Citation : 2024 Latest Caselaw 18793 Mad
Judgement Date : 25 September, 2024
C.M.P.(MD) No.1855 of 2023
BEFORE THE MADURAI BENCH OF MADRAS HIGH COURT
DATED : 25.09.2024
CORAM
THE HON'BLE MR.JUSTICE SUNDER MOHAN
C.M.P.(MD) No.1855 of 2023
in
C.M.A. (MD) SR. No.66899 of 2022
The Project Director,
National Highways No.45E & 220,
National Highways Authority of India
having his office at Plot No.3,
Suriya Towers, 2nd Floor, 1st East Street,
K.K.Nagar (Near Dr.Muthuvelrajan Hospital)
Madurai - 625 020.
Presently at:-
Plot No.1, Aishwaryam Heights,
Indira Nagar, 1st Street
Sennamanaickenpatti (PO),
Thadikombu Road,
Dindigul – 624 004. ... Petitioner/Appellant
Vs.
1.K.Renuga
W/o.S.Kayambu
2.The Special District Revenue Officer/
Competent Authority for Land Acquisition,
(National Highways - 45E & 220),
Collectorate Buildings,
Theni. ... Respondents/Respondents
_____________
https://www.mhc.tn.gov.in/judis
Page No. 1 of 8
C.M.P.(MD) No.1855 of 2023
Prayer in C.M.P.(MD) No.1855 of 2023: Civil Miscellaneous Petition
filed under Section 5 of the Limitation Act, 1963, to condone the delay of
563 days in filing the above C.M.A.(MD) SR.No.66899 of 2022.
Prayer in C.M.A.(MD) SR.No.66899 of 2022: Civil Miscellaneous
Appeal filed under Section 37(1) & (2) of the Arbitration and Conciliation
Act, 1996, to call for the records and set aside the order made in
Arbitration O.P.No.47 of 2016 dated 07.01.2019 on the file of the
Principal District and Sessions Judge, Theni.
For Petitioner/Appellant : Mr.P.Karthick
For R1/R1 : Mr.R.Govindaraj
For R2/R2 : Mr.M.Muthumanikkam
Government Advocate
ORDER
This petition has been filed to condone the delay of 563 days in
filing the above appeal.
2. In the affidavit filed in support of this petition, the petitioner has
primarily stated that the learned Principal District and Sessions Judge had
modified the award passed by the learned arbitrator by reappraising the
evidence, which is impermissible under Section 34 of the Arbitration and
_____________ https://www.mhc.tn.gov.in/judis
Conciliation Act, 1996; that they have a fair chance of success in the
appeal; that the delay occurred due to the transfer of case files from the
Project Implementation Unit (PIU) in Madurai, which was earlier
handling the case, to the PIU in Dindigul, which was formed on
22.01.2018; that there was no full time Director in PIU, Dindigul; and that
therefore, sufficient cause was shown for condonation of delay.
3. The first respondent filed a counter opposing the petition, stating
that the petitioner has not given sufficient cause for the delay. The learned
counsel for the first respondent submitted that the Hon'ble Supreme Court
in Government of Maharashtra (Water Resources Department)
represented by Executive Engineer Vs. Borse Brothers Engineers and
Contractors Private Limited, reported in (2021) 6 SCC 460, held that the
objective of the Act is for speedy disposal of the case, and therefore, the
time limit prescribed under the Act has to be strictly complied with, and
that the delay can be condoned only in exceptional circumstances; and
that this Court, by an order dated 27.08.2024, dismissed C.M.P.(MD) No.
11260 of 2023 in C.M.A.(MD) SR.No.25399 of 2023 filed by the
appellant to condone the delay of 950 days mentioning the same reasons.
_____________ https://www.mhc.tn.gov.in/judis
4. This Court has given its anxious consideration to the pleading
and the submissions made by the learned counsel on either side.
