) Arb.O.P. (Com.Div.) No.98 of 2023
(c) Time was not the essence of the contract in view of several
extensions granted by the petitioner in favour of the first respondent for
completing the project. Once extensions have been granted, Section 46
of the Indian Contract Act relied upon by the learned counsel for the
petitioner does not arise.
(d) The moratorium order passed by the NCLT under Section 14 of
the IBC will not apply to the proceedings initiated by the corporate
debtor for the recovery of money against its debtors.
(e) The scope of Section 34 of the Arbitration and Conciliation Act
is limited. Only in cases where the award has been passed in violation of
public policy and the arbitral award suffers from patent illegality or it
falls under the various other grounds mentioned in Section 34 of the
Arbitration and Conciliation Act, the question of interfering with the
arbitral award does not arise.
39. Only based on the evidence available on record, the Arbitrator
has passed the impugned arbitral award in favour of the first respondent
and the Arbitrator has rightly rejected the counter-claim made by the
petitioner against the first respondent. This Court does not find any
https://www.mhc.tn.gov.in/judis ( Uploaded on: 26/08/2025 02:58:02 pm ) Arb.O.P. (Com.Div.) No.98 of 2023
infirmity in the findings rendered by the Arbitrator. The law is well
settled that this court cannot re-appreciate the evidence and if the view
taken by the Arbitrator is a plausible view, this Court cannot interfere
with the arbitral award. In the result, there is no merit in this petition and
accordingly, this petition is dismissed. No Costs.
26.08.2025
Index: Yes Speaking order Neutral citation : Yes ab
https://www.mhc.tn.gov.in/judis ( Uploaded on: 26/08/2025 02:58:02 pm ) Arb.O.P. (Com.Div.) No.98 of 2023
ABDUL QUDDHOSE, J.
ab
Pre-delivery order in Arb.O.P. (Com.Div.) No.98 of 2023
26.08.2025
https://www.mhc.tn.gov.in/judis ( Uploaded on: 26/08/2025 02:58:02 pm )
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!