5. This petition for condonation of delay has been filed primarily on
the ground that the order passed by the learned Principal District and
Session Judge is illegal inasmuch as the learned Judge has reappraised the
evidence and modified the award, which is contrary to the settled position
of law. The other reasons given by the petitioner are found in paragraph
17 of the affidavit, which reads as follows:
“17.It is respectfully submitted that the impugned order was passed by the Lower Court on 07.01.2019 and the said order was made ready on 13.03.2019 and received by the PIU 14.03.2019. It is submitted that while the case was pending before the District Court, the Highways project was within the authority of Project Director of PIU, Madurai. In the meanwhile, the Dindigul Project Implementation Unit of NHAI was carved out Madurai PIU of NHAI and came into being w.e.f. 22.01.2018. The files pertaining to newly related Dindigul Unit was received from Madurai PIU in different dates of February 2018. It is further submitted for some period, as the post of Project Director Dindigul was vacant, it was looked after by the Project Director of Nagercoil as additional charge from 22.01.2018 to 01.09.2020. Full time Project Director was appointed to the newly carved out office for PIU, Dindigul wef 02.09.2020. Similarly, the (southern) Regional Officer of NHAI post at Madurai was also
_____________ https://www.mhc.tn.gov.in/judis
vacant from 26.04.2019 to 23.08.2021. Due to all these reasons, the appeals could not be filed by the Petitioner/Appellant immediately within the prescribed period of limitation.”
6. The question in the instant petition is not whether the order
passed by the learned District and Sessions Judge, Theni, impugned in the
above C.M.A is illegal. The question is whether the petitioner has shown
sufficient cause for filing the above appeal with a huge delay of 563 days.
7. The Hon'ble Supreme Court in Borse Brothers Engineers and
Contractors Private Limited case, referred to supra, held as follows:
“63. Given the aforesaid and the object of speedy disposal sought to be achieved both under the Arbitration Act and the Commercial Courts Act, for appeals filed under Section 37 of the Arbitration Act that are governed by Articles 116 and 117 of the Limitation Act or Section 13(1-A) of the Commercial Courts Act, a delay beyond 90 days, 30 days or 60 days, respectively, is to be condoned by way of exception and not by way of rule. In a fit case in which a party has otherwise acted bona fide and not in a negligent manner, a short delay beyond such period can, in the discretion of the court, be condoned, always bearing in mind that the other side of the picture is that the opposite party may have acquired both in equity and justice, what may now be lost by the first party's inaction, negligence or laches.”
_____________ https://www.mhc.tn.gov.in/judis
8. From the above observations, it is clear that the delay in filing an
appeal under Section 37 of the Arbitration and Conciliation Act, 1996 can
be condoned only by way of an exception and not by way of rule. This
Court is of the view that the reason given by the petitioner for the delay,
which is extracted above in the paragraph 5 of this order, does not come
under the exceptional circumstances warranting the condonation of delay.
In any case, it is well settled that the administrative delay cannot be a
ground for condonation of delay.
9. The learned counsel on either side cited Judgments of the
Division Bench of this Court, wherein, in some cases, the delays were
condoned and, in others, the delay petitions were dismissed. This Court, in
the order dated 27.08.2024 passed in C.M.P.(MD) No.11260 of 2023 in
C.M.A. (MD) SR.No.25399 of 2023, has discussed those Judgments and
held that whether sufficient cause is shown or not would depend on the
facts and circumstances of each case. Since sufficient cause has not been
shown, this petition is liable to be dismissed.
_____________ https://www.mhc.tn.gov.in/judis
10. Accordingly, this Civil Miscellaneous Petition is dismissed. No
costs. Consequently, the C.M.A. stands rejected at the S.R. stage itself.
25.09.2024 Index: Yes/ No Neutral Citation: Yes / No Speaking Order / Non-Speaking Order
JEN
Copy To:
The Principal District and Sessions Judge, Theni, Theni District.
_____________ https://www.mhc.tn.gov.in/judis
SUNDER MOHAN, J.
JEN
in C.M.A. (MD) SR. No.66899 of 2022
25.09.2024
_____________ https://www.mhc.tn.gov.in/judis
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